Illinois Department of Transportation, Erica Borggren, Acting Secretary
Loading
Patrick J. Quinn, Governor
Traveling PublicMapsProjectsRoad ClosuresNewsDoing BusinessLetting & BiddingCareers@IDOTGeneral Info





State of Illinois Department of Transportation

Contract Search

 07/24/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 06/11/2012
DOT Vendor: C13200  Contract: 66408 

IL Project:      From Date: 06/01/2012
Route: FAI 80
Section: (32,47-4)HBK-4 & (G)N To Date: 06/11/2012
Project: IM-HPP-080-4/189/115 State Job: C-93-006-04
Letting Date: 09/17/2010 Dist/Cnty: 03 - 063 (GRUNDY )
Airport: (32,47-4)HBK-4 & (G)N State Job: C-93-006-04
Scope: FAI-80, FAU401 (BRISBIN RD) INTERSECTION IMPROV US RT 6 & BR
BRISBIN RD,

Payee:

D CONSTRUCTION INC 1488 S BROADWAY  COAL CITY , IL  60416

 

 

 

 

Percent Completed:  72.71%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
18,890,285.03      1,519,752.52      534,412.00      19,875,625.55      14,483,927.35     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 14,483,927.35     
Total paid this estimate:   14,483,927.35     
     Previous payments to contractor: -14,273,786.78     
     Payment to contractor this estimate: 210,140.57     
 
          Voucher #   BC07089 Date: 06/12/2012 1 of 1 210,140.57     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  28 Total: 210,140.57     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
28000250  TEMP EROS CONTR SEED   6,585.000  0.000  6,585.000  6,578.000  6,585.000  7.000  2.50  17.50 
28000305  TEMP DITCH CHECKS   163.000  2,445.000  2,608.000  2,026.000  2,158.000  132.000  14.85  1,960.20 
28000400  PERIMETER EROS BAR   7,703.000  3,951.400  11,654.400  11,196.900  11,626.900  430.000  1.95  838.50 
28000500  INLET & PIPE PROTECT   13.000  28.000  41.000  27.000  31.000  4.000  110.00  440.00 
31200500  STAB SUBBASE HMA 4   56,554.000  0.000  56,554.000  53,788.700  55,994.100  2,205.400  13.50  29,772.90 
40702011  HMA PAVT FD 16 1/2   6,921.000  0.000  6,921.000  3,927.400  4,488.200  560.800  52.00  29,161.60 
42000506  PCC PVT 10 1/4 JOINTD   47,574.000  -3,323.000  44,251.000  41,513.900  42,651.300  1,137.400  45.00  51,183.00 
50300225  CONC STRUCT   679.300  0.000  679.300  556.360  593.560  37.200  700.00  26,040.00 
50800205  REINF BARS, EPOXY CTD   397,320.000  2,884.000  400,204.000  155,999.000  159,247.000  3,248.000  1.15  3,735.20 
52100010  ELAST BEARING ASSY T1   20.000  0.000  20.000  0.000  20.000  20.000  850.00  17,000.00 
52100520  ANCHOR BOLTS 1   40.000  0.000  40.000  0.000  40.000  40.000  45.00  1,800.00 
52100530  ANCHOR BOLTS 1 1/4   20.000  0.000  20.000  0.000  20.000  20.000  60.00  1,200.00 
59100100  GEOCOMPOSITE WALL DR   423.000  0.000  423.000  248.400  324.700  76.300  24.00  1,831.20 
63000001  SPBGR TY A 6FT POSTS   1,337.500  0.000  1,337.500  375.000  937.500  562.500  20.50  11,531.25 
63100085  TRAF BAR TERM T6   6.000  0.000  6.000  2.000  4.000  2.000  2,835.00  5,670.00 
63100169  TR BAR TRM T1 SPL FLR   6.000  0.000  6.000  2.000  4.000  2.000  2,310.00  4,620.00 
78200410  GUARDRAIL MKR TYPE A   34.000  0.000  34.000  9.000  20.000  11.000  8.40  92.40 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
78201000  TERMINAL MARKER - DA   7.000  0.000  7.000  2.000  4.000  2.000  36.75  73.50 
81018500  CON P 2 GALVS   55.000  0.000  55.000  0.000  55.000  55.000  23.00  1,265.00 
81020500  CON P 2 IM   840.000  0.000  840.000  239.000  757.500  518.500  19.11  9,908.54 
81020700  CON P 3 IM   145.000  0.000  145.000  140.000  145.000  5.000  25.00  125.00 
81603000  UD 2#8 #8G XLPUSE 3/4   1,040.000  0.000  1,040.000  0.000  295.000  295.000  2.70  796.50 
81603025  UD 2#4 #4G XLPUSE 1   8,350.000  0.000  8,350.000  1,676.000  6,198.500  4,522.500  4.35  19,672.88 
81603065  UD 2#2#2GXLPUSE 1 1/4   3,820.000  0.000  3,820.000  2,202.000  3,673.000  1,471.000  5.78  8,502.38 
81900200  TR & BKFIL F ELECT WK   18,591.000  0.000  18,591.000  6,533.500  11,845.500  5,312.000  1.93  10,252.16 
MATALL00  MATERIAL ALLOWANCE   0.000  0.000  0.000  0.000  0.000  0.000  0.00  -27,349.14 
Total:   

$210,140.57

 