State of Illinois Department of Transportation

Contract Search

 06/13/2013 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 10/03/2012
DOT Vendor: C63100  Contract: 95679 

IL Project:      From Date: 08/10/2012
Route: TR 282
Section: 07-05136-00-BR To Date: 10/03/2012
Project: BR0S-0029/293/000 State Job: C-97-046-12
Letting Date: 06/15/2012 Dist/Cnty: 07 - 029 (COLES )
Airport: 07-05136-00-BR State Job: C-97-046-12
Scope: 3.2 MILES SOUTHEAST OF HUTTON OVER STREAM

Payee:

A J WALKER CONSTRUCTION CO 421 S 21ST ST P O BOX 118  MATTOON , IL  61938

 

 

 

 

Percent Completed:  75.97%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
158,454.85      0.00      0.00      158,454.85      121,273.80     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 121,273.80     
Mobilzation Paid:900.00     
Total paid this estimate:   121,273.80     
     Previous payments to contractor: -4,500.00     
     Payment to contractor this estimate: 116,773.80     
 
          Voucher #   CC06246 Date: 10/05/2012 1 of 1 116,773.80     

----------------------------------------------------------------------------------------------------------------------------------------------     

Includes 15% mobilization Pay Estimate Number:  01 Total: 116,773.80     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
20100500  TREE REMOV ACRES   0.030  0.000  0.030  0.000  0.030  0.030  55,240.00  1,657.20 
20300100  CHANNEL EXCAVATION   230.000  0.000  230.000  0.000  230.000  230.000  16.58  3,813.40 
28100107  STONE RIPRAP CL A4   300.000  0.000  300.000  0.000  300.000  300.000  47.54  14,262.00 
28200200  FILTER FABRIC   300.000  0.000  300.000  0.000  300.000  300.000  2.00  600.00 
50100100  REM EXIST STRUCT   1.000  0.000  1.000  0.000  1.000  1.000  9,692.00  9,692.00 
50200100  STRUCTURE EXCAVATION   120.000  0.000  120.000  0.000  120.000  120.000  10.00  1,200.00 
50300225  CONC STRUCT   22.400  0.000  22.400  0.000  17.400  17.400  650.00  11,310.00 
50300280  CONCRETE ENCASEMENT   3.500  0.000  3.500  0.000  3.500  3.500  600.00  2,100.00 
50400405  P P CONC DK BM 21 DP   1,253.000  0.000  1,253.000  0.000  1,253.000  1,253.000  40.00  50,120.00 
50800205  REINF BARS, EPOXY CTD   3,970.000  0.000  3,970.000  0.000  3,084.000  3,084.000  1.50  4,626.00 
51201400  FUR STL PILE HP10X42   160.000  0.000  160.000  0.000  160.000  160.000  58.02  9,283.20 
51202305  DRIVING PILES   160.000  0.000  160.000  0.000  160.000  160.000  0.00  0.00 
51203400  TEST PILE ST HP10X42   2.000  0.000  2.000  0.000  2.000  2.000  2,975.00  5,950.00 
59300100  CONTR LOW-STRENG MATL   36.300  0.000  36.300  0.000  9.000  9.000  65.00  585.00 
67100100  MOBILIZATION   1.000  0.000  1.000  0.750  0.900  0.150  6,000.00  900.00 
70101830  TRAF CONT-PROT BLR 21   1.000  0.000  1.000  0.000  0.450  0.450  1,500.00  675.00 
Total:   

$116,773.80

 