Contract Search

 07/21/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 12/13/2012
DOT Vendor: C05930  Contract: 64D17 

IL Project:      From Date: 11/28/2012
Route: FAP 316
Section: 4VBR-1 To Date: 12/13/2012
Project: NHF-0316/037/ State Job: C-92-079-07
Letting Date: 11/18/2011 Dist/Cnty: 02 - 141 (OGLE )
Airport: 4VBR-1 State Job: C-92-079-07
Scope: FAP-316, US52/IL26 OVER BNSF RR LOCATED 1MI S OF JUNCTION
WITH US 52.

Payee:

BRANDT CONSTRUCTION COMPANY 700 4TH ST WEST  MILAN , IL  61264

 

 

 

 

Percent Completed:  90.69%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
2,602,639.10      237,808.75      1,023.87      2,839,423.98      2,575,011.20     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 2,575,011.20     
Mobilzation Paid:17,380.00     
Total paid this estimate:   2,575,011.20     
     Previous payments to contractor: -2,435,309.30     
     Payment to contractor this estimate: 139,701.90     
 
          Voucher #   CC11150 Date: 12/14/2012 1 of 1 139,701.90     

----------------------------------------------------------------------------------------------------------------------------------------------     

Includes final mobilization Pay Estimate Number:  14 Total: 139,701.90     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
Z0046304  P UNDR FOR STRUCT 4   144.000  0.000  144.000  134.360  144.000  9.640  21.00  202.44 
Z0065704  BIT CT AG SLOPEWALL 6   723.000  0.000  723.000  0.000  710.200  710.200  15.75  11,185.65 
20200100  EARTH EXCAVATION   225.000  0.000  225.000  179.000  225.000  46.000  16.00  736.00 
20400800  FURNISHED EXCAVATION   165.000  0.000  165.000  119.000  165.000  46.000  26.25  1,207.50 
21101615  TOPSOIL F & P 4   2,648.000  0.000  2,648.000  0.000  2,648.000  2,648.000  3.00  7,944.00 
25100115  MULCH METHOD 2   1.000  0.000  1.000  0.000  1.000  1.000  1,250.00  1,250.00 
28000250  TEMP EROS CONTR SEED   132.000  0.000  132.000  50.000  132.000  82.000  3.50  287.00 
28100105  STONE RIPRAP CL A3   398.000  0.000  398.000  0.000  398.000  398.000  16.00  6,368.00 
28100107  STONE RIPRAP CL A4   27.000  0.000  27.000  0.000  23.100  23.100  48.75  1,126.13 
28200200  FILTER FABRIC   27.000  0.000  27.000  0.000  23.100  23.100  6.00  138.60 
35102000  AGG BASE CSE B 8   265.000  0.000  265.000  0.000  178.900  178.900  14.75  2,638.78 
40800050  INCIDENTAL HMA SURF   33.000  0.000  33.000  0.000  33.000  33.000  150.00  4,950.00 
50300300  PROTECTIVE COAT   2,098.000  0.000  2,098.000  0.000  2,098.000  2,098.000  2.50  5,245.00 
51100100  SLOPE WALL 4   39.000  0.000  39.000  0.000  38.100  38.100  205.00  7,810.50 
63000003  SPBGR TY A 9FT POSTS   900.000  0.000  900.000  450.000  900.000  450.000  26.50  11,925.00 
63100085  TRAF BAR TERM T6   4.000  0.000  4.000  2.000  4.000  2.000  2,800.00  5,600.00 
63100167  TR BAR TRM T1 SPL TAN   2.000  0.000  2.000  1.000  2.000  1.000  2,350.00  2,350.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
63100169  TR BAR TRM T1 SPL FLR   2.000  0.000  2.000  1.000  2.000  1.000  2,175.00  2,175.00 
63500105  DELINEATORS   4.000  0.000  4.000  0.000  4.000  4.000  50.00  200.00 
66600105  FUR ERECT ROW MARKERS   11.000  0.000  11.000  0.000  10.000  10.000  225.00  2,250.00 
67000400  ENGR FIELD OFFICE A   9.000  0.000  9.000  7.030  7.580  0.550  1,550.00  852.50 
67100100  MOBILIZATION   1.000  0.000  1.000  0.890  1.000  0.110  158,000.00  17,380.00 
70301000  WORK ZONE PAVT MK REM   1,367.000  0.000  1,367.000  239.700  857.000  617.300  1.35  833.35 
78001110  PAINT PVT MK LINE 4   5,930.000  0.000  5,930.000  0.000  4,792.000  4,792.000  0.50  2,396.00 
78100100  RAISED REFL PAVT MKR   8.000  0.000  8.000  0.000  8.000  8.000  175.00  1,400.00 
78200410  GUARDRAIL MKR TYPE A   22.000  0.000  22.000  11.000  22.000  11.000  15.00  165.00 
78200520  BAR WALL MKR TYPE B   8.000  0.000  8.000  0.000  8.000  8.000  17.50  140.00 
78201000  TERMINAL MARKER - DA   4.000  0.000  4.000  2.000  4.000  2.000  35.00  70.00 
XXX02100  RAILROAD FLAGGERS   0.000  210,000.000  210,000.000  36,308.730  77,184.180  40,875.450  1.00  40,875.45 
Total:   

$139,701.90

 