DOT Vendor: C40450  Contract: 68482 

IL Project:      From Date: 08/24/2011
Route: FAP 542
Section: 105BR-1 To Date: 09/27/2011
Project: BRF-0542/005/ State Job: C-94-073-05
Letting Date: 04/29/2011 Dist/Cnty: 04 - 109 (MCDONOUGH )
Airport: 105BR-1 State Job: C-94-073-05
Scope: FAP-542, IL 61 OVER THE LAMOINE RIVER LOCATED 1MI S OF
COLMAR.

Payee:

MIDWEST BRIDGE AND CRANE INC 135 S CHESTNUT ST PO BOX 188  GOOD HOPE , IL  61438

 

 

 

 

Percent Completed:  24.98%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
4,914,007.74      0.00      0.00      4,914,007.74      1,227,329.83     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 1,227,329.83     
Total paid this estimate:   1,227,329.83     
     Previous payments to contractor: -695,854.20     
     Payment to contractor this estimate: 531,475.63     
 
          Voucher #   CC06286 Date: 09/29/2011 1 of 1 531,475.63     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  03 Total: 531,475.63     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X3112700  COARSE AGGR FILL   1,627.000  0.000  1,627.000  1,131.980  1,399.380  267.400  22.47  6,008.48 
X5080600  MECHANICAL SPLICERS   310.000  0.000  310.000  0.000  14.000  14.000  49.13  687.82 
X6660410  REMOVE ROW MARKERS   5.000  0.000  5.000  0.000  5.000  5.000  115.20  576.00 
X7010216  TRAF CONT & PROT SPL   1.000  0.000  1.000  0.250  0.330  0.080  39,378.34  3,150.26 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.000  0.250  0.250  44,307.56  11,076.89 
Z0026407  TEMP SHT PILING   1,904.000  0.000  1,904.000  0.000  1,904.000  1,904.000  42.48  80,881.92 
Z0054500  ROCK FILL   4,825.000  0.000  4,825.000  3,265.000  3,598.000  333.000  17.21  5,730.93 
20200100  EARTH EXCAVATION   6,990.000  0.000  6,990.000  0.000  2,446.000  2,446.000  11.85  28,985.10 
20400800  FURNISHED EXCAVATION   14,609.000  0.000  14,609.000  0.000  7,304.000  7,304.000  18.08  132,056.32 
28000250  TEMP EROS CONTR SEED   1,395.000  0.000  1,395.000  250.000  550.000  300.000  2.22  666.00 
50100100  REM EXIST STRUCT   1.000  0.000  1.000  0.300  0.500  0.200  167,845.88  33,569.18 
50105220  PIPE CULVERT REMOV   221.000  0.000  221.000  0.000  107.300  107.300  7.37  790.80 
50200300  COFFERDAM EXCAVATION   352.000  0.000  352.000  0.000  169.000  169.000  16.02  2,707.38 
50202901  COFFERDAM LOCATION 1   1.000  0.000  1.000  0.000  0.500  0.500  74,114.49  37,057.25 
50300225  CONC STRUCT   490.500  0.000  490.500  0.000  12.400  12.400  589.29  7,307.20 
50300265  SEAL COAT CONC   61.500  0.000  61.500  0.000  30.600  30.600  114.41  3,500.95 
50300280  CONCRETE ENCASEMENT   22.500  0.000  22.500  0.000  1.600  1.600  650.44  1,040.70 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
50800205  REINF BARS, EPOXY CTD   228,400.000  0.000  228,400.000  0.000  9,738.800  9,738.800  1.12  10,907.46 
50800515  BAR SPLICERS   1,893.000  0.000  1,893.000  0.000  162.000  162.000  12.18  1,973.16 
51201600  FUR STL PILE HP12X53   1,301.000  0.000  1,301.000  0.000  426.000  426.000  37.40  15,932.40 
51201800  FUR STL PILE HP14X73   1,305.000  0.000  1,305.000  0.000  659.000  659.000  47.77  31,480.43 
51202000  FUR STL PILE HP14X102   2,112.000  0.000  2,112.000  0.000  1,160.000  1,160.000  65.58  76,072.80 
51203600  TEST PILE ST HP12X53   1.000  0.000  1.000  0.000  1.000  1.000  4,133.26  4,133.26 
51203800  TEST PILE ST HP14X73   1.000  0.000  1.000  0.000  1.000  1.000  4,217.45  4,217.45 
51204000  TEST PILE ST HP14X102   4.000  0.000  4.000  0.000  4.000  4.000  5,108.58  20,434.32 
51204650  PILE SHOES   76.000  0.000  76.000  0.000  35.000  35.000  120.97  4,233.95 
67000400  ENGR FIELD OFFICE A   16.000  0.000  16.000  1.000  3.000  2.000  1,329.23  2,658.46 
67000600  ENGR FIELD LAB   16.000  0.000  16.000  1.000  3.000  2.000  822.46  1,644.92 
70106800  CHANGEABLE MESSAGE SN   16.000  0.000  16.000  1.000  2.000  1.000  1,993.84  1,993.84 
Total:   

$531,475.63

 