State of Illinois Department of Transportation

Contract Search

 05/23/2013 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 08/14/2011
DOT Vendor: C27790  Contract: 85521 

IL Project:      From Date: 07/25/2011
Route: ROCKFORD RIVERWALK
Section: 06-00543-00-BT To Date: 08/14/2011
Project: TE-00D2/133/000 State Job: C-92-019-07
Letting Date: 01/21/2011 Dist/Cnty: 02 - 201 (WINNEBAGO )
Airport: 06-00543-00-BT State Job: C-92-019-07
Scope: WHITMAN STREET TO PARK AVENUE

Payee:

ILLINOIS CONSTRUCTORS CORP 39W866 FABYAN PARKWAY  ELBURN , IL  60119

 

 

 

 

Percent Completed:  27.47%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
5,440,640.60      38,243.50      4,031.25      5,474,852.85      1,503,974.11     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 1,503,974.11     
Total paid this estimate:   1,503,974.11     
     Previous payments to contractor: -1,291,946.20     
     Payment to contractor this estimate: 212,027.91     
 
          Voucher #   CC02757 Date: 08/17/2011 1 of 3 92,248.00     
          Voucher #   CC02762 Date: 08/17/2011 2 of 3 23,062.00     
          Voucher #   CC02746 Date: 08/17/2011 3 of 3 96,717.91     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  06 Total: 212,027.91     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
XX008423  PRECAST CONC LAGGING   1,616.000  0.000  1,616.000  0.000  896.000  896.000  25.00  22,400.00 
20200100  EARTH EXCAVATION   5,215.000  0.000  5,215.000  2,760.000  3,075.000  315.000  40.00  12,600.00 
50200100  STRUCTURE EXCAVATION   1,931.000  0.000  1,931.000  1,210.000  1,348.000  138.000  28.05  3,870.90 
50200450  REM/DISP UNS MATL-STR   100.000  0.000  100.000  0.000  10.300  10.300  48.00  494.40 
50300225  CONC STRUCT   814.400  0.000  814.400  0.000  177.400  177.400  650.00  115,310.00 
50300285  FORM LINER TEX SURF   7,648.000  0.000  7,648.000  0.000  2,785.000  2,785.000  11.00  30,635.00 
50500505  STUD SHEAR CONNECTORS   2,098.000  0.000  2,098.000  1,109.000  1,410.000  301.000  6.31  1,899.31 
50800205  REINF BARS, EPOXY CTD   69,316.000  0.000  69,316.000  2,580.000  21,671.000  19,091.000  1.30  24,818.30 
Total:   

$212,027.91

 