Archive 72A73 / 21
Archive 72A73 / 20
Archive 72A73 / 19
Archive 72A73 / 18
Archive 72A73 / 17
Archive 72A73 / 16
Archive 72A73 / 15
Archive 72A73 / 14
Archive 72A73 / 13
Archive 72A73 / 12
Archive 72A73 / 11
Archive 72A73 / 10
Archive 72A73 / 09
Archive 72A73 / 08
Archive 72A73 / 07
Archive 72A73 / 06
Archive 72A73 / 05
Archive 72A73 / 04
Archive 72A73 / 03
Archive 72A73 / 02
Archive 72A73 / 01
Archive 72A73 / 00
|
State of Illinois
Department of Transportation
Current Report
| DOT Vendor: |
C53100 |
|
Contract: |
72A73 |
| Route: |
FAP 662 |
|
From Date: |
10/22/2012 |
| Section: |
H(RS-10,B-2) |
To Date: |
12/04/2012
|
| Project: |
BRF-0662/065/ |
State Job: |
C-96-073-09 |
| Letting Date: |
09/17/2010 |
|
Dist/Cnty: |
06 - 167
(SANGAMON ) |
|
|
|
|
|
|
Payee: |
REYHAN BROTHERS INC D/B/A
|
|
|
|
|
2100 E MOFFAT AVE
|
|
|
|
|
SPRINGFIELD , IL 62702
|
|
|
Contract Awarded
Amount |
Additions |
Deductions |
Total Adjusted
Contract Value |
Total Amount
Due to Date |
| 3,266,501.05 |
172,169.90 |
278,297.52 |
3,160,373.44 |
3,160,373.44 |
|
Total retainage incld this est held by IDOT:
|
|
|
0.00 |
| Total due after retainage: |
|
|
3,160,373.44 |
| Total
paid this estimate: |
|
|
3,160,373.44 |
|
Previous payments to contractor: |
|
|
-3,155,343.03 |
|
Payment to contractor this estimate: |
|
| 5,030.41 |
| |
|
Voucher # CC10547 | Date: 12/05/2012 |
|
1
of 1
|
5,030.41 |
|
---------------------------------------------------------------------------------------------------------------------------------------------- |
|
|
|
Pay Estimate Number: 22 |
Total: |
5,030.41 |
Report of Resident Engineer
Completed Work-In Place
For This Estimate Only
|
|
|
PAY ITEM |
QUANTITY |
PAYMENT |
|
Number |
Description |
Awarded |
Net of Adds/
Deducts |
Total Adjusted |
Completed Prior Est. |
Completed to Date |
This Estimate |
$ Unit Price |
$ This Estimate |
| 67000400 |
ENGR FIELD OFFICE A |
12.000 |
0.000 |
12.000 |
11.000 |
12.000 |
1.000 |
1,485.33 |
1,485.33 |
| 70106800 |
CHANGEABLE MESSAGE SN |
12.000 |
0.000 |
12.000 |
11.000 |
12.000 |
1.000 |
2,002.44 |
2,002.44 |
| 78000300 |
THPL PVT MK LINE 5 |
15,807.000 |
3,086.000 |
18,893.000 |
18,101.000 |
18,893.000 |
792.000 |
0.49 |
388.08 |
| FRC01200 |
ADJ GUARDRAIL POST(SLE |
0.000 |
515.240 |
515.240 |
512.240 |
515.240 |
3.000 |
1.00 |
3.00 |
| XXX99300 |
BIT PRICE ADJ INC |
0.000 |
12,459.090 |
12,459.090 |
11,999.190 |
12,459.090 |
459.900 |
1.00 |
459.90 |
| X9600900 |
THPL PVT MK LTR & SYMB |
0.000 |
96.200 |
96.200 |
22.000 |
96.200 |
74.200 |
8.40 |
623.28 |
| X96015A0 |
URETHANE PVT MK LINE 6 |
0.000 |
1,096.000 |
1,096.000 |
1,070.000 |
1,096.000 |
26.000 |
2.63 |
68.38 |
|
Total: |
$5,030.41 |
|