Contract Search

 07/31/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 11/07/2012
DOT Vendor: C31450  Contract: 95672 

IL Project:      From Date: 10/06/2012
Route: FAS 8526
Section: 10-00054-00-PV To Date: 11/07/2012
Project: M-5023/011/000 State Job: C-97-072-12
Letting Date: 04/27/2012 Dist/Cnty: 07 - 025 (CLAY )
Airport: 10-00054-00-PV State Job: C-97-072-12
Scope: 8TH STREET TO WEST NORTH AVENUE IN THE CITY OF FLORA

Payee:

KIEFFER BROTHERS CONST CO INC 118 N DIVISION ST  MT CARMEL , IL  62863

 

 

 

 

Percent Completed:  20.5%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
1,623,922.00      73,649.00      89,030.00      1,608,541.00      329,751.87     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 329,751.87     
Mobilzation Paid:6,689.85     
Total paid this estimate:   329,751.87     
     Previous payments to contractor: -121,713.67     
     Payment to contractor this estimate: 208,038.20     
 
          Voucher #   CC08874 Date: 11/09/2012 1 of 1 208,038.20     

----------------------------------------------------------------------------------------------------------------------------------------------     

Includes 15% mobilization Pay Estimate Number:  02 Total: 208,038.20     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
XX008653  PIPE TEE 36P 12R WMQ   1.000  0.000  1.000  0.000  1.000  1.000  6,055.00  6,055.00 
X0325323  MAN TA SAN 4 D T1F CL   1.000  0.000  1.000  0.000  1.000  1.000  2,240.00  2,240.00 
X0326713  SANITARY SEWER CONN   1.000  0.000  1.000  0.000  1.000  1.000  1,215.00  1,215.00 
X6022930  MAN TA 5 DIA SPL F&G   1.000  0.000  1.000  0.000  0.500  0.500  2,800.00  1,400.00 
X6024244  INLETS SPL N2   1.000  0.000  1.000  0.000  0.500  0.500  1,350.00  675.00 
X6024246  INLETS SPL N3   13.000  0.000  13.000  0.000  3.000  3.000  1,236.00  3,708.00 
X6029000  JUNCTION BOX   1.000  0.000  1.000  0.000  0.500  0.500  6,450.00  3,225.00 
X7010216  TRAF CONT & PROT SPL   1.000  0.000  1.000  0.000  0.410  0.410  14,680.00  6,018.80 
Z0056608  STORM SEW WM REQ 12   199.000  0.000  199.000  0.000  27.800  27.800  36.00  1,000.80 
Z0056622  STORM SEW WM REQ 36   21.000  0.000  21.000  0.000  21.000  21.000  225.00  4,725.00 
Z0056700  SAN SEW 4   61.000  0.000  61.000  12.000  61.000  49.000  37.00  1,813.00 
Z0056900  SAN SEW 8   60.000  0.000  60.000  0.000  60.000  60.000  160.00  9,600.00 
20800150  TRENCH BACKFILL   1,420.000  0.000  1,420.000  108.400  379.100  270.700  30.00  8,121.00 
40200800  AGG SURF CSE B   294.000  0.000  294.000  0.000  12.000  12.000  32.00  384.00 
42000800  HES PCC PVT 7   75.000  0.000  75.000  16.600  45.000  28.400  260.00  7,384.00 
44000100  PAVEMENT REM   6,860.000  0.000  6,860.000  17.600  57.600  40.000  6.70  268.00 
44000200  DRIVE PAVEMENT REM   372.000  0.000  372.000  0.000  94.000  94.000  8.25  775.50 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
44000500  COMB CURB GUTTER REM   286.000  0.000  286.000  0.000  35.000  35.000  5.00  175.00 
50105220  PIPE CULVERT REMOV   1,303.000  0.000  1,303.000  0.000  29.500  29.500  11.50  339.25 
550B0050  STORM SEW CL B 1 12   1,465.000  0.000  1,465.000  0.000  79.000  79.000  42.00  3,318.00 
550B0070  STORM SEW CL B 1 15   492.000  0.000  492.000  0.000  454.500  454.500  33.00  14,998.50 
550B0090  STORM SEW CL B 1 18   7.000  0.000  7.000  0.000  7.000  7.000  68.00  476.00 
550B0120  STORM SEW CL B 1 24   231.000  0.000  231.000  0.000  14.000  14.000  59.00  826.00 
550B0160  STORM SEW CL B 1 36   1,273.000  0.000  1,273.000  0.000  703.500  703.500  91.00  64,018.50 
55100700  STORM SEWER REM 15   617.000  0.000  617.000  0.000  214.000  214.000  13.00  2,782.00 
55100900  STORM SEWER REM 18   51.000  0.000  51.000  0.000  40.000  40.000  13.00  520.00 
55101200  STORM SEWER REM 24   2.000  0.000  2.000  0.000  2.000  2.000  27.00  54.00 
56300100  ADJ SAN SEWER 8 LESS   80.000  0.000  80.000  0.000  68.000  68.000  24.00  1,632.00 
59300100  CONTR LOW-STRENG MATL   93.000  0.000  93.000  25.000  51.500  26.500  124.00  3,286.00 
60221000  MAN TA 5 DIA T1F OL   5.000  0.000  5.000  0.000  0.500  0.500  2,925.00  1,462.50 
60236200  INLETS TA T8G   19.000  0.000  19.000  2.000  4.500  2.500  735.00  1,837.50 
60500060  REMOV INLETS   5.000  0.000  5.000  0.000  3.000  3.000  300.00  900.00 
60500090  REM INLET- MAIN FLOW   2.000  0.000  2.000  0.000  2.000  2.000  240.00  480.00 
67000500  ENGR FIELD OFFICE B   8.000  0.000  8.000  0.000  1.500  1.500  1,500.00  2,250.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
67100100  MOBILIZATION   1.000  0.000  1.000  0.750  0.900  0.150  44,599.00  6,689.85 
70102620  TR CONT & PROT 701501   1.000  0.000  1.000  0.000  1.000  1.000  9,755.00  9,755.00 
X9700104  PIPE TEE 36P 12R SPECI   0.000  25.000  25.000  0.000  13.000  13.000  2,000.00  26,000.00 
X9700105  PIPE TEE 36P 18R SPECI   0.000  1.000  1.000  0.000  1.000  1.000  2,250.00  2,250.00 
X9700106  CONDUIT BORED 2"   0.000  105.000  105.000  0.000  100.000  100.000  53.80  5,380.00 
Total:   

$208,038.20

 