Contractor Invoice

Previous Report 06/01/2012
DOT Vendor: C23080  Contract: 76830 

IL Project:      From Date: 05/18/2012
Route: FAP 600
Section: 60-(30,31,128)-1 To Date: 06/01/2012
Project: NHF-0600/060/ State Job: C-98-086-09
Letting Date: 06/11/2010 Dist/Cnty: 08 - 119 (MADISON )
Airport: 60-(30,31,128)-1 State Job: C-98-086-09
Scope: PAVEMENT WIDENING AND A NEW TRIPLE BOX CULVERT ON IL 159
IN COLLINSVILLE, FROM S. MORRISON TO CHURCH STREET.

Payee:

HANKS EXCAVATING & LANDSCAPING 5825 W STATE ROUTE 161  BELLEVILLE , IL  62223

 

 

 

 

Percent Completed:  73.83%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
9,384,063.14      1,501,901.61      512,661.17      10,373,303.58      7,711,721.04     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 7,711,721.04     
Total paid this estimate:   7,711,721.04     
     Previous payments to contractor: -7,471,463.05     
     Payment to contractor this estimate: 240,257.99     
 
          Voucher #   BC06895 Date: 06/05/2012 1 of 1 240,257.99     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  43 Total: 240,257.99     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.751  0.770  0.019  44,000.00  836.00 
20200100  EARTH EXCAVATION   37,949.000  220.700  38,169.700  26,326.300  26,916.600  590.300  18.00  10,625.40 
20800150  TRENCH BACKFILL   12,402.000  0.000  12,402.000  6,818.980  7,371.420  552.440  33.00  18,230.52 
28100107  STONE RIPRAP CL A4   778.000  0.000  778.000  0.000  445.900  445.900  34.00  15,160.60 
28200200  FILTER FABRIC   1,065.000  0.000  1,065.000  0.000  445.900  445.900  1.15  512.79 
35102000  AGG BASE CSE B 8   14,227.000  0.000  14,227.000  9,829.100  9,792.700  -36.400  7.00  -254.80 
35102400  AGG BASE CSE B 12   17,598.000  0.000  17,598.000  13,187.600  13,618.200  430.600  13.00  5,597.80 
40200800  AGG SURF CSE B   257.000  0.000  257.000  162.400  182.300  19.900  34.00  676.60 
42400100  PC CONC SIDEWALK 4   44,229.000  0.000  44,229.000  26,621.750  26,497.450  -124.300  5.25  -652.58 
44000100  PAVEMENT REM   12,921.000  0.000  12,921.000  11,272.420  12,921.000  1,648.580  10.00  16,485.80 
44000200  DRIVE PAVEMENT REM   10,421.000  0.000  10,421.000  8,849.350  8,857.150  7.800  3.35  26.13 
44200202  PAVT PATCH T2 17   649.000  0.000  649.000  215.250  257.450  42.200  173.00  7,300.60 
50200100  STRUCTURE EXCAVATION   330.000  -73.000  257.000  257.000  216.200  -40.800  26.00  -1,060.80 
50500505  STUD SHEAR CONNECTORS   1,018.000  -224.000  794.000  661.000  793.000  132.000  8.75  1,155.00 
50700209  UNTREATED TIMBER LAG   1,738.000  -408.000  1,330.000  1,230.400  1,330.000  99.600  20.50  2,041.80 
54001003  BOX CUL END SEC C3   1.000  0.000  1.000  0.000  1.000  1.000  1,565.00  1,565.00 
54010402  PCBC 4X2   676.000  0.000  676.000  613.700  654.200  40.500  168.00  6,804.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
54010505  PCBC 5X5   142.000  0.000  142.000  0.000  108.800  108.800  278.00  30,246.40 
54213657  PRC FLAR END SEC 12   8.000  0.000  8.000  3.000  6.000  3.000  565.00  1,695.00 
550A0050  STORM SEW CL A 1 12   1,078.000  0.000  1,078.000  844.200  883.400  39.200  26.50  1,038.80 
550A0070  STORM SEW CL A 1 15   286.000  0.000  286.000  207.300  254.600  47.300  38.00  1,797.40 
550A0340  STORM SEW CL A 2 12   3,597.000  0.000  3,597.000  2,675.950  3,098.450  422.500  31.00  13,097.50 
550A0360  STORM SEW CL A 2 15   786.000  0.000  786.000  679.800  666.500  -13.300  36.50  -485.45 
55100300  STORM SEWER REM 8   59.000  0.000  59.000  31.000  59.000  28.000  6.00  168.00 
55102100  STORM SEWER REM 60   101.000  0.000  101.000  0.000  101.000  101.000  17.25  1,742.25 
59100100  GEOCOMPOSITE WALL DR   119.000  -25.000  94.000  89.200  94.000  4.800  25.00  120.00 
60109580  P UNDR FOR STRUCT 4   435.000  -89.000  346.000  193.000  253.000  60.000  15.00  900.00 
60218400  MAN TA 4 DIA T1F CL   37.000  1.000  38.000  32.000  33.500  1.500  1,500.00  2,250.00 
60235700  INLETS TA T3F&G   56.000  2.000  58.000  37.000  45.500  8.500  820.00  6,970.00 
60240220  INLETS TB T3F&G   18.000  0.000  18.000  12.000  13.000  1.000  1,250.00  1,250.00 
60500060  REMOV INLETS   22.000  0.000  22.000  18.000  20.000  2.000  130.00  260.00 
60600605  CONC CURB TB   1,418.000  0.000  1,418.000  771.200  1,418.000  646.800  37.15  24,028.62 
60605000  COMB CC&G TB6.24   12,887.000  0.000  12,887.000  8,732.900  9,043.500  310.600  22.35  6,941.91 
70102620  TR CONT & PROT 701501   1.000  0.000  1.000  0.766  0.783  0.017  21,000.00  357.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
70102622  TR CONT & PROT 701502   1.000  0.000  1.000  0.766  0.783  0.017  1,000.00  17.00 
70102635  TR CONT & PROT 701701   1.000  0.000  1.000  0.766  0.783  0.017  1,000.00  17.00 
70103815  TR CONT SURVEILLANCE   200.000  200.000  400.000  327.060  339.630  12.570  300.00  3,771.00 
70301000  WORK ZONE PAVT MK REM   5,181.000  0.000  5,181.000  616.100  1,061.800  445.700  0.75  334.27 
78001110  PAINT PVT MK LINE 4   1,536.000  0.000  1,536.000  0.000  1,536.000  1,536.000  0.55  844.80 
78001150  PAINT PVT MK LINE 12   179.000  0.000  179.000  0.000  57.800  57.800  1.85  106.93 
FRC04300  EXTEND FIRE HYD   0.000  35,000.000  35,000.000  28,253.990  35,000.000  6,746.010  1.00  6,746.01 
FRC05300  CURB & GUTTER ADJ   0.000  3,882.020  3,882.020  0.000  3,882.020  3,882.020  1.00  3,882.02 
X9804800  5X5 END SECTION (SP)   0.000  4.000  4.000  0.000  3.000  3.000  15,703.89  47,111.67 
Total:   

$240,257.99

 