DOT Vendor: C15540  Contract: 66409 

IL Project:      From Date: 12/04/2012
Route: FAI 57
Section: (46-2)I,HBR,VBR To Date: 12/20/2012
Project: IM-057-6/190/306 State Job: C-93-007-04
Letting Date: 04/29/2011 Dist/Cnty: 03 - 091 (KANKAKEE )
Airport: (46-2)I,HBR,VBR State Job: C-93-007-04
Scope: FAI-57, INTERCHANGE @ IL50 IN KANKAKEE CO.

Payee:

DUNNET BAY CONST/K-FIVE CONST 115 NORTH BRANDON DRIVE  GLENDALE HEIGHTS , IL  60139

 

 

 

 

Percent Completed:  71.8%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
39,534,651.70      6,378,055.04      3,422,603.04      42,490,103.70      30,916,298.92     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 30,916,298.92     
Total paid this estimate:   30,916,298.92     
     Previous payments to contractor: -30,166,636.26     
     Payment to contractor this estimate: 749,662.66     
 
          Voucher #   CC11717 Date: 12/24/2012 1 of 1 749,662.66     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  31 Total: 749,662.66     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X0326907  PORT VHMNT CH MSS SGN   35.000  0.000  35.000  15.000  17.000  2.000  3,200.00  6,400.00 
X2130010  EXPLOR TRENCH SPL   250.000  0.000  250.000  25.000  172.000  147.000  7.50  1,102.50 
X6013600  PIPE UNDERDRAIN 4 MOD   43,381.900  5,500.000  48,881.900  36,514.900  46,412.900  9,898.000  7.00  69,286.00 
Z0001050  AGG SUBGRADE 12   110,580.000  5,238.700  115,818.700  88,766.800  101,974.500  13,207.700  8.00  105,661.60 
Z0001058  AGG SUBGRADE 18   1,066.000  18,207.400  19,273.400  14,331.400  16,094.700  1,763.300  20.00  35,266.00 
Z0001060  AGG SUBGRADE 24   1,979.000  10,486.900  12,465.900  11,180.100  12,015.900  835.800  28.00  23,402.40 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.690  0.750  0.060  215,000.00  12,900.00 
Z0034105  MATL TRANSFER DEVICE   7,438.000  0.000  7,438.000  0.000  1,302.150  1,302.150  2.50  3,255.38 
20200100  EARTH EXCAVATION   248,559.000  -1,740.000  246,819.000  218,559.000  226,059.000  7,500.000  11.00  82,500.00 
20800150  TRENCH BACKFILL   3,639.000  51.300  3,690.300  3,293.070  3,405.170  112.100  18.00  2,017.80 
21001000  GEOTECH FAB F/GR STAB   3,044.000  100,110.100  103,154.100  85,424.500  99,680.700  14,256.200  2.00  28,512.40 
25100115  MULCH METHOD 2   70.400  0.000  70.400  3.900  11.790  7.890  350.00  2,761.50 
28000305  TEMP DITCH CHECKS   4,100.000  0.000  4,100.000  3,168.000  3,432.000  264.000  8.50  2,244.00 
42000501  PCC PVT 10 JOINTED   42,331.000  0.000  42,331.000  23,430.300  23,629.000  198.700  42.00  8,345.40 
50100400  REM EXIST STRUCT N2   1.000  0.000  1.000  0.850  1.000  0.150  330,000.00  49,500.00 
50100600  REM EXIST STRUCT N4   1.000  0.000  1.000  0.900  1.000  0.100  340,000.00  34,000.00 
50300225  CONC STRUCT   2,291.600  49.600  2,341.200  1,782.730  1,970.120  187.390  700.00  131,173.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
50300280  CONCRETE ENCASEMENT   35.000  0.000  35.000  28.480  34.410  5.930  600.00  3,558.00 
50800205  REINF BARS, EPOXY CTD   1,006,838.000  5,108.000  1,011,946.000  729,787.600  745,166.600  15,379.000  1.35  20,761.65 
51201500  FUR STL PILE HP10X57   3,916.000  0.000  3,916.000  3,111.000  3,792.000  681.000  26.00  17,706.00 
51202305  DRIVING PILES   3,916.000  0.000  3,916.000  2,687.000  3,268.590  581.590  0.01  5.82 
51204650  PILE SHOES   98.000  0.000  98.000  81.000  98.000  17.000  100.00  1,700.00 
54213657  PRC FLAR END SEC 12   13.000  1.000  14.000  9.000  13.000  4.000  400.00  1,600.00 
550A0050  STORM SEW CL A 1 12   1,152.800  0.000  1,152.800  323.000  553.000  230.000  29.00  6,670.00 
550A0340  STORM SEW CL A 2 12   3,550.000  80.000  3,630.000  2,946.000  3,490.500  544.500  24.00  13,068.00 
55100500  STORM SEWER REM 12   939.300  243.000  1,182.300  664.300  734.300  70.000  7.00  490.00 
60201340  CB TA 4 DIA T24F&G   19.000  0.000  19.000  10.000  17.000  7.000  1,300.00  9,100.00 
60218400  MAN TA 4 DIA T1F CL   11.000  1.000  12.000  5.000  10.000  5.000  1,200.00  6,000.00 
60237470  INLETS TA T24F&G   7.000  0.000  7.000  5.000  6.000  1.000  640.00  640.00 
60240328  INLETS TB T24F&G   3.000  0.000  3.000  0.000  2.000  2.000  850.00  1,700.00 
60605000  COMB CC&G TB6.24   10,738.000  0.000  10,738.000  2,384.000  2,735.000  351.000  18.00  6,318.00 
70106800  CHANGEABLE MESSAGE SN   140.000  0.000  140.000  106.000  122.000  16.000  800.00  12,800.00 
70301000  WORK ZONE PAVT MK REM   88,414.000  -35,350.000  53,064.000  16,396.200  16,706.400  310.200  0.30  93.06 
FRC06900  TEMP PVMT @ RAMP F   0.000  65,000.000  65,000.000  0.000  848.890  848.890  1.00  848.89 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
FRC07400  FIX 2.1 RAMP E SLOPE   0.000  50,000.000  50,000.000  1,724.740  50,000.000  48,275.260  1.00  48,275.26 
Total:   

$749,662.66

 