Illinois Department of Transportation, Erica Borggren, Acting Secretary
Loading
Patrick J. Quinn, Governor
Traveling PublicMapsProjectsRoad ClosuresNewsDoing BusinessLetting & BiddingCareers@IDOTGeneral Info





State of Illinois Department of Transportation

Contract Search

 07/22/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 05/07/2013
DOT Vendor: C55500  Contract: 78165 

IL Project:      From Date: 04/11/2013
Route: FAP 885
Section: 6B-3 To Date: 05/07/2013
Project: ACF-0885/045/ State Job: C-99-020-10
Letting Date: 04/27/2012 Dist/Cnty: 09 - 151 (POPE )
Airport: 6B-3 State Job: C-99-020-10
Scope: FAP-885, IL RT 146 OVER LITTLE GRAND PIERRE CK.

Payee:

E T SIMONDS CONSTRUCTION CO PO BOX 2107  CARBONDALE , IL  62902

 

 

 

 

Percent Completed:  95.14%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
794,811.98      11,062.31      609.45      805,264.84      766,095.21     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 766,095.21     
Mobilzation Paid:2,832.50     
Total paid this estimate:   766,095.21     
     Previous payments to contractor: -677,469.42     
     Payment to contractor this estimate: 88,625.79     
 
          Voucher #   CC19275 Date: 05/08/2013 1 of 1 88,625.79     

----------------------------------------------------------------------------------------------------------------------------------------------     

Includes final mobilization Pay Estimate Number:  07 Total: 88,625.79     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X2070304  POROUS GRAN EMB SPEC   142.000  0.000  142.000  71.000  142.000  71.000  38.28  2,717.88 
Z0046304  P UNDR FOR STRUCT 4   137.000  0.000  137.000  77.700  137.000  59.300  15.49  918.56 
Z0076600  TRAINEES   500.000  0.000  500.000  220.000  248.000  28.000  0.80  22.40 
20200100  EARTH EXCAVATION   111.000  0.000  111.000  55.000  111.000  56.000  18.73  1,048.88 
28100107  STONE RIPRAP CL A4   183.000  0.000  183.000  86.700  183.000  96.300  28.25  2,720.47 
28200200  FILTER FABRIC   183.000  0.000  183.000  86.700  183.000  96.300  2.28  219.56 
42001430  BR APPR PVT CON (FLX)   45.000  0.000  45.000  22.560  45.000  22.440  129.43  2,904.41 
48203029  HMA SHOULDERS 8   231.000  0.000  231.000  165.600  231.000  65.400  45.29  2,961.97 
50300255  CONC SUP-STR   243.200  0.000  243.200  179.600  243.200  63.600  609.00  38,732.40 
50800205  REINF BARS, EPOXY CTD   59,660.000  0.000  59,660.000  46,004.000  59,660.000  13,656.000  1.11  15,158.16 
50800515  BAR SPLICERS   610.000  0.000  610.000  523.000  610.000  87.000  18.19  1,582.53 
51100300  SLOPE WALL 6   106.000  0.000  106.000  97.700  106.000  8.300  158.18  1,312.89 
51500100  NAME PLATES   1.000  0.000  1.000  0.000  1.000  1.000  453.93  453.93 
59100100  GEOCOMPOSITE WALL DR   81.000  0.000  81.000  35.600  70.500  34.900  13.95  486.86 
63000001  SPBGR TY A 6FT POSTS   425.000  0.000  425.000  262.500  425.000  162.500  22.15  3,599.37 
63100085  TRAF BAR TERM T6   4.000  0.000  4.000  2.000  4.000  2.000  3,090.00  6,180.00 
63100167  TR BAR TRM T1 SPL TAN   3.000  0.000  3.000  2.000  3.000  1.000  2,472.00  2,472.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
63100169  TR BAR TRM T1 SPL FLR   1.000  0.000  1.000  0.000  1.000  1.000  2,214.50  2,214.50 
67100100  MOBILIZATION   1.000  0.000  1.000  0.900  1.000  0.100  28,325.00  2,832.50 
78200410  GUARDRAIL MKR TYPE A   11.000  0.000  11.000  8.000  11.000  3.000  8.24  24.72 
78201000  TERMINAL MARKER - DA   4.000  0.000  4.000  2.000  4.000  2.000  30.90  61.80 
Total:   

$88,625.79

 

IDOT Privacy Statement | Illinois Privacy Information | Kids Privacy | Web Accessibility  | FOIA