Previous Report 05/16/2012
DOT Vendor: C03380  Contract: 76E06 

IL Project:      From Date: 05/01/2012
Route: FAP 998
Section: 82-2-1K To Date: 05/16/2012
Project: State Job: C-98-093-10
Letting Date: 01/20/2012 Dist/Cnty: 08 - 163 (ST. CLAIR )
Airport: 82-2-1K State Job: C-98-093-10
Scope: FAP-998, (RELOCATED I-70) A NEW INTERCHANGE IN FAIRMONT CITY

Payee:

BAXMEYER CONSTRUCTION INC 1034 FLORAVILLE RD  WATERLOO , IL  62298

 

 

 

 

Percent Completed:  15.14%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
9,477,161.33      0.00      0.00      9,477,161.33      1,434,805.07     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 1,434,805.07     
Mobilzation Paid:68,997.00     
Total paid this estimate:   1,434,805.07     
     Previous payments to contractor: -854,517.35     
     Payment to contractor this estimate: 580,287.72     
 
          Voucher #   BC06560 Date: 05/18/2012 1 of 1 580,287.72     

----------------------------------------------------------------------------------------------------------------------------------------------     

Includes 15% mobilization Pay Estimate Number:  04 Total: 580,287.72     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X0326802  UTILITY STRUC REMOVAL   31.000  0.000  31.000  12.000  22.000  10.000  420.00  4,200.00 
Z0001050  AGG SUBGRADE 12   41,326.000  0.000  41,326.000  4,180.500  12,581.500  8,401.000  13.72  115,261.72 
20400800  FURNISHED EXCAVATION   78,240.000  0.000  78,240.000  0.000  5,926.900  5,926.900  14.00  82,976.60 
20800150  TRENCH BACKFILL   852.000  0.000  852.000  0.000  100.500  100.500  23.05  2,316.53 
31200500  STAB SUBBASE HMA 4   30,247.000  0.000  30,247.000  0.000  1,859.400  1,859.400  18.48  34,361.71 
44000100  PAVEMENT REM   8,598.000  0.000  8,598.000  1,170.300  5,985.800  4,815.500  5.30  25,522.15 
44000500  COMB CURB GUTTER REM   1,376.000  0.000  1,376.000  185.000  900.000  715.000  5.00  3,575.00 
44004250  PAVED SHLD REMOVAL   674.000  0.000  674.000  0.000  352.000  352.000  5.30  1,865.60 
542A1060  P CUL CL A 2 15   79.000  0.000  79.000  0.000  63.000  63.000  34.65  2,182.95 
542D0220  P CUL CL D 1 15   88.000  0.000  88.000  0.000  64.000  64.000  45.95  2,940.80 
542D0223  P CUL CL D 1 18   64.000  0.000  64.000  0.000  64.000  64.000  44.15  2,825.60 
54213450  END SECTIONS 15   4.000  0.000  4.000  0.000  2.000  2.000  188.00  376.00 
54213453  END SECTIONS 18   2.000  0.000  2.000  0.000  2.000  2.000  260.00  520.00 
54213675  PRC FLAR END SEC 30   2.000  0.000  2.000  0.000  2.000  2.000  1,040.00  2,080.00 
550A0050  STORM SEW CL A 1 12   32.000  0.000  32.000  0.000  31.200  31.200  35.60  1,110.72 
550A0360  STORM SEW CL A 2 15   1,028.000  0.000  1,028.000  0.000  72.500  72.500  36.75  2,664.38 
550A0430  STORM SEW CL A 2 30   85.000  0.000  85.000  0.000  85.000  85.000  63.25  5,376.25 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
55100300  STORM SEWER REM 8   85.000  0.000  85.000  0.000  39.000  39.000  7.75  302.25 
55100500  STORM SEWER REM 12   502.000  0.000  502.000  0.000  57.000  57.000  17.10  974.70 
55100900  STORM SEWER REM 18   383.000  0.000  383.000  0.000  6.000  6.000  16.00  96.00 
56400500  FIRE HYDNTS TO BE REM   1.000  0.000  1.000  0.000  1.000  1.000  450.00  450.00 
60201105  CB TA 4 DIA T11F&G   8.000  0.000  8.000  0.000  2.000  2.000  1,895.00  3,790.00 
60204805  CB TA 5 DIA T11F&G   1.000  0.000  1.000  0.000  1.000  1.000  2,500.00  2,500.00 
60240310  INLETS TB T11F&G   6.000  0.000  6.000  0.000  2.000  2.000  1,401.00  2,802.00 
66900200  NON SPL WASTE DISPOSL   38,535.000  0.000  38,535.000  5,491.950  11,326.450  5,834.500  36.00  210,042.00 
67100100  MOBILIZATION   1.000  0.000  1.000  0.750  0.900  0.150  459,980.00  68,997.00 
70300220  TEMP PVT MK LINE 4   39,359.000  0.000  39,359.000  0.000  176.000  176.000  0.15  26.40 
70301000  WORK ZONE PAVT MK REM   20,985.000  0.000  20,985.000  0.000  191.600  191.600  0.79  151.36 
Total:   

$580,287.72

 