DOT Vendor: C38100  Contract: 74296 

IL Project:      From Date: 09/16/2011
Route: FAI 57/70
Section: (25-3)R,BY,BR To Date: 10/04/2011
Project: State Job: C-97-042-08
Letting Date: 07/30/2010 Dist/Cnty: 07 - 049 (EFFINGHAM )
Airport: (25-3)R,BY,BR State Job: C-97-042-08
Scope: FAI-57/70, S OF EFFINGHAM.

Payee:

MCCARTHY IMPROVEMENT CO 5401 VICTORIA AVENUE SUITE 700  DAVENPORT , IA  52807

 

 

 

 

Percent Completed:  48.74%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
45,780,265.61      1,352,960.36      423,755.00      46,709,470.97      23,662,601.72     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 23,662,601.72     
Total paid this estimate:   23,662,601.72     
     Previous payments to contractor: -21,816,606.66     
     Payment to contractor this estimate: 1,845,995.06     
 
          Voucher #   BC03023 Date: 10/11/2011 1 of 1 1,845,995.06     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  23 Total: 1,845,995.06     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
Z0012200  CONC BR DECK SCAR 1/2   652.000  0.000  652.000  326.000  652.000  326.000  70.00  22,820.00 
Z0030350  IMP ATTN REL NRD TL3   13.000  0.000  13.000  2.000  3.000  1.000  1,300.00  1,300.00 
20200100  EARTH EXCAVATION   119,780.000  0.000  119,780.000  37,148.800  44,280.000  7,131.200  20.00  142,624.00 
20201200  REM & DISP UNS MATL   705.000  300.000  1,005.000  907.810  1,005.000  97.190  30.00  2,915.70 
20400800  FURNISHED EXCAVATION   91,325.000  0.000  91,325.000  78,977.000  79,025.000  48.000  20.00  960.00 
28100107  STONE RIPRAP CL A4   12,811.000  0.000  12,811.000  1,441.800  2,093.000  651.200  45.00  29,304.00 
28200200  FILTER FABRIC   12,811.000  0.000  12,811.000  1,441.800  2,093.000  651.200  2.00  1,302.40 
30200650  PROCESS MOD SOIL 12   132,106.000  2,044.500  134,150.500  75,599.000  78,803.100  3,204.100  3.00  9,612.30 
31200500  STAB SUBBASE HMA 4   136,991.000  0.000  136,991.000  59,809.100  62,786.700  2,977.600  20.00  59,552.00 
40800050  INCIDENTAL HMA SURF   349.000  0.000  349.000  0.000  20.550  20.550  150.00  3,082.50 
42000501  PCC PVT 10 JOINTED   4,594.000  0.000  4,594.000  63.400  1,611.100  1,547.700  55.00  85,123.50 
42000540  PCC PVT 12   31,393.000  7,563.000  38,956.000  31,322.700  33,707.700  2,385.000  55.00  131,175.00 
42001200  PAVEMENT FABRIC   31,415.000  7,561.200  38,976.200  31,141.100  32,825.300  1,684.200  10.00  16,842.00 
42100360  CONT REINF PCC PVT 13   124,143.000  0.000  124,143.000  37,156.500  46,697.200  9,540.700  51.00  486,575.70 
42100960  PAVT REINFORCEMENT 13   124,143.000  0.000  124,143.000  37,156.500  46,697.200  9,540.700  20.00  190,814.00 
42101080  WF BM TERM JT COM SPL   4.000  0.000  4.000  0.000  2.000  2.000  55,000.00  110,000.00 
44000100  PAVEMENT REM   75,297.000  0.000  75,297.000  40,557.800  42,254.800  1,697.000  10.00  16,970.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
44004400  PAVT REMOVAL SPL   29,495.000  4,472.000  33,967.000  0.000  897.600  897.600  10.00  8,976.00 
48101500  AGGREGATE SHLDS B 6   7,528.000  0.000  7,528.000  0.000  97.600  97.600  9.00  878.40 
50104650  SLOPE WALL REMOV   1,826.000  420.000  2,246.000  927.800  952.200  24.400  30.00  732.00 
50300100  FLOOR DRAINS   109.000  0.000  109.000  27.000  54.000  27.000  400.00  10,800.00 
50300225  CONC STRUCT   1,816.000  0.000  1,816.000  759.600  769.000  9.400  600.00  5,640.00 
50300255  CONC SUP-STR   2,076.900  0.000  2,076.900  541.600  910.200  368.600  900.00  331,740.00 
50800205  REINF BARS, EPOXY CTD   790,760.000  0.000  790,760.000  298,371.600  381,228.600  82,857.000  0.75  62,142.75 
50800515  BAR SPLICERS   4,015.000  0.000  4,015.000  2,548.000  3,895.000  1,347.000  6.00  8,082.00 
51100100  SLOPE WALL 4   400.000  420.000  820.000  414.400  423.200  8.800  135.00  1,188.00 
52000110  PREF JT STRIP SEAL   334.000  0.000  334.000  88.800  161.000  72.200  300.00  21,660.00 
60107700  PIPE UNDERDRAINS 6   40,190.000  0.000  40,190.000  0.000  4,113.000  4,113.000  8.00  32,904.00 
60108200  PIPE UNDERDRAIN 6 SP   902.000  0.000  902.000  0.000  70.000  70.000  20.00  1,400.00 
60240220  INLETS TB T3F&G   15.000  0.000  15.000  2.000  4.000  2.000  2,350.00  4,700.00 
60605000  COMB CC&G TB6.24   3,222.000  0.000  3,222.000  0.000  283.700  283.700  26.00  7,376.20 
63000001  SPBGR TY A 6FT POSTS   14,250.000  0.000  14,250.000  0.000  625.000  625.000  16.00  10,000.00 
63100085  TRAF BAR TERM T6   14.000  0.000  14.000  0.000  1.000  1.000  2,500.00  2,500.00 
63100167  TR BAR TRM T1 SPL TAN   15.000  0.000  15.000  0.000  1.000  1.000  2,200.00  2,200.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
63200310  GUARDRAIL REMOV   12,267.000  0.000  12,267.000  7,265.300  8,390.300  1,125.000  3.00  3,375.00 
70400100  TEMP CONC BARRIER   26,762.500  0.000  26,762.500  24,950.000  25,700.000  750.000  28.00  21,000.00 
70400200  REL TEMP CONC BARRIER   29,512.500  0.000  29,512.500  312.500  2,075.000  1,762.500  6.00  10,575.00 
78200410  GUARDRAIL MKR TYPE A   112.000  0.000  112.000  0.000  9.000  9.000  7.50  67.50 
78201000  TERMINAL MARKER - DA   15.000  0.000  15.000  0.000  1.000  1.000  27.00  27.00 
MATALL00  MATERIAL ALLOWANCE   0.000  0.000  0.000  0.000  0.000  0.000  0.00  -12,941.89 
Total:   

$1,845,995.06

 