 04/17/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 01/18/2012
DOT Vendor: C23080  Contract: 76830 

IL Project:      From Date: 01/10/2012
Route: FAP 600
Section: 60-(30,31,128)-1 To Date: 01/18/2012
Project: NHF-0600/060/ State Job: C-98-086-09
Letting Date: 06/11/2010 Dist/Cnty: 08 - 119 (MADISON )
Airport: 60-(30,31,128)-1 State Job: C-98-086-09
Scope: PAVEMENT WIDENING AND A NEW TRIPLE BOX CULVERT ON IL 159
IN COLLINSVILLE, FROM S. MORRISON TO CHURCH STREET.

Payee:

HANKS EXCAVATING & LANDSCAPING 5825 W STATE ROUTE 161  BELLEVILLE , IL  62223

 

 

 

 

Percent Completed:  49.66%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
9,384,063.14      979,639.65      393,977.06      9,969,725.73      5,003,323.05     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 5,003,323.05     
Total paid this estimate:   5,003,323.05     
     Previous payments to contractor: -4,936,821.17     
     Payment to contractor this estimate: 66,501.88     
 
          Voucher #   BC04662 Date: 01/19/2012 1 of 1 66,501.88     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  34 Total: 66,501.88     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X0324455  DRILL/SET SOLD P SOIL   18,746.000  -4,795.000  13,951.000  4,031.900  4,244.380  212.480  14.60  3,102.21 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.580  0.599  0.019  44,000.00  836.00 
20200100  EARTH EXCAVATION   37,949.000  220.700  38,169.700  23,010.100  23,145.100  135.000  18.00  2,430.00 
20800150  TRENCH BACKFILL   12,402.000  0.000  12,402.000  5,192.630  5,366.010  173.380  33.00  5,721.54 
28000500  INLET & PIPE PROTECT   130.000  0.000  130.000  30.000  49.000  19.000  180.00  3,420.00 
40201000  AGGREGATE-TEMP ACCESS   5,107.000  0.000  5,107.000  3,369.840  3,455.720  85.880  26.50  2,275.82 
44000100  PAVEMENT REM   12,921.000  0.000  12,921.000  7,999.470  8,080.470  81.000  10.00  810.00 
50100100  REM EXIST STRUCT   1.000  0.000  1.000  0.900  1.000  0.100  18,000.00  1,800.00 
50200100  STRUCTURE EXCAVATION   330.000  -73.000  257.000  179.500  245.500  66.000  26.00  1,716.00 
50500505  STUD SHEAR CONNECTORS   1,018.000  -224.000  794.000  56.000  208.000  152.000  8.75  1,330.00 
50700209  UNTREATED TIMBER LAG   1,738.000  -408.000  1,330.000  141.500  501.500  360.000  20.50  7,380.00 
51202230  FUR SOLDIER PILES WS   2,433.000  -652.000  1,781.000  622.200  654.800  32.600  92.50  3,015.50 
550A0050  STORM SEW CL A 1 12   1,078.000  0.000  1,078.000  770.100  776.000  5.900  26.50  156.35 
550A0340  STORM SEW CL A 2 12   3,597.000  0.000  3,597.000  1,521.250  1,767.650  246.400  31.00  7,638.40 
550A0360  STORM SEW CL A 2 15   786.000  0.000  786.000  629.700  664.900  35.200  36.50  1,284.80 
550A0380  STORM SEW CL A 2 18   272.000  0.000  272.000  21.500  151.500  130.000  41.55  5,401.50 
55100400  STORM SEWER REM 10   90.000  0.000  90.000  0.000  21.000  21.000  8.00  168.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
55100500  STORM SEWER REM 12   795.000  0.000  795.000  622.400  664.400  42.000  5.50  231.00 
55100700  STORM SEWER REM 15   182.000  0.000  182.000  0.000  10.000  10.000  5.80  58.00 
55101200  STORM SEWER REM 24   639.000  0.000  639.000  343.700  381.200  37.500  12.00  450.00 
59100100  GEOCOMPOSITE WALL DR   119.000  -25.000  94.000  9.300  36.300  27.000  25.00  675.00 
60218400  MAN TA 4 DIA T1F CL   37.000  0.000  37.000  24.000  27.000  3.000  1,500.00  4,500.00 
60223800  MAN TA 6 DIA T1F CL   16.000  0.000  16.000  15.500  16.000  0.500  2,975.00  1,487.50 
60235700  INLETS TA T3F&G   56.000  0.000  56.000  23.000  24.000  1.000  820.00  820.00 
60240220  INLETS TB T3F&G   18.000  0.000  18.000  10.500  11.000  0.500  1,250.00  625.00 
60500040  REMOV MANHOLES   4.000  0.000  4.000  0.000  2.000  2.000  525.00  1,050.00 
60500060  REMOV INLETS   22.000  0.000  22.000  9.000  11.000  2.000  130.00  260.00 
70102620  TR CONT & PROT 701501   1.000  0.000  1.000  0.613  0.630  0.017  21,000.00  357.00 
70102622  TR CONT & PROT 701502   1.000  0.000  1.000  0.613  0.630  0.017  1,000.00  17.00 
70102635  TR CONT & PROT 701701   1.000  0.000  1.000  0.613  0.630  0.017  1,000.00  17.00 
X9800704  RESTRICT PLATE MH   0.000  2.000  2.000  0.500  1.000  0.500  8,097.61  4,048.80 
X9803300  TR FR &GRATES MATERIAL   0.000  1,872.860  1,872.860  0.000  1,872.860  1,872.860  1.00  1,872.86 
X9803301  COR MET PIPE MATERIAL   0.000  1,546.600  1,546.600  0.000  1,546.600  1,546.600  1.00  1,546.60 
Total:   

$66,501.88

 