Previous Report 11/02/2012
DOT Vendor: C12320  Contract: 68691 

IL Project:      From Date: 09/25/2012
Route: FAP 310
Section: (38B-2)BR To Date: 11/02/2012
Project: NHF-0310/147/ State Job: C-94-023-07
Letting Date: 03/09/2012 Dist/Cnty: 04 - 109 (MCDONOUGH )
Airport: (38B-2)BR State Job: C-94-023-07
Scope: FAP-310, US67 OVER FARMERS FORK CK S OF US67/IL 9 INTERSCTN,
3MI N OF MACOMB.

Payee:

COUNTY CONTRACTORS INC PO BOX 3522  QUINCY , IL  62305

 

 

 

 

Percent Completed:  52.55%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
4,018,777.15      184,421.45      168,097.33      4,035,101.27      2,120,377.61     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 2,120,377.61     
Total paid this estimate:   2,120,377.61     
     Previous payments to contractor: -1,611,383.11     
     Payment to contractor this estimate: 508,994.50     
 
          Voucher #   CC08645 Date: 11/05/2012 1 of 1 508,994.50     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  05 Total: 508,994.50     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X4400600  END SECTIONS REMOVED   1.000  0.000  1.000  0.000  1.000  1.000  44.56  44.56 
Z0001002  GDRL AGG EROS CONT   514.000  0.000  514.000  0.000  176.110  176.110  28.77  5,066.68 
Z0034105  MATL TRANSFER DEVICE   896.000  0.000  896.000  0.000  461.430  461.430  7.84  3,617.61 
Z0076600  TRAINEES   1,000.000  0.000  1,000.000  150.500  369.500  219.000  0.80  175.20 
20200100  EARTH EXCAVATION   3,075.000  0.000  3,075.000  181.700  1,457.000  1,275.300  9.85  12,561.70 
20300100  CHANNEL EXCAVATION   2,036.000  0.000  2,036.000  0.000  387.000  387.000  6.38  2,469.06 
20400800  FURNISHED EXCAVATION   4,165.000  0.000  4,165.000  1,712.000  2,481.000  769.000  7.76  5,967.44 
21101615  TOPSOIL F & P 4   10,656.000  0.000  10,656.000  0.000  4,547.400  4,547.400  1.52  6,912.05 
25000210  SEEDING CL 2A   3.250  0.000  3.250  0.000  0.950  0.950  775.00  736.25 
25000400  NITROGEN FERT NUTR   290.000  0.000  290.000  0.000  85.500  85.500  1.30  111.15 
25000500  PHOSPHORUS FERT NUTR   290.000  0.000  290.000  0.000  85.500  85.500  1.30  111.15 
25000600  POTASSIUM FERT NUTR   290.000  0.000  290.000  0.000  85.500  85.500  1.30  111.15 
25100630  EROSION CONTR BLANKET   406.000  0.000  406.000  0.000  406.000  406.000  3.52  1,429.12 
28000250  TEMP EROS CONTR SEED   650.000  0.000  650.000  144.000  194.000  50.000  2.23  111.50 
28100807  STONE DUMP RIP CL A4   2,311.000  0.000  2,311.000  558.070  889.430  331.360  48.97  16,226.70 
28200200  FILTER FABRIC   2,858.000  0.000  2,858.000  798.900  1,369.100  570.200  3.18  1,813.24 
40600215  P BIT MATLS PR CT   24.100  0.000  24.100  4.500  8.590  4.090  1,002.42  4,099.90 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
40600982  HMA SURF REM BUTT JT   2,228.000  0.000  2,228.000  0.000  1,563.530  1,563.530  12.92  20,200.81 
40603085  HMA BC IL-19.0 N70   6,720.000  0.000  6,720.000  4,372.920  4,592.650  219.730  101.01  22,194.93 
40603235  P HMA BC IL19.0 N70   993.000  0.000  993.000  0.000  602.960  602.960  115.75  69,792.62 
40603540  P HMA SC "D" N70   1,666.000  -636.000  1,030.000  0.000  650.610  650.610  113.13  73,603.51 
42001430  BR APPR PVT CON (FLX)   125.000  0.000  125.000  0.000  59.000  59.000  115.78  6,831.02 
48101200  AGGREGATE SHLDS B   711.000  0.000  711.000  0.000  132.530  132.530  25.40  3,366.26 
48203100  HMA SHOULDERS   783.000  0.000  783.000  0.000  87.200  87.200  107.71  9,392.31 
50100100  REM EXIST STRUCT   2.000  0.000  2.000  0.500  1.000  0.500  44,677.93  22,338.96 
50300255  CONC SUP-STR   781.800  0.000  781.800  186.370  344.810  158.440  685.50  108,610.62 
50300260  BR DECK GROOVING   1,706.000  0.000  1,706.000  0.000  754.000  754.000  7.00  5,278.00 
50300300  PROTECTIVE COAT   2,052.000  0.000  2,052.000  0.000  920.500  920.500  2.30  2,117.15 
50800205  REINF BARS, EPOXY CTD   203,190.000  0.000  203,190.000  57,263.500  91,850.000  34,586.500  1.27  43,924.85 
51500100  NAME PLATES   2.000  0.000  2.000  0.000  1.000  1.000  345.00  345.00 
60100060  CONC HDWL FOR P DRAIN   20.000  0.000  20.000  0.000  3.000  3.000  129.26  387.78 
60108100  PIPE UNDERDRAIN 4 SP   132.000  0.000  132.000  0.000  50.000  50.000  17.53  876.50 
63000001  SPBGR TY A 6FT POSTS   975.000  0.000  975.000  0.000  450.000  450.000  18.00  8,100.00 
63100045  TRAF BAR TERM T2   1.000  0.000  1.000  0.000  1.000  1.000  900.00  900.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
63100085  TRAF BAR TERM T6   6.000  0.000  6.000  0.000  4.000  4.000  2,650.00  10,600.00 
63100167  TR BAR TRM T1 SPL TAN   6.000  0.000  6.000  0.000  4.000  4.000  2,140.00  8,560.00 
63100169  TR BAR TRM T1 SPL FLR   1.000  0.000  1.000  0.000  1.000  1.000  2,000.00  2,000.00 
67000400  ENGR FIELD OFFICE A   18.000  0.000  18.000  4.000  5.000  1.000  1,580.10  1,580.10 
67000600  ENGR FIELD LAB   18.000  0.000  18.000  4.000  5.000  1.000  857.05  857.05 
70300210  TEMP PVT MK LTR & SYM   141.000  0.000  141.000  0.000  31.200  31.200  20.00  624.00 
70300220  TEMP PVT MK LINE 4   10,913.000  0.000  10,913.000  0.000  6,418.000  6,418.000  1.00  6,418.00 
70300240  TEMP PVT MK LINE 6   1,420.000  0.000  1,420.000  0.000  310.000  310.000  2.00  620.00 
70300250  TEMP PVT MK LINE 8   702.000  0.000  702.000  0.000  240.000  240.000  2.50  600.00 
70300280  TEMP PVT MK LINE 24   43.000  0.000  43.000  0.000  36.000  36.000  13.00  468.00 
70301000  WORK ZONE PAVT MK REM   12,096.000  0.000  12,096.000  0.000  4,020.700  4,020.700  1.20  4,824.84 
70400100  TEMP CONC BARRIER   2,204.000  0.000  2,204.000  2,175.000  2,204.000  29.000  9.85  285.65 
70400200  REL TEMP CONC BARRIER   2,204.000  0.000  2,204.000  0.000  412.500  412.500  12.43  5,127.38 
78200410  GUARDRAIL MKR TYPE A   30.000  0.000  30.000  12.000  23.000  11.000  8.00  88.00 
78200530  BAR WALL MKR TYPE C   270.000  0.000  270.000  264.000  270.000  6.000  6.00  36.00 
78201000  TERMINAL MARKER - DA   7.000  0.000  7.000  0.000  5.000  5.000  30.00  150.00 
X9400600  BIT MATLS PR CT MC-30   0.000  9.000  9.000  0.000  3.810  3.810  1,474.20  5,616.70 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X9400601  MOWING REVISED   0.000  24.500  24.500  0.000  4.250  4.250  168.00  714.00 
Total:   

$508,994.50

 