State of Illinois Department of Transportation

Contract Search

 04/14/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 02/04/2013
DOT Vendor: C30850  Contract: 76C52 

IL Project:      From Date: 01/16/2013
Route: FAI 64 FAI 55
Section: 82-1-R(A),82-1-R(B) To Date: 02/04/2013
Project: State Job: C-98-002-12
Letting Date: 04/27/2012 Dist/Cnty: 08 - 163 (ST. CLAIR )
Airport: 82-1-R(A),82-1-R(B) State Job: C-98-002-12
Scope: FAI-64 & 55, I-55/70 TO 18TH ST; I-70 FROM B&0 RR TO I-64.

Payee:

KEELEY & SONS INC P O BOX 837  EAST ST LOUIS , IL  62203

 

 

 

 

Percent Completed:  27.44%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
18,254,486.53      790,503.90      664,108.90      18,380,881.53      5,042,886.12     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 5,042,886.12     
Total paid this estimate:   5,042,886.12     
     Previous payments to contractor: -4,776,457.87     
     Payment to contractor this estimate: 266,428.25     
 
          Voucher #   CC13946 Date: 02/06/2013 1 of 1 266,428.25     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  15 Total: 266,428.25     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
20200100  EARTH EXCAVATION   113,545.000  0.000  113,545.000  87,488.250  88,713.250  1,225.000  7.10  8,697.50 
20800150  TRENCH BACKFILL   2,302.000  0.000  2,302.000  1,482.920  1,647.260  164.340  31.62  5,196.43 
28000400  PERIMETER EROS BAR   12,311.000  0.000  12,311.000  1,099.700  1,192.200  92.500  2.20  203.50 
28000500  INLET & PIPE PROTECT   148.000  0.000  148.000  35.000  56.000  21.000  91.80  1,927.80 
28100107  STONE RIPRAP CL A4   1,351.000  0.000  1,351.000  0.000  577.100  577.100  48.96  28,254.82 
28200200  FILTER FABRIC   1,351.000  0.000  1,351.000  603.200  1,351.000  747.800  2.04  1,525.51 
44000400  GUTTER REM   3,398.000  0.000  3,398.000  1,046.000  1,140.000  94.000  7.14  671.16 
44001980  CONC BARRIER REMOV   6,015.000  0.000  6,015.000  4,036.000  5,794.000  1,758.000  10.00  17,580.00 
44004250  PAVED SHLD REMOVAL   20,841.000  0.000  20,841.000  9,886.300  11,161.200  1,274.900  7.91  10,084.46 
44213200  SAW CUTS   5,753.000  0.000  5,753.000  665.300  1,605.300  940.000  6.80  6,392.00 
44213204  TIE BARS 3/4   2,638.000  0.000  2,638.000  2,117.000  2,127.000  10.000  11.90  119.00 
48300500  PCC SHOULDERS 10   4,622.000  0.000  4,622.000  2,729.310  2,735.610  6.300  61.80  389.34 
550A0340  STORM SEW CL A 2 12   2,383.000  0.000  2,383.000  1,333.000  1,849.000  516.000  69.36  35,789.76 
550A0360  STORM SEW CL A 2 15   1,083.000  0.000  1,083.000  584.400  701.400  117.000  72.42  8,473.14 
55100500  STORM SEWER REM 12   2,033.000  0.000  2,033.000  1,379.600  1,484.600  105.000  20.40  2,142.00 
60200805  CB TA 4 DIA T8G   5.000  0.000  5.000  3.000  4.000  1.000  2,917.20  2,917.20 
60201340  CB TA 4 DIA T24F&G   9.000  0.000  9.000  3.000  9.000  6.000  3,513.90  21,083.40 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
60218400  MAN TA 4 DIA T1F CL   17.000  0.000  17.000  14.000  16.000  2.000  3,049.80  6,099.60 
60237470  INLETS TA T24F&G   6.000  0.000  6.000  2.000  6.000  4.000  1,723.80  6,895.20 
60240328  INLETS TB T24F&G   2.000  0.000  2.000  1.000  2.000  1.000  1,922.70  1,922.70 
60255500  MAN ADJUST   7.000  0.000  7.000  0.000  2.000  2.000  408.00  816.00 
60500040  REMOV MANHOLES   15.000  0.000  15.000  6.000  9.000  3.000  390.00  1,170.00 
63700275  CONC BAR 2F 42HT   2,838.000  0.000  2,838.000  211.700  424.500  212.800  73.90  15,725.92 
63700805  CONC BAR TRANS   558.000  0.000  558.000  85.900  210.700  124.800  227.85  28,435.68 
63700900  CONC BARRIER BASE   8,982.000  0.000  8,982.000  2,897.900  2,914.700  16.800  53.80  903.84 
73400200  DRILL SHAFT CONC FDN   173.900  0.000  173.900  148.540  173.900  25.360  2,090.39  53,012.29 
Total:   

$266,428.25

 