Contract Search

 07/28/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 09/30/2011
DOT Vendor: C27810  Contract: 76A47 

IL Project:      From Date: 09/01/2011
Route: FAP 809
Section: (133,134)RS-5, 135RS-6 To Date: 09/30/2011
Project: F-0809/004/ State Job: C-98-021-07
Letting Date: 07/30/2010 Dist/Cnty: 08 - 163 (ST. CLAIR )
Airport: (133,134)RS-5, 135RS-6 State Job: C-98-021-07
Scope: FAP-809, IL 158 FROM M&O STATION RD IN MILLSTADT TO IL 15
RAMPS IN BELLEVILLE.

Payee:

ILLINOIS EXCAVATORS INC 55 E MILL ST  RUMA , IL  62278

 

 

 

 

Percent Completed:  20.61%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
8,523,641.12      1,540,418.85      1,381,548.08      8,682,511.89      1,795,641.28     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 1,795,641.28     
Total paid this estimate:   1,795,641.28     
     Previous payments to contractor: -1,538,648.15     
     Payment to contractor this estimate: 256,993.13     
 
          Voucher #   CC06744 Date: 10/04/2011 1 of 1 256,993.13     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  14 Total: 256,993.13     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
Z0023500  FILL EXIST CULVERTS   2.000  10.000  12.000  2.000  5.700  3.700  585.00  2,164.50 
20100210  TREE REMOV OVER 15   210.000  108.700  318.700  210.000  318.700  108.700  41.00  4,456.70 
20200100  EARTH EXCAVATION   50,368.000  4,606.000  54,974.000  0.000  3,202.000  3,202.000  7.93  25,391.86 
20800150  TRENCH BACKFILL   859.000  0.000  859.000  526.300  510.800  -15.500  58.25  -902.87 
35102400  AGG BASE CSE B 12   24,175.600  0.000  24,175.600  975.700  2,395.300  1,419.600  12.13  17,219.75 
40200800  AGG SURF CSE B   1,675.500  0.000  1,675.500  0.000  34.270  34.270  31.35  1,074.36 
40603085  HMA BC IL-19.0 N70   14,324.000  0.000  14,324.000  0.000  1,133.550  1,133.550  71.20  80,708.76 
44004250  PAVED SHLD REMOVAL   10,712.000  0.000  10,712.000  135.000  283.000  148.000  6.68  988.64 
44200124  PAVT PATCH T3 10   850.000  0.000  850.000  43.700  159.900  116.200  0.01  1.16 
44201023  CL B PATCH T3 14   77.000  188.600  265.600  77.000  265.600  188.600  130.00  24,518.00 
48203029  HMA SHOULDERS 8   26,284.500  0.000  26,284.500  0.000  143.000  143.000  28.35  4,054.05 
50104400  CONC HDWL REM   154.000  0.000  154.000  18.000  20.000  2.000  163.65  327.30 
50105220  PIPE CULVERT REMOV   4,103.000  0.000  4,103.000  1,385.400  1,410.300  24.900  14.10  351.09 
54001006  BOX CUL END SEC C6   1.000  0.000  1.000  0.000  1.000  1.000  2,003.45  2,003.45 
54001017  BOX CUL END SEC C17   1.000  0.000  1.000  0.000  1.000  1.000  2,226.20  2,226.20 
54001018  BOX CUL END SEC C18   1.000  0.000  1.000  0.000  1.000  1.000  2,226.20  2,226.20 
54010706  PCBC 7X6   31.500  0.000  31.500  0.000  16.700  16.700  354.40  5,918.48 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
54010804  PCBC 8X4   60.000  0.000  60.000  0.000  60.000  60.000  432.25  25,935.00 
54248515  CONCRETE COLLAR   22.000  0.000  22.000  9.000  11.000  2.000  720.40  1,440.80 
60235700  INLETS TA T3F&G   12.000  13.000  25.000  19.000  18.000  -1.000  948.70  -948.70 
60600095  CLASS SI CONC OUTLET   101.700  0.000  101.700  0.930  6.260  5.330  634.00  3,379.22 
60602500  CONC GUTTER TA   4,547.000  0.000  4,547.000  238.500  338.800  100.300  18.66  1,871.60 
60605000  COMB CC&G TB6.24   6,014.000  0.000  6,014.000  989.750  1,986.250  996.500  29.61  29,506.36 
66900450  SPL WASTE PLNS/REPORT   1.000  0.000  1.000  0.000  1.000  1.000  5,145.00  5,145.00 
67000400  ENGR FIELD OFFICE A   30.000  0.000  30.000  9.000  10.000  1.000  1,500.00  1,500.00 
FRC00800  POT HOLE REPAIRS   0.000  6,758.210  6,758.210  5,868.620  6,758.210  889.590  1.00  889.59 
X9800301  STORM SEW WMQ 16   0.000  1,782.600  1,782.600  1,569.000  1,782.600  213.600  58.30  12,452.88 
X9800304  3/4 IN ANCHOR BOLTS   0.000  165.000  165.000  0.000  165.000  165.000  18.75  3,093.75 
Total:   

$256,993.13

 