Invoice Archive
Contract Number
&
Estimate Numbers are listed below
Please note:
All estimates are listed. Credit invoices are not processed
for payment, however, they are provided for access to pay items which
may be new or reduced work in place for the estimate.
Archive 63578 / 03
Archive 63578 / 02
Archive 63578 / 01
|
State of Illinois
Department of Transportation
Current Report
| DOT Vendor: |
C36570 |
|
Contract: |
63578 |
| Route: |
RIDGE FIELD |
|
From Date: |
02/08/2012 |
| Section: |
00-C2000-03-BT |
To Date: |
05/14/2012
|
| Project: |
CMM-9003/680/000 |
State Job: |
C-91-711-10 |
| Letting Date: |
06/17/2011 |
|
Dist/Cnty: |
01 - 111
(MCHENRY ) |
|
|
|
|
|
|
Payee: |
MANEVAL CONSTRUCTION CO INC
|
|
|
|
|
1015 N CORPORATE CIRCLE STE D
|
|
|
|
|
GRAYSLAKE , IL 60030
|
|
|
Contract Awarded
Amount |
Additions |
Deductions |
Total Adjusted
Contract Value |
Total Amount
Due to Date |
| 320,036.58 |
5,124.57 |
63,181.02 |
261,980.13 |
261,980.13 |
|
Total retainage incld this est held by IDOT:
|
|
|
0.00 |
| Total due after retainage: |
|
|
261,980.13 |
| Total
paid this estimate: |
|
|
261,980.13 |
|
Previous payments to contractor: |
|
|
-253,161.91 |
|
Payment to contractor this estimate: |
|
| 8,818.22 |
| |
|
Voucher # CC06599 | Date: 10/15/2012 |
|
1
of 1
|
8,818.22 |
|
---------------------------------------------------------------------------------------------------------------------------------------------- |
|
|
|
Pay Estimate Number: 04 |
Total: |
8,818.22 |
Report of Resident Engineer
Completed Work-In Place
For This Estimate Only
|
|
|
PAY ITEM |
QUANTITY |
PAYMENT |
|
Number |
Description |
Awarded |
Net of Adds/
Deducts |
Total Adjusted |
Completed Prior Est. |
Completed to Date |
This Estimate |
$ Unit Price |
$ This Estimate |
| 21001000 |
GEOTECH FAB F/GR STAB |
6,404.000 |
454.200 |
6,858.200 |
6,404.000 |
6,858.200 |
454.200 |
0.89 |
404.24 |
| 21101505 |
TOPSOIL EXC & PLAC |
1,405.000 |
72.800 |
1,477.800 |
1,405.000 |
1,477.800 |
72.800 |
10.50 |
764.40 |
| 40603310 |
HMA SC "C" N50 |
652.000 |
-36.790 |
615.210 |
534.970 |
615.210 |
80.240 |
78.41 |
6,291.62 |
| 42400200 |
PC CONC SIDEWALK 5 |
1,380.000 |
81.800 |
1,461.800 |
1,380.000 |
1,461.800 |
81.800 |
4.67 |
382.01 |
| 44000600 |
SIDEWALK REM |
384.000 |
162.000 |
546.000 |
384.000 |
546.000 |
162.000 |
2.36 |
382.32 |
| 78000100 |
THPL PVT MK LTR & SYM |
180.000 |
74.700 |
254.700 |
180.000 |
254.700 |
74.700 |
7.35 |
549.05 |
| 78001100 |
PT PVT MK LTRS & SYMB |
105.000 |
14.400 |
119.400 |
105.000 |
119.400 |
14.400 |
2.84 |
40.90 |
| 78300100 |
PAVT MARKING REMOVAL |
14.000 |
0.700 |
14.700 |
14.000 |
14.700 |
0.700 |
5.25 |
3.68 |
|
Total: |
$8,818.22 |
|
Return to the IDOT Home Page
|