State of Illinois Department of Transportation

Contract Search

 07/21/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 03/16/2012
DOT Vendor: C23080  Contract: 76830 

IL Project:      From Date: 03/01/2012
Route: FAP 600
Section: 60-(30,31,128)-1 To Date: 03/16/2012
Project: NHF-0600/060/ State Job: C-98-086-09
Letting Date: 06/11/2010 Dist/Cnty: 08 - 119 (MADISON )
Airport: 60-(30,31,128)-1 State Job: C-98-086-09
Scope: PAVEMENT WIDENING AND A NEW TRIPLE BOX CULVERT ON IL 159
IN COLLINSVILLE, FROM S. MORRISON TO CHURCH STREET.

Payee:

HANKS EXCAVATING & LANDSCAPING 5825 W STATE ROUTE 161  BELLEVILLE , IL  62223

 

 

 

 

Percent Completed:  57.7%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
9,384,063.14      1,235,983.93      512,661.17      10,107,385.90      5,884,329.21     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 5,884,329.21     
Total paid this estimate:   5,884,329.21     
     Previous payments to contractor: -5,448,187.36     
     Payment to contractor this estimate: 436,141.85     
 
          Voucher #   BC05571 Date: 03/20/2012 1 of 1 436,141.85     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  38 Total: 436,141.85     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X0320591  SAN MAN REMOVED   2.000  0.000  2.000  0.000  2.000  2.000  1,400.00  2,800.00 
X0322923  SEGMENT CONC BLK WALL   163.000  0.000  163.000  81.500  115.200  33.700  62.00  2,089.40 
X0324455  DRILL/SET SOLD P SOIL   18,746.000  -4,795.000  13,951.000  4,244.380  7,480.280  3,235.900  14.60  47,244.14 
X0487700  SAN SEW REMOV 10   45.000  0.000  45.000  0.000  45.000  45.000  17.50  787.50 
X0840000  SAN SEW REMOV 8   451.000  0.000  451.000  0.000  236.400  236.400  7.00  1,654.80 
X5640150  FIRE HYDNT ASSY COMP   19.000  1.000  20.000  19.000  20.000  1.000  4,670.00  4,670.00 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.656  0.675  0.019  44,000.00  836.00 
Z0056900  SAN SEW 8   455.000  0.000  455.000  0.000  232.400  232.400  71.50  16,616.60 
Z0057000  SAN SEW 10   45.000  0.000  45.000  0.000  45.000  45.000  110.00  4,950.00 
20200100  EARTH EXCAVATION   37,949.000  220.700  38,169.700  23,145.100  24,544.300  1,399.200  18.00  25,185.60 
20800150  TRENCH BACKFILL   12,402.000  0.000  12,402.000  6,066.030  6,435.030  369.000  33.00  12,177.00 
28000315  AGG DITCH CHECKS   192.000  0.000  192.000  59.000  69.000  10.000  30.00  300.00 
35300610  PCC BSE CSE 11 1/2   127.000  0.000  127.000  48.600  127.000  78.400  95.00  7,448.00 
40201000  AGGREGATE-TEMP ACCESS   5,107.000  0.000  5,107.000  3,790.060  4,056.150  266.090  26.50  7,051.39 
42300200  PCC DRIVEWAY PAVT 6   588.000  0.000  588.000  123.610  528.610  405.000  68.50  27,742.50 
42300400  PCC DRIVEWAY PAVT 8   1,350.000  0.000  1,350.000  342.860  754.360  411.500  72.50  29,833.75 
42400100  PC CONC SIDEWALK 4   44,229.000  0.000  44,229.000  7,620.750  8,580.850  960.100  5.25  5,040.53 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
42400800  DETECTABLE WARNINGS   946.000  -432.000  514.000  88.000  106.000  18.000  47.00  846.00 
44000100  PAVEMENT REM   12,921.000  0.000  12,921.000  8,593.520  9,394.620  801.100  10.00  8,011.00 
44000198  HMA SURF REM VAR DP   13,824.000  0.000  13,824.000  0.000  3,123.900  3,123.900  1.80  5,623.02 
44000200  DRIVE PAVEMENT REM   10,421.000  0.000  10,421.000  7,135.050  8,334.450  1,199.400  3.35  4,017.99 
44000400  GUTTER REM   3,956.000  0.000  3,956.000  3,593.000  3,944.600  351.600  1.75  615.30 
44000600  SIDEWALK REM   13,412.000  0.000  13,412.000  9,739.430  10,095.630  356.200  1.00  356.20 
50800205  REINF BARS, EPOXY CTD   98,347.000  -4,230.000  94,117.000  44,368.010  61,480.410  17,112.400  1.20  20,534.88 
51202220  FUR SOLDIER PILES BU   122.000  0.000  122.000  0.000  68.400  68.400  208.00  14,227.20 
51202230  FUR SOLDIER PILES WS   2,433.000  -652.000  1,781.000  654.800  1,096.300  441.500  92.50  40,838.75 
54003000  CONC BOX CUL   270.600  0.000  270.600  140.470  195.870  55.400  655.00  36,287.00 
550A0120  STORM SEW CL A 1 24   270.000  15.000  285.000  270.000  285.000  15.000  55.00  825.00 
55100500  STORM SEWER REM 12   795.000  0.000  795.000  706.400  795.000  88.600  5.50  487.30 
55100700  STORM SEWER REM 15   182.000  0.000  182.000  160.000  182.000  22.000  5.80  127.60 
56300100  ADJ SAN SEWER 8 LESS   10.000  0.000  10.000  0.000  10.000  10.000  128.00  1,280.00 
60223800  MAN TA 6 DIA T1F CL   16.000  2.000  18.000  16.000  16.500  0.500  2,975.00  1,487.50 
60228110  MAN SAN 4 DIA T1F CL   2.000  0.000  2.000  0.000  0.500  0.500  4,800.00  2,400.00 
60260050  SAN MAN RECONST   3.000  0.000  3.000  0.000  1.000  1.000  6,575.00  6,575.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
60600605  CONC CURB TB   1,418.000  0.000  1,418.000  145.600  171.900  26.300  37.15  977.05 
60605000  COMB CC&G TB6.24   12,887.000  0.000  12,887.000  6,205.200  6,590.000  384.800  22.35  8,600.28 
70102620  TR CONT & PROT 701501   1.000  0.000  1.000  0.681  0.698  0.017  21,000.00  357.00 
70102622  TR CONT & PROT 701502   1.000  0.000  1.000  0.681  0.698  0.017  1,000.00  17.00 
70102635  TR CONT & PROT 701701   1.000  0.000  1.000  0.681  0.698  0.017  1,000.00  17.00 
70103815  TR CONT SURVEILLANCE   200.000  200.000  400.000  200.000  279.590  79.590  300.00  23,877.00 
70300220  TEMP PVT MK LINE 4   74,562.000  26,500.000  101,062.000  73,379.000  95,651.000  22,272.000  0.15  3,340.80 
81012300  CON T 1 PVC   156.000  75.000  231.000  0.000  206.200  206.200  4.85  1,000.07 
81012500  CON T 1 1/2 PVC   63.000  0.000  63.000  0.000  20.000  20.000  6.50  130.00 
81012600  CON T 2 PVC   62.000  155.000  217.000  0.000  59.100  59.100  8.00  472.80 
81012800  CON T 3 PVC   60.000  0.000  60.000  0.000  60.000  60.000  11.35  681.00 
81013000  CON T 4 PVC   30.000  0.000  30.000  0.000  20.100  20.100  9.75  195.98 
81018700  CON P 3 GALVS   137.000  0.000  137.000  0.000  131.000  131.000  20.40  2,672.40 
81018900  CON P 4 GALVS   80.000  0.000  80.000  0.000  80.000  80.000  19.50  1,560.00 
81400700  HANDHOLE PCC   5.000  0.000  5.000  1.000  4.000  3.000  750.75  2,252.25 
81400720  DBL HANDHOLE PCC   1.000  0.000  1.000  0.000  1.000  1.000  1,506.75  1,506.75 
81900200  TR & BKFIL F ELECT WK   281.000  230.000  511.000  0.000  291.000  291.000  4.50  1,309.50 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
87800100  CONC FDN TY A   3.000  0.000  3.000  0.000  3.000  3.000  94.50  283.50 
87800200  CONC FDN TY D   3.000  0.000  3.000  0.000  3.000  3.000  162.75  488.25 
FRC00300  RETAINING WALL REM   0.000  5,000.000  5,000.000  4,034.080  5,000.000  965.920  1.00  965.92 
FRC00600  LOCATE UTILITIES   0.000  225,000.000  225,000.000  189,497.920  195,615.870  6,117.950  1.00  6,117.95 
FRC01200  ROAD MAINTENANCE   0.000  50,000.000  50,000.000  30,000.000  35,614.300  5,614.300  1.00  5,614.30 
FRC01500  TRAF CONT MODIFICATION   0.000  25,000.000  25,000.000  18,671.560  19,116.460  444.900  1.00  444.90 
FRC02200  TEMP INLETS   0.000  21,088.850  21,088.850  11,088.850  21,088.850  10,000.000  1.00  10,000.00 
FRC04300  EXTEND FIRE HYD   0.000  35,000.000  35,000.000  0.000  16,756.050  16,756.050  1.00  16,756.05 
FRC04600  WATERLINE REMOVAL   0.000  1,454.600  1,454.600  0.000  1,454.600  1,454.600  1.00  1,454.60 
X9802800  ADD ENGINEERING COST   0.000  2,838.450  2,838.450  1,625.250  2,838.450  1,213.200  1.00  1,213.20 
X9804004  LIGHT POLE FDN SPL   0.000  29.000  29.000  0.000  14.500  14.500  120.75  1,750.88 
X9804400  PCC MANHOLE MATERIALS   0.000  1,118.470  1,118.470  0.000  1,118.470  1,118.470  1.00  1,118.47 
Total:   

$436,141.85

 