|
Invoice Archive
Contract Number
&
Estimate Numbers are listed below
Go to Current Estimate for this Contract Number
|
Contractor Invoice
Previous Report 12/16/2010
| DOT Vendor: |
C31080 |
|
Contract: |
76634 |
| IL Project: |
|
From Date: |
11/29/2010 |
| Route: |
FAP 310 |
|
|
|
| Section: |
60-15VB-1&2 |
To Date: |
12/16/2010 |
| Project: |
NHF-0310/136/ |
State Job: |
C-98-014-03 |
| Letting Date: |
06/12/2009 |
Dist/Cnty: |
08 - 119 (MADISON )
|
| Airport: |
60-15VB-1&2 |
State Job: |
C-98-014-03 |
| Scope: |
FAP-310, IL 255 OVER THE UP & KCS RR 0.21 MI W OF HUMBERT RD
IN VILLAGE OF GODFREY. |
|
|
|
Payee: |
KELLER CONSTRUCTION INC |
22 ILLINI DR GLEN CARBON , IL 62034
|
|
|
|
|
|
|
Contract Awarded
Amount |
Additions |
Deductions |
Total Adjusted
Contract Value |
Total Amount
Due to Date |
| 6,530,185.87 |
43,246.00 |
6,840.00 |
6,566,591.87 |
2,206,458.35 |
|
Total retainage incld this est held by IDOT:
|
|
|
0.00
|
| Total
due after retainage: |
|
|
2,206,458.35 |
| Total
paid this estimate: |
|
|
2,206,458.35 |
|
Previous payments to contractor: |
|
|
-2,204,337.87 |
|
Payment to contractor this estimate: |
|
| 2,120.48 |
| |
|
Voucher # CC13945 | Date: 12/22/2010 |
|
1
of 1
|
2,120.48 |
|
---------------------------------------------------------------------------------------------------------------------------------------------- |
|
|
|
Pay Estimate Number: 06 |
Total: |
2,120.48 |
Report of Resident Engineer
Completed Work-In Place
For This Estimate Only
|
|
|
PAY ITEM |
QUANTITY |
PAYMENT |
|
Number |
Description |
Awarded |
Net of Adds/
Deducts |
Total Adjusted |
Completed Prior Est. |
Completed to Date |
This Estimate |
$ Unit Price |
$ This Estimate |
| M5020100 |
STRUCTURE EXCAVATION |
2,203.000 |
0.000 |
2,203.000 |
0.000 |
139.900 |
139.900 |
9.23 |
1,291.28 |
| M542T215 |
P CUL CL C 1 300 TEM |
51.500 |
0.000 |
51.500 |
0.000 |
12.000 |
12.000 |
69.10 |
829.20 |
|
Total: |
$2,120.48 |
|
|