Contractor Invoice

Previous Report 07/26/2012
DOT Vendor: C12840  Contract: 68914 

IL Project:      From Date: 06/13/2012
Route: FAI 155
Section: 90108RS-4;(107,106,106X)RS-2 To Date: 07/26/2012
Project: IM-155-1/010/031 State Job: C-94-123-09
Letting Date: 03/09/2012 Dist/Cnty: 04 - 179 (TAZEWELL )
Airport: 90108RS-4;(107,106,106X)RS-2 State Job: C-94-123-09
Scope: FAI-155, ON BROADWAY EXIT, VARIOUS LOCATIONS, FROM N OF BIR-
CHWOOD AVE TO S OF FEATHER RD N OF HOPEDALE. 10.91MI.

Payee:

UNITED CONTRACTORS MIDWEST INC 3151 ROBBINS RD  SPRINGFIELD , IL  62704

 

 

 

 

Percent Completed:  18.03%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
18,653,556.91      5,987,844.81      5,556,830.16      19,084,571.56      3,441,314.70     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 3,441,314.70     
Total paid this estimate:   3,441,314.70     
     Previous payments to contractor: -1,871,059.29     
     Payment to contractor this estimate: 1,570,255.41     
 
          Voucher #   BC00405 Date: 07/31/2012 1 of 1 1,570,255.41     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  04 Total: 1,570,255.41     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X0322936  REMOV EX FLAR END SEC   1.000  0.000  1.000  0.000  1.000  1.000  455.74  455.74 
X0327116  SOLAR POWER ASSEMBLY   1.000  0.000  1.000  0.000  1.000  1.000  1,837.50  1,837.50 
X2503100  MOWING   3,057.000  0.000  3,057.000  0.000  576.000  576.000  11.76  6,773.76 
X5420624  PIPE CULV CLEANED 24   584.000  0.000  584.000  0.000  319.500  319.500  21.91  7,000.25 
X5420636  PIPE CULV CLEANED 36   181.000  0.000  181.000  0.000  181.000  181.000  28.27  5,116.87 
Z0010615  CLEAN EX INLETS   2.000  0.000  2.000  0.000  1.000  1.000  552.11  552.11 
Z0040530  PIPE UNDERDRAIN REMOV   71,457.000  109,971.000  181,428.000  3,390.000  15,735.000  12,345.000  0.13  1,604.85 
21101615  TOPSOIL F & P 4   1,954.000  0.000  1,954.000  0.000  1,785.000  1,785.000  2.31  4,123.35 
40600200  BIT MATLS PR CT   122.000  0.000  122.000  0.000  13.640  13.640  610.51  8,327.36 
40600895  CONSTRUC TEST STRIP   2.000  0.000  2.000  0.000  1.000  1.000  4,967.31  4,967.31 
40600985  PCC SURF REM BUTT JT   3,073.000  0.000  3,073.000  0.000  400.000  400.000  16.45  6,580.00 
40603216  P HMA BC IL12.5 N90   38,230.000  0.000  38,230.000  0.000  506.270  506.270  96.76  48,986.69 
44000155  HMA SURF REM 1 1/2   494,021.000  -23,285.000  470,736.000  0.000  50,608.740  50,608.740  2.31  116,906.19 
44000164  HMA SURF REM 3 3/4   9,581.000  0.000  9,581.000  0.000  2,388.000  2,388.000  2.74  6,543.12 
44004250  PAVED SHLD REMOVAL   60,856.000  -29,250.500  31,605.500  9,590.100  24,082.630  14,492.530  8.86  128,403.81 
54213669  PRC FLAR END SEC 24   1.000  0.000  1.000  0.000  1.000  1.000  1,260.00  1,260.00 
54215559  MET END SEC 24   2.000  0.000  2.000  0.000  1.000  1.000  262.50  262.50 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
60107600  PIPE UNDERDRAINS 4   71,457.000  102,338.000  173,795.000  66,992.800  130,721.800  63,729.000  5.86  373,451.94 
60108100  PIPE UNDERDRAIN 4 SP   2,475.000  5,158.500  7,633.500  620.000  6,750.700  6,130.700  20.84  127,763.79 
67000400  ENGR FIELD OFFICE A   9.000  0.000  9.000  1.230  2.230  1.000  2,380.72  2,380.72 
70100800  TRAF CONT-PROT 701401   1.000  0.000  1.000  0.374  0.472  0.098  5,250.00  514.50 
70100820  TRAF CONT-PROT 701451   1.000  0.000  1.000  0.029  0.126  0.097  5,250.00  509.25 
70300100  SHORT TERM PAVT MKING   73,942.000  0.000  73,942.000  0.000  352.000  352.000  0.92  323.84 
81028730  UNDRGRD C CNC 1 1/4   166.000  0.000  166.000  0.000  24.000  24.000  27.98  671.52 
81028770  UNDRGRD C CNC 3   203.000  0.000  203.000  0.000  177.400  177.400  24.68  4,378.23 
81400200  HD HANDHOLE   4.000  0.000  4.000  0.000  4.000  4.000  1,674.75  6,699.00 
86300300  CONT CAB TYPE III   1.000  0.000  1.000  0.000  1.000  1.000  2,992.50  2,992.50 
87800215  CONC FDN TY D   1.000  0.000  1.000  0.000  1.000  1.000  1,811.25  1,811.25 
88600100  DET LOOP T1   515.000  0.000  515.000  0.000  78.700  78.700  12.60  991.62 
FRC00500  PARTIAL DEPTH REPAIR   0.000  10,000.000  10,000.000  0.000  10,000.000  10,000.000  1.00  10,000.00 
FRC00802  HMA PLUG   0.000  690,774.000  690,774.000  0.000  103,616.000  103,616.000  1.00  103,616.00 
X9400100  TREE REMOVAL   0.000  1.000  1.000  0.000  1.000  1.000  525.00  525.00 
X9400800  REM & REINSTALL HEADW   0.000  336.000  336.000  0.000  281.000  281.000  217.10  61,005.10 
X9400801  CONC HDWL FOR PU   0.000  99.000  99.000  0.000  85.000  85.000  195.85  16,647.25 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X9400803  HMA SHOULDERS   0.000  40,724.000  40,724.000  2,280.480  8,083.030  5,802.550  87.25  506,272.49 
Total:   

$1,570,255.41

 