DOT Vendor: C23080  Contract: 76830 

IL Project:      From Date: 07/18/2012
Route: FAP 600
Section: 60-(30,31,128)-1 To Date: 08/03/2012
Project: NHF-0600/060/ State Job: C-98-086-09
Letting Date: 06/11/2010 Dist/Cnty: 08 - 119 (MADISON )
Airport: 60-(30,31,128)-1 State Job: C-98-086-09
Scope: PAVEMENT WIDENING AND A NEW TRIPLE BOX CULVERT ON IL 159
IN COLLINSVILLE, FROM S. MORRISON TO CHURCH STREET.

Payee:

HANKS EXCAVATING & LANDSCAPING 5825 W STATE ROUTE 161  BELLEVILLE , IL  62223

 

 

 

 

Percent Completed:  85.52%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
9,384,063.14      1,789,844.74      567,503.84      10,606,404.04      9,117,992.71     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 9,117,992.71     
Total paid this estimate:   9,117,992.71     
     Previous payments to contractor: -8,859,551.92     
     Payment to contractor this estimate: 258,440.79     
 
          Voucher #   BC00528 Date: 08/07/2012 1 of 1 258,440.79     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  47 Total: 258,440.79     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
XX004018  REM & RELAY BRCK SDWK   35.000  0.000  35.000  0.000  35.000  35.000  21.00  735.00 
Z0012450  CONCRETE STEPS   14.500  0.000  14.500  5.960  8.180  2.220  1,475.00  3,274.50 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.827  0.846  0.019  44,000.00  836.00 
20800150  TRENCH BACKFILL   12,402.000  0.000  12,402.000  7,480.320  7,496.990  16.670  33.00  550.11 
25100630  EROSION CONTR BLANKET   7,183.000  11,000.000  18,183.000  7,183.000  16,435.950  9,252.950  1.65  15,267.37 
28000315  AGG DITCH CHECKS   192.000  0.000  192.000  134.500  150.500  16.000  30.00  480.00 
28000500  INLET & PIPE PROTECT   130.000  0.000  130.000  57.000  60.000  3.000  180.00  540.00 
40600200  BIT MATLS PR CT   13.500  0.000  13.500  8.640  9.190  0.550  1,325.00  728.75 
40600990  TEMPORARY RAMP   393.000  0.000  393.000  342.200  393.000  50.800  7.35  373.38 
40603570  P HMA SC "E" N90   5,579.000  -1,814.000  3,765.000  336.370  344.370  8.000  96.50  772.00 
40800050  INCIDENTAL HMA SURF   454.000  0.000  454.000  370.310  380.810  10.500  110.25  1,157.62 
42300200  PCC DRIVEWAY PAVT 6   588.000  193.100  781.100  588.000  781.100  193.100  68.50  13,227.35 
42300400  PCC DRIVEWAY PAVT 8   1,350.000  0.000  1,350.000  1,089.470  1,135.770  46.300  72.50  3,356.75 
42400420  PC CONC SIDEWALK 4 SP   426.000  0.000  426.000  217.200  426.000  208.800  21.00  4,384.80 
44000198  HMA SURF REM VAR DP   13,824.000  0.000  13,824.000  13,010.100  13,824.000  813.900  1.80  1,465.02 
54247170  GRATING-C FL END S 36   1.000  0.000  1.000  0.000  1.000  1.000  875.00  875.00 
54247190  GRATING-C FL END S 48   1.000  0.000  1.000  0.000  1.000  1.000  1,100.00  1,100.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
70101800  TRAF CONT & PROT SPL   1.000  0.000  1.000  0.500  0.900  0.400  88,000.00  35,200.00 
70102620  TR CONT & PROT 701501   1.000  0.000  1.000  0.834  0.851  0.017  21,000.00  357.00 
70102622  TR CONT & PROT 701502   1.000  0.000  1.000  0.834  0.851  0.017  1,000.00  17.00 
70102635  TR CONT & PROT 701701   1.000  0.000  1.000  0.834  0.851  0.017  1,000.00  17.00 
70300100  SHORT-TERM PAVT MKING   8,000.000  0.000  8,000.000  1,168.000  1,324.000  156.000  1.30  202.80 
70300220  TEMP PVT MK LINE 4   74,562.000  53,000.000  127,562.000  95,651.000  102,836.000  7,185.000  0.15  1,077.75 
70300260  TEMP PVT MK LINE 12   784.000  140.000  924.000  365.000  390.000  25.000  1.00  25.00 
70301000  WORK ZONE PAVT MK REM   5,181.000  0.000  5,181.000  1,061.800  1,206.100  144.300  0.75  108.23 
87700200  S MAA & P 32   2.000  0.000  2.000  0.000  2.000  2.000  4,462.50  8,925.00 
88600100  DET LOOP T1   1,800.000  0.000  1,800.000  0.000  1,800.000  1,800.000  6.50  11,700.00 
88600600  DET LOOP REPL   475.000  0.000  475.000  0.000  462.500  462.500  6.20  2,867.50 
FRC00300  RETAINING WALL REM   0.000  15,000.000  15,000.000  5,000.000  7,004.690  2,004.690  1.00  2,004.69 
FRC01200  ROAD MAINTENANCE   0.000  50,000.000  50,000.000  36,284.360  37,591.010  1,306.650  1.00  1,306.65 
FRC01700  CLEAN EXIST CULVERT   0.000  24,308.870  24,308.870  11,300.120  24,308.870  13,008.750  1.00  13,008.75 
FRC01800  SEDIMENT BASIN   0.000  35,000.000  35,000.000  28,945.670  34,669.310  5,723.640  1.00  5,723.64 
FRC02000  REM & REPL UNSUIT MAT   0.000  200,000.000  200,000.000  140,000.000  200,000.000  60,000.000  1.00  60,000.00 
FRC02300  UNKN SUBSURF COND   0.000  75,000.000  75,000.000  65,000.000  71,662.980  6,662.980  1.00  6,662.98 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
FRC02500  RESAW CUTTING   0.000  15,000.000  15,000.000  2,719.910  10,147.240  7,427.330  1.00  7,427.33 
FRC05900  RELOCATE FIRE HYDRANT   0.000  40,000.000  40,000.000  0.000  40,000.000  40,000.000  1.00  40,000.00 
MATALL00  MATERIAL ALLOWANCE   0.000  0.000  0.000  0.000  0.000  0.000  0.00  -5,530.52 
X9803200  HMA POLY, N90, C MIX   0.000  1,814.000  1,814.000  1,631.380  1,814.000  182.620  99.75  18,216.34 
Total:   

$258,440.79

 