State of Illinois Department of Transportation

Contract Search

 04/16/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 02/15/2013
DOT Vendor: C00490  Contract: 66A48 

IL Project:      From Date: 01/03/2013
Route: FAI 80
Section: (50-2,4)RS-5 & (50-3)RS-6 To Date: 02/15/2013
Project: IM-080-3/138/080 State Job: C-93-106-11
Letting Date: 03/09/2012 Dist/Cnty: 03 - 099 (LASALLE )
Airport: (50-2,4)RS-5 & (50-3)RS-6 State Job: C-93-106-11
Scope: FAI-80, FROM 0.5MI E OF IL 178 E TO FOX RIVER BR IN OTTAWA.

Payee:

ADVANCED ASPHALT COMPANY PO BOX 234  PRINCETON , IL  61356

 

 

 

 

Percent Completed:  97.44%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
20,270,431.75      5,160,634.57      5,148,373.71      20,282,692.61      19,762,654.28     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 19,762,654.28     
Total paid this estimate:   19,762,654.28     
     Previous payments to contractor: -19,255,379.78     
     Payment to contractor this estimate: 507,274.50     
 
          Voucher #   BC04966 Date: 02/21/2013 1 of 2 250,496.57     
          Voucher #   CC14579 Date: 02/21/2013 2 of 2 256,777.93     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  15 Total: 507,274.50     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X6650202  WOV W FENCE REMOV   10,700.000  -261.500  10,438.500  10,321.000  10,438.500  117.500  1.95  229.13 
X7830070  GRV RCSD PVT MRKG 5   265,915.000  -16,243.700  249,671.300  249,462.360  249,671.300  208.940  0.50  104.47 
X7830076  GRV RCSD PVT MRKG 9   1,400.000  7,531.000  8,931.000  1,400.000  8,931.000  7,531.000  1.00  7,531.00 
25000300  SEEDING CL 3   3.800  0.500  4.300  3.820  4.300  0.480  1,800.00  864.00 
25000400  NITROGEN FERT NUTR   341.000  51.000  392.000  338.000  392.000  54.000  2.00  108.00 
25000500  PHOSPHORUS FERT NUTR   341.000  51.000  392.000  338.000  392.000  54.000  2.00  108.00 
25000600  POTASSIUM FERT NUTR   341.000  51.000  392.000  338.000  392.000  54.000  2.00  108.00 
25100635  HD EROS CONTR BLANKET   15,338.000  -3,940.460  11,397.540  8,770.850  11,397.540  2,626.690  1.50  3,940.04 
40603243  P HMA BC IL19.0FGN90   57,791.000  -871.640  56,919.360  56,067.060  56,919.260  852.200  88.00  74,993.60 
40603570  P HMA SC "E" N90   32,885.000  1,892.440  34,777.440  34,617.740  34,777.440  159.700  95.00  15,171.50 
50102400  CONC REM   13.500  0.100  13.600  13.500  13.600  0.100  600.00  60.00 
50200100  STRUCTURE EXCAVATION   100.000  5.870  105.870  100.000  105.870  5.870  35.00  205.45 
50800205  REINF BARS, EPOXY CTD   5,418.000  50.000  5,468.000  5,418.000  5,468.000  50.000  2.00  100.00 
54003000  CONC BOX CUL   37.600  -5.700  31.900  31.200  31.900  0.700  1,000.00  700.00 
63000001  SPBGR TY A 6FT POSTS   6,399.000  -2,474.000  3,925.000  3,043.000  3,925.000  882.000  18.50  16,317.00 
63100045  TRAF BAR TERM T2   9.000  -3.000  6.000  4.000  6.000  2.000  900.00  1,800.00 
63100085  TRAF BAR TERM T6   14.000  0.000  14.000  10.000  14.000  4.000  2,650.00  10,600.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
63100167  TR BAR TRM T1 SPL TAN   16.000  0.000  16.000  14.000  16.000  2.000  2,250.00  4,500.00 
63200310  GUARDRAIL REMOV   5,797.000  93.000  5,890.000  4,773.000  5,890.000  1,117.000  4.75  5,305.75 
63500105  DELINEATORS   479.000  111.000  590.000  366.000  461.000  95.000  40.00  3,800.00 
64200116  SHOULDER RUM STRIP 16   244,360.000  -5,734.700  238,625.300  220,558.940  238,625.300  18,066.360  0.15  2,709.95 
66500105  WOV W FENCE 4   10,700.000  327.500  11,027.500  10,700.000  11,027.500  327.500  8.00  2,620.00 
70300220  TEMP PVT MK LINE 4   255,515.000  166,954.150  422,469.150  255,515.000  422,469.150  166,954.150  0.20  33,390.83 
70300240  TEMP PVT MK LINE 6   31,939.000  42,023.000  73,962.000  31,939.000  73,962.000  42,023.000  0.50  21,011.50 
78004230  PREF PL PM TB INL L6   31,939.000  -1,412.000  30,527.000  29,618.000  30,527.000  909.000  7.00  6,363.00 
78009004  MOD URETH PM LINE 4   265,915.000  -9,709.500  256,205.500  225,325.500  256,205.500  30,880.000  0.90  27,792.00 
78009008  MOD URETH PM LINE 8   1,400.000  6,709.000  8,109.000  200.000  8,109.000  7,909.000  1.80  14,236.20 
78009012  MOD URETH PM LINE 12   600.000  831.000  1,431.000  385.000  1,431.000  1,046.000  5.00  5,230.00 
78100100  RAISED REFL PAVT MKR   3,194.000  126.000  3,320.000  2,736.000  3,320.000  584.000  34.50  20,148.00 
78200410  GUARDRAIL MKR TYPE A   68.000  7.000  75.000  54.000  75.000  21.000  8.00  168.00 
78201000  TERMINAL MARKER - DA   16.000  0.000  16.000  14.000  16.000  2.000  30.00  60.00 
FRC00200  SHOULDER CLEAN UP   0.000  13,457.730  13,457.730  12,000.000  13,457.730  1,457.730  1.00  1,457.73 
FRC00801  CABLE RAIL REPAIR   0.000  6,946.980  6,946.980  0.000  6,946.980  6,946.980  1.00  6,946.98 
FRC00901  CABLE RAIL REPAIR   0.000  14,423.940  14,423.940  0.000  10,000.000  10,000.000  1.00  10,000.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
FRC01200  TREE REMOVAL MOBILIZAT   0.000  1,900.000  1,900.000  1,000.000  1,900.000  900.000  1.00  900.00 
FRC01500  CABLE RAIL REPAIR   0.000  6,000.000  6,000.000  0.000  6,000.000  6,000.000  1.00  6,000.00 
FRC01600  CABLE RAIL REPAIR   0.000  5,000.000  5,000.000  126.020  3,047.620  2,921.600  1.00  2,921.60 
FRC01700  CABLE RAIL RESTOCKING   0.000  3,000.000  3,000.000  0.000  3,000.000  3,000.000  1.00  3,000.00 
FRC01800  CABLE RAIL REPAIR   0.000  5,000.000  5,000.000  126.020  3,595.700  3,469.680  1.00  3,469.68 
FRC02000  CABLE RAIL REPAIR   0.000  5,000.000  5,000.000  126.020  2,746.050  2,620.030  1.00  2,620.03 
FRC02200  CABLE RAIL REPAIR   0.000  13,000.000  13,000.000  126.020  3,406.820  3,280.800  1.00  3,280.80 
FRC02300  SEAL EXPANSION PATCHES   0.000  3,000.000  3,000.000  0.000  3,000.000  3,000.000  1.00  3,000.00 
XXX16000  TRAFFIC CONTROL DEFICI   0.000  1.000  1.000  0.000  1.000  1.000  -2,500.00  -2,500.00 
XXX19800  PFP DISINCENTIVE   0.000  116,689.930  116,689.930  94,250.750  116,689.930  22,439.180  -1.00  -22,439.18 
XXX21300  SMOOTH INC BIT HMA SC   0.000  4,000.000  4,000.000  0.000  4,000.000  4,000.000  1.00  4,000.00 
X9300101  HMA SHOULDERS 7 1/2   0.000  13,215.630  13,215.630  12,862.360  13,215.630  353.270  31.95  11,286.98 
X9300102  HMA SHOULDERS 8 1/2   0.000  35,882.730  35,882.730  30,654.450  35,882.730  5,228.280  36.50  190,832.22 
X9300103  HMA SHOULDERS 10   0.000  2,025.070  2,025.070  1,988.580  2,025.070  36.490  60.90  2,222.24 
Total:   

$507,274.50

 