 04/16/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 07/17/2013
DOT Vendor: C12840  Contract: 89525 

IL Project:      From Date: 06/05/2013
Route: FAU 6647
Section: 05-00302-01-PV To Date: 07/17/2013
Project: M-5093/137/000 State Job: C-94-103-09
Letting Date: 06/15/2012 Dist/Cnty: 04 - 143 (PEORIA )
Airport: 05-00302-01-PV State Job: C-94-103-09
Scope: FROM UNIVERSITY STREET TO SHERIDAN ROAD

Payee:

UNITED CONTRACTORS MIDWEST INC 3151 ROBBINS RD  SPRINGFIELD , IL  62704

 

 

 

 

Percent Completed:  15.63%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
2,997,498.96      184,941.69      173,259.31      3,009,181.34      470,324.10     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 470,324.10     
Mobilzation Paid:16,457.33     
Total paid this estimate:   470,324.10     
     Previous payments to contractor: -243,162.33     
     Payment to contractor this estimate: 227,161.77     
 
          Voucher #   CC01282 Date: 07/29/2013 1 of 1 227,161.77     

----------------------------------------------------------------------------------------------------------------------------------------------     

Includes 15% mobilization Pay Estimate Number:  06 Total: 227,161.77     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
XX000610  RELOCATE EX MAILBOX   14.000  0.000  14.000  0.000  7.000  7.000  527.48  3,692.36 
X5015225  PIPE CULVERT REM SPL   432.000  0.000  432.000  85.900  114.100  28.200  50.76  1,431.44 
X6020094  MAN TA 6D T1F CL R-P   1.000  0.000  1.000  0.000  0.500  0.500  8,043.00  4,021.50 
X6021065  INLETS TG-1 SPL   20.000  0.000  20.000  0.500  2.400  1.900  2,840.36  5,396.68 
X7010216  TRAF CONT & PROT SPL   1.000  0.000  1.000  0.650  0.700  0.050  30,003.75  1,500.19 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.630  0.700  0.070  17,367.00  1,215.69 
Z0056668  SS 2 WAT MN 12   363.000  0.000  363.000  0.000  48.000  48.000  57.75  2,772.00 
Z0056670  SS 2 WAT MN 18   118.000  0.000  118.000  0.000  114.400  114.400  80.85  9,249.24 
Z0056678  SS 2 WAT MN 36   86.000  0.000  86.000  0.000  29.600  29.600  224.96  6,658.82 
Z0076600  TRAINEES   1,000.000  0.000  1,000.000  0.000  75.000  75.000  0.80  60.00 
20800150  TRENCH BACKFILL   1,538.000  0.000  1,538.000  62.500  783.600  721.100  34.13  24,611.14 
28000305  TEMP DITCH CHECKS   192.000  0.000  192.000  28.000  111.700  83.700  16.84  1,409.51 
40201000  AGGREGATE-TEMP ACCESS   711.000  0.000  711.000  0.000  461.300  461.300  55.92  25,795.90 
44000100  PAVEMENT REM   7,294.000  0.000  7,294.000  0.000  3,636.000  3,636.000  8.89  32,324.04 
44000500  COMB CURB GUTTER REM   1,294.000  0.000  1,294.000  0.000  468.000  468.000  6.00  2,808.00 
44000600  SIDEWALK REM   484.000  0.000  484.000  0.000  250.000  250.000  1.58  395.00 
44003100  MEDIAN REMOVAL   1,831.000  0.000  1,831.000  0.000  1,647.900  1,647.900  2.35  3,872.57 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
5421D030  P CUL CL D 1 30 TEMP   20.000  0.000  20.000  0.000  12.500  12.500  142.72  1,784.00 
550A0450  STORM SEW CL A 2 36   808.000  0.000  808.000  0.000  474.200  474.200  97.65  46,305.63 
60223800  MAN TA 6 DIA T1F CL   12.000  0.000  12.000  0.000  4.800  4.800  5,092.50  24,444.00 
60236200  INLETS TA T8G   4.000  0.000  4.000  0.500  0.800  0.300  1,081.50  324.45 
60500060  REMOV INLETS   5.000  0.000  5.000  0.000  1.000  1.000  506.10  506.10 
67000400  ENGR FIELD OFFICE A   15.000  0.000  15.000  8.000  9.000  1.000  2,194.33  2,194.33 
67100100  MOBILIZATION   1.000  0.000  1.000  0.750  0.900  0.150  109,715.51  16,457.33 
X9400601  LTP A 40MH 15DA MO   0.000  3.000  3.000  0.000  3.000  3.000  2,082.41  6,247.23 
X9400602  BRWY DEV TR B 15BC MO   0.000  3.000  3.000  0.000  3.000  3.000  561.54  1,684.62 
Total:   

$227,161.77

 