State of Illinois Department of Transportation

Contract Search

 07/25/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 09/04/2012
DOT Vendor: C17700  Contract: 91468 

IL Project:      From Date: 06/07/2012
Route: LAKE OF THE WOODS
Section: 10-00026-00-BT To Date: 09/04/2012
Project: TE-00D5/098/000 State Job: C-95-315-12
Letting Date: 04/27/2012 Dist/Cnty: 05 - 019 (CHAMPAIGN )
Airport: 10-00026-00-BT State Job: C-95-315-12
Scope: BARBER PARK ON SOUTH MCDOUGAL ROAD TO THE FOREST PRESERVE
MAIN ENTRANCE ON LAKE OF THE WOODS ROAD

Payee:

FEUTZ CONTRACTORS INC 1120 N MAIN P O BOX 130  PARIS , IL  61944

 

 

 

 

Percent Completed:  51.9%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
398,768.60      0.00      0.00      398,768.60      209,126.90     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 209,126.90     
Mobilzation Paid:2,175.00     
Total paid this estimate:   209,126.90     
     Previous payments to contractor: -10,875.00     
     Payment to contractor this estimate: 198,251.90     
 
          Voucher #   CC06419 Date: 10/10/2012 1 of 1 198,251.90     

----------------------------------------------------------------------------------------------------------------------------------------------     

Includes 15% mobilization Pay Estimate Number:  01 Total: 198,251.90     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X4240440  PC CONC SIDEWALK 6 SP   1,875.000  0.000  1,875.000  0.000  1,875.000  1,875.000  4.50  8,437.50 
20100110  TREE REMOV 6-15   122.000  0.000  122.000  0.000  122.000  122.000  26.00  3,172.00 
20100210  TREE REMOV OVER 15   106.000  0.000  106.000  0.000  106.000  106.000  26.00  2,756.00 
20100500  TREE REMOV ACRES   0.200  0.000  0.200  0.000  0.200  0.200  8,300.00  1,660.00 
20200100  EARTH EXCAVATION   394.000  0.000  394.000  0.000  221.000  221.000  62.00  13,702.00 
20400800  FURNISHED EXCAVATION   452.000  0.000  452.000  0.000  452.000  452.000  25.00  11,300.00 
20800150  TRENCH BACKFILL   210.000  0.000  210.000  0.000  150.300  150.300  22.00  3,306.60 
28000400  PERIMETER EROS BAR   520.000  0.000  520.000  0.000  520.000  520.000  2.60  1,352.00 
28000500  INLET & PIPE PROTECT   12.000  0.000  12.000  0.000  8.000  8.000  190.00  1,520.00 
42400300  PC CONC SIDEWALK 6   33,284.000  0.000  33,284.000  0.000  19,897.000  19,897.000  4.00  79,588.00 
42400410  PC CONC SIDEWALK 8   4,838.000  0.000  4,838.000  0.000  3,665.800  3,665.800  5.00  18,329.00 
42400800  DETECTABLE WARNINGS   188.000  0.000  188.000  0.000  88.000  88.000  20.00  1,760.00 
44000100  PAVEMENT REM   1,551.000  0.000  1,551.000  0.000  1,080.100  1,080.100  8.00  8,640.80 
50105220  PIPE CULVERT REMOV   393.000  0.000  393.000  0.000  297.000  297.000  8.00  2,376.00 
542A0217  P CUL CL A 1 12   65.000  0.000  65.000  0.000  65.000  65.000  23.00  1,495.00 
542D0217  P CUL CL D 1 12   75.000  0.000  75.000  0.000  75.000  75.000  28.00  2,100.00 
542D0223  P CUL CL D 1 18   98.000  0.000  98.000  0.000  52.000  52.000  35.00  1,820.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
54213447  END SECTIONS 12   4.000  0.000  4.000  0.000  4.000  4.000  240.00  960.00 
54213453  END SECTIONS 18   4.000  0.000  4.000  0.000  2.000  2.000  265.00  530.00 
550A0070  STORM SEW CL A 1 15   767.000  0.000  767.000  0.000  705.000  705.000  28.00  19,740.00 
550A0360  STORM SEW CL A 2 15   148.000  0.000  148.000  0.000  144.000  144.000  28.00  4,032.00 
60221700  MAN TA 5 DIA T8G   1.000  0.000  1.000  0.000  1.000  1.000  2,700.00  2,700.00 
60240301  INLETS TB T8G   5.000  0.000  5.000  0.000  4.000  4.000  1,200.00  4,800.00 
67100100  MOBILIZATION   1.000  0.000  1.000  0.750  0.900  0.150  14,500.00  2,175.00 
Total:   

$198,251.90

 