State of Illinois Department of Transportation

Contract Search

 05/16/2013 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 08/17/2012
DOT Vendor: C13200  Contract: 66B49 

IL Project:      From Date: 06/05/2012
Route: FAI 80
Section: (06-4BR-1)I To Date: 08/17/2012
Project: State Job: C-93-130-11
Letting Date: 04/27/2012 Dist/Cnty: 03 - 011 (BUREAU )
Airport: (06-4BR-1)I State Job: C-93-130-11
Scope: FAI-80, EB & WB FAI RT 80 OVER BUREAU CK APPROX 2 MI W OF IL
RT 26 (NEAR PRINCETON).

Payee:

D CONSTRUCTION INC 1488 S BROADWAY  COAL CITY , IL  60416

 

 

 

 

Percent Completed:  32.6%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
267,538.27      0.00      0.00      267,538.27      89,478.50     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 89,478.50     
Mobilzation Paid:2,250.00     
Total paid this estimate:   89,478.50     
     Previous payments to contractor: -11,250.00     
     Payment to contractor this estimate: 78,228.50     
 
          Voucher #   CC03152 Date: 08/21/2012 1 of 1 78,228.50     

----------------------------------------------------------------------------------------------------------------------------------------------     

Includes 15% mobilization Pay Estimate Number:  01 Total: 78,228.50     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X7010208  TC-PROT 701402 SPL   2.000  0.000  2.000  0.000  0.934  0.934  14,000.00  13,076.00 
Z0016200  DECK SLAB REP (PART)   77.000  0.000  77.000  0.000  5.000  5.000  250.00  1,250.00 
50102400  CONC REM   14.000  0.000  14.000  0.000  7.000  7.000  800.00  5,600.00 
50300255  CONC SUP-STR   14.000  0.000  14.000  0.000  7.000  7.000  1,200.00  8,400.00 
50800205  REINF BARS, EPOXY CTD   2,780.000  0.000  2,780.000  0.000  1,390.000  1,390.000  3.00  4,170.00 
50800515  BAR SPLICERS   28.000  0.000  28.000  0.000  28.000  28.000  20.00  560.00 
52000110  PREF JT STRIP SEAL   176.000  0.000  176.000  0.000  80.000  80.000  160.00  12,800.00 
63300575  R&R RAIL ELEM EX GDRL   15.000  0.000  15.000  0.000  15.000  15.000  50.00  750.00 
67100100  MOBILIZATION   1.000  0.000  1.000  0.750  0.900  0.150  15,000.00  2,250.00 
70400100  TEMP CONC BARRIER   1,126.000  0.000  1,126.000  0.000  1,126.000  1,126.000  25.00  28,150.00 
78300100  PAVT MARKING REMOVAL   2,292.000  0.000  2,292.000  0.000  489.000  489.000  2.50  1,222.50 
Total:   

$78,228.50

 