Illinois Department of Transportation, Ann L. Schneider, Secretary
Loading
Patrick J. Quinn, Governor
Traveling PublicMapsProjectsRoad ClosuresNewsDoing BusinessLetting & BiddingCareers@IDOTGeneral Info





State of Illinois Department of Transportation

Contract Search

 04/16/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 11/01/2013
DOT Vendor: C55500  Contract: 78172 

IL Project:      From Date: 10/16/2013
Route: FAI 57
Section: (41-2-1,41-3,41-3-1)R-1 To Date: 11/01/2013
Project: IM-057-2/155/091 State Job: C-99-027-10
Letting Date: 04/29/2011 Dist/Cnty: 09 - 081 (JEFFERSON )
Airport: (41-2-1,41-3,41-3-1)R-1 State Job: C-99-027-10
Scope: FAI-57, BEGINS @ S I57/64 TRI LEVEL & PROCEEDS N TO N I57/64
TRI LEVEL IN MT. VERNON.

Payee:

E T SIMONDS CONSTRUCTION CO PO BOX 2107  CARBONDALE , IL  62902

 

 

 

 

Percent Completed:  93.16%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
30,561,921.21      5,183,783.30      2,252,469.82      33,493,234.69      31,216,933.19     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 31,216,933.19     
Total paid this estimate:   31,216,933.19     
     Previous payments to contractor: -30,471,797.38     
     Payment to contractor this estimate: 745,135.81     
 
          Voucher #   CC08548 Date: 11/07/2013 1 of 1 745,135.81     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  52 Total: 745,135.81     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
XZ191203  BR DK MIC C OVL 2 3/4   1,642.000  0.000  1,642.000  836.000  876.000  40.000  62.76  2,510.40 
X3120005  STAB SUBBASE HMA VD   17,933.000  1,135.000  19,068.000  18,978.170  19,068.000  89.830  74.27  6,671.67 
X5030530  FLOOR DRAIN EXTENSION   24.000  0.000  24.000  8.000  16.000  8.000  583.25  4,666.00 
X7010216  TRAF CONT & PROT SPL   1.000  0.000  1.000  0.800  0.810  0.010  462,157.16  4,621.57 
X7830070  GRV RCSD PVT MRKG 5   83,882.000  0.000  83,882.000  46,422.000  64,287.000  17,865.000  0.50  8,932.50 
X7830074  GRV RCSD PVT MRKG 7   27,547.000  0.000  27,547.000  11,720.000  15,699.000  3,979.000  0.58  2,307.82 
X7830076  GRV RCSD PVT MRKG 9   7,207.000  0.000  7,207.000  3,215.000  6,618.000  3,403.000  0.95  3,232.85 
X8570000  SMART TRAF MONIT SYS   1.000  0.000  1.000  0.800  0.810  0.010  1,000,000.00  10,000.00 
Z0012130  BR DECK SCAR 3/4   1,642.000  0.000  1,642.000  1,232.800  1,641.700  408.900  38.04  15,554.56 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.770  0.780  0.010  150,000.00  1,500.00 
Z0030350  IMP ATTN REL NRD TL3   10.000  0.000  10.000  5.000  4.000  -1.000  678.73  -678.73 
20200100  EARTH EXCAVATION   48,118.000  0.000  48,118.000  45,357.400  47,357.400  2,000.000  12.34  24,680.00 
25000200  SEEDING CL 2   44.000  14.600  58.600  48.600  49.800  1.200  772.21  926.65 
25000500  PHOSPHORUS FERT NUTR   3,950.000  1,314.000  5,264.000  4,364.000  4,482.000  118.000  0.88  103.84 
25000600  POTASSIUM FERT NUTR   3,950.000  1,314.000  5,264.000  4,364.000  4,482.000  118.000  0.88  103.84 
28100707  STONE DUMP RIP CL A4   166.000  183.900  349.900  166.000  349.900  183.900  36.82  6,771.20 
40603575  P HMA SC "E" N105   29.000  182.120  211.120  131.580  193.220  61.640  419.99  25,888.19 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
42100340  CONT REINF PCC PVT 12   46,552.000  366.670  46,918.670  41,720.100  42,735.530  1,015.430  44.51  45,196.79 
42100615  PAVT REINFORCEMENT   146,644.000  0.000  146,644.000  139,785.790  140,801.220  1,015.430  20.55  20,867.09 
42101436  LUG SYSTEM COMPL 36   8.000  -1.330  6.670  5.580  5.910  0.330  28,443.14  9,386.24 
44000100  PAVEMENT REM   64,461.000  -6,678.330  57,782.670  46,640.050  57,782.670  11,142.620  5.64  62,844.38 
44004250  PAVED SHLD REMOVAL   52,153.000  13,822.100  65,975.100  64,375.020  65,912.770  1,537.750  4.66  7,165.92 
44213204  TIE BARS 3/4   32,715.000  0.000  32,715.000  24,654.000  25,028.000  374.000  8.58  3,208.92 
48300510  PCC SHOULDERS 10 1/2   47,262.000  3,139.300  50,401.300  47,262.000  50,401.300  3,139.300  35.20  110,503.36 
48300700  PCC SHOULDERS 12   16,558.000  929.320  17,487.320  17,230.220  17,487.320  257.100  41.64  10,705.64 
50102400  CONC REM   32.100  0.000  32.100  31.500  32.100  0.600  1,000.00  600.00 
50300255  CONC SUP-STR   32.100  0.530  32.630  32.100  32.630  0.530  2,297.01  1,217.42 
50300260  BR DECK GROOVING   1,629.000  0.000  1,629.000  814.600  1,254.600  440.000  8.07  3,550.80 
50500405  F & E STRUCT STEEL   2,280.000  251.400  2,531.400  2,280.000  2,531.400  251.400  4.37  1,098.62 
50500505  STUD SHEAR CONNECTORS   192.000  0.000  192.000  168.000  192.000  24.000  9.87  236.88 
50800205  REINF BARS, EPOXY CTD   3,170.000  0.000  3,170.000  2,518.450  3,170.000  651.550  2.19  1,426.89 
50800515  BAR SPLICERS   48.000  0.000  48.000  36.000  48.000  12.000  39.64  475.68 
67000400  ENGR FIELD OFFICE A   31.000  0.000  31.000  27.500  28.000  0.500  1,700.00  850.00 
70100205  TRAF CONT-PROT 701401   8.000  0.000  8.000  7.660  7.700  0.040  21,859.22  874.36 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
70100207  TRAF CONT-PROT 701402   4.000  0.000  4.000  3.190  3.350  0.160  12,131.22  1,941.00 
70106800  CHANGEABLE MESSAGE SN   250.000  0.000  250.000  156.000  159.500  3.500  700.00  2,450.00 
70300520  PAVT MARK TAPE T3 4   341,581.000  -146,724.000  194,857.000  86,138.800  94,457.800  8,319.000  1.19  9,899.61 
70301000  WORK ZONE PAVT MK REM   113,860.000  -36,209.000  77,651.000  22,462.570  23,093.870  631.300  1.11  700.75 
70400200  REL TEMP CONC BARRIER   42,325.000  0.000  42,325.000  37,900.000  40,237.500  2,337.500  4.35  10,168.13 
78004210  PREF PL PM TB INL L4   83,873.000  0.000  83,873.000  46,389.000  64,254.000  17,865.000  2.69  48,056.85 
78004230  PREF PL PM TB INL L6   25,043.000  0.000  25,043.000  11,720.000  15,699.000  3,979.000  4.03  16,035.37 
78004240  PREF PL PM TB INL L8   7,194.000  0.000  7,194.000  3,215.000  6,618.000  3,403.000  5.38  18,308.14 
81603035  UD 2#6 #6G XLPUSE 1   13,788.000  10,000.000  23,788.000  18,463.000  21,511.000  3,048.000  5.15  15,697.20 
81900200  TR & BKFIL F ELECT WK   13,530.000  4,596.500  18,126.500  13,530.000  18,126.500  4,596.500  1.21  5,561.77 
82102400  LUM SV HOR MT 400W   43.000  0.000  43.000  23.000  29.000  6.000  656.25  3,937.50 
83010600  LT P A 50MH 15MA   43.000  0.000  43.000  23.000  29.000  6.000  3,228.75  19,372.50 
83600300  LIGHT POLE FDN 30D   608.000  0.000  608.000  504.000  532.000  28.000  131.25  3,675.00 
83800205  BKWY DEV TR B 15BC   76.000  0.000  76.000  23.000  29.000  6.000  472.50  2,835.00 
84400105  RELOC EX LT UNIT   33.000  10.000  43.000  43.000  36.000  -7.000  498.75  -3,491.25 
FRC00201  REPAIR EXISTING BASE   0.000  52,000.000  52,000.000  44,871.510  45,752.630  881.120  1.00  881.12 
FRC00300  POTHOLE PATCHING   0.000  270,000.000  270,000.000  243,268.390  243,828.150  559.760  1.00  559.76 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
FRC00800  SLOPE WALL MODIFICATIO   0.000  20,809.190  20,809.190  13,040.100  20,809.190  7,769.090  1.00  7,769.09 
FRC01200  EMERGE4NCY PATCHING   0.000  255,500.000  255,500.000  230,617.860  240,482.860  9,865.000  1.00  9,865.00 
FRC02600  SURFACE REM SPL   0.000  10,524.070  10,524.070  9,486.670  10,524.070  1,037.400  1.00  1,037.40 
FRC02800  PIPE UNDERDRAIN SPL   0.000  16,195.940  16,195.940  10,695.940  13,958.540  3,262.600  1.00  3,262.60 
MATALL00  MATERIAL ALLOWANCE   0.000  0.000  0.000  0.000  0.000  0.000  0.00  -15,108.00 
XXX02100  RAILROAD FLAGGER   0.000  60,000.000  60,000.000  38,678.720  41,941.620  3,262.900  1.00  3,262.90 
X9903600  REM & REP GRAIL PANEL   0.000  1,175.000  1,175.000  1,025.000  1,175.000  150.000  11.88  1,782.00 
X9903602  REM & REP GR BLOCK-OUT   0.000  106.000  106.000  86.000  106.000  20.000  22.00  440.00 
X9903603  REPAIR TBT TYPE 1 SPL   0.000  10.000  10.000  4.000  6.000  2.000  1,375.00  2,750.00 
X9904001  WZ PVT MKING REM - WAT   0.000  36,209.000  36,209.000  12,180.270  25,834.470  13,654.200  1.07  14,609.99 
X9904500  CL C PATCH T1 15 (SPL)   0.000  87.500  87.500  0.000  63.000  63.000  186.76  11,765.88 
X9904501  CL C PATCH T2 15 (SPL)   0.000  287.900  287.900  0.000  196.600  196.600  174.70  34,346.02 
X9904502  CL C PATCH T3 (SPL)   0.000  209.400  209.400  0.000  160.000  160.000  168.81  27,009.60 
X9904503  CL C PATCH T4 (SPL)   0.000  714.100  714.100  0.000  480.400  480.400  158.34  76,066.54 
X9904504  TIE BARS (SPL)   0.000  1,494.000  1,494.000  0.000  1,127.000  1,127.000  10.37  11,686.99 
Total:   

$745,135.81

 