Contract Search

 07/28/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 02/20/2013
DOT Vendor: C09740  Contract: 64C29 

IL Project:      From Date: 12/10/2012
Route: FAI 90
Section: (X2-1)R To Date: 02/20/2013
Project: NHI-0901/032/000 State Job: C-92-156-10
Letting Date: 01/20/2012 Dist/Cnty: 02 - 201 (WINNEBAGO )
Airport: (X2-1)R State Job: C-92-156-10
Scope: FAI-90, @ ROCKTON RD FROM WISCONSIN/ILLINOIS ST LN TO ROCK-
TON RD IN S. BELOIT.

Payee:

WILLIAM CHARLES CONSTRUCTION C PO BOX 2071  LOVES PARK , IL  61130

 

 

 

 

Percent Completed:  49.67%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
33,759,648.57      1,669,109.62      1,277,248.22      34,151,509.97      16,963,073.99     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 16,963,073.99     
Total paid this estimate:   16,963,073.99     
     Previous payments to contractor: -16,662,154.10     
     Payment to contractor this estimate: 300,919.89     
 
          Voucher #   BC04973 Date: 02/21/2013 1 of 1 300,919.89     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  12 Total: 300,919.89     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X4400110  TEMP PAVT REMOVAL   68,860.000  0.000  68,860.000  0.000  2,575.900  2,575.900  8.61  22,178.50 
X7040650  REM TEMP CONC BARRIER   563.000  68.100  631.100  563.000  631.100  68.100  11.24  765.44 
Z0023500  FILL EXIST CULVERTS   17.000  11.340  28.340  17.000  28.340  11.340  300.35  3,405.97 
20100110  TREE REMOV 6-15   113.000  734.500  847.500  310.400  435.800  125.400  15.00  1,881.00 
20100210  TREE REMOV OVER 15   219.000  2,046.000  2,265.000  758.200  1,019.800  261.600  20.00  5,232.00 
21101615  TOPSOIL F & P 4   12,823.000  165,000.000  177,823.000  71,129.200  94,026.480  22,897.280  3.00  68,691.84 
25100115  MULCH METHOD 2   29.750  12.000  41.750  11.900  17.491  5.591  762.26  4,261.80 
28000305  TEMP DITCH CHECKS   1,967.000  3,000.000  4,967.000  1,967.000  2,874.500  907.500  9.15  8,303.63 
28001000  AGGREGATE - EROS CONT   67.000  60.000  127.000  67.000  77.780  10.780  37.19  400.91 
28100109  STONE RIPRAP CL A5   2,879.000  -214.180  2,664.820  1,677.420  1,738.820  61.400  57.78  3,547.69 
31100100  SUB GRAN MAT A   403.000  1,110.840  1,513.840  403.000  1,513.840  1,110.840  24.43  27,137.82 
44000100  PAVEMENT REM   147,996.000  8,940.000  156,936.000  41,533.570  100,511.280  58,977.710  8.09  477,129.68 
44004250  PAVED SHLD REMOVAL   8,940.000  -8,940.000  0.000  60,940.000  0.000  -60,940.000  8.40  -511,896.00 
50300225  CONC STRUCT   491.000  3.530  494.530  219.000  222.530  3.530  560.01  1,976.84 
50300255  CONC SUP-STR   1,111.800  1.470  1,113.270  524.500  525.970  1.470  575.01  845.26 
50300260  BR DECK GROOVING   2,159.000  343.110  2,502.110  1,014.000  1,357.110  343.110  4.75  1,629.77 
50300300  PROTECTIVE COAT   2,446.000  440.430  2,886.430  1,344.080  1,597.430  253.350  1.00  253.35 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
50800205  REINF BARS, EPOXY CTD   344,145.000  -9.970  344,135.030  155,812.000  161,328.250  5,516.250  1.08  5,957.54 
5421A018  P CUL CL A 1 18 TEMP   599.000  -11.500  587.500  578.500  587.500  9.000  41.90  377.10 
550A0680  STORM SEW CL A 3 18   100.000  2.000  102.000  100.000  102.000  2.000  87.40  174.80 
60108100  PIPE UNDERDRAIN 4 SP   175.000  416.800  591.800  275.000  591.800  316.800  16.95  5,369.76 
60500040  REMOV MANHOLES   2.000  1.000  3.000  2.000  3.000  1.000  363.25  363.25 
63000001  SPBGR TY A 6FT POSTS   1,537.500  0.000  1,537.500  0.000  487.500  487.500  19.85  9,676.88 
63100070  TRAF BAR TERM T5   2.000  0.000  2.000  0.000  1.000  1.000  525.01  525.01 
63100085  TRAF BAR TERM T6   2.000  0.000  2.000  0.000  1.000  1.000  2,440.04  2,440.04 
63100167  TR BAR TRM T1 SPL TAN   7.000  0.000  7.000  0.000  2.000  2.000  2,085.04  4,170.08 
63200310  GUARDRAIL REMOV   3,560.000  2,405.000  5,965.000  3,560.000  4,289.000  729.000  3.40  2,478.60 
67000400  ENGR FIELD OFFICE A   19.000  0.000  19.000  7.500  9.500  2.000  1,400.03  2,800.06 
70301000  WORK ZONE PAVT MK REM   87,918.000  0.000  87,918.000  6,173.200  27,049.500  20,876.300  0.12  2,505.16 
70400200  REL TEMP CONC BARRIER   101,841.000  0.000  101,841.000  2,156.000  20,859.000  18,703.000  1.50  28,054.50 
72000200  SIGN PANEL T2   461.000  0.000  461.000  0.000  52.000  52.000  15.00  780.00 
72000300  SIGN PANEL T3   5,163.000  0.000  5,163.000  0.000  30.000  30.000  20.00  600.00 
72600100  MILEPOST MKR ASSEMBLY   22.000  0.000  22.000  0.000  11.000  11.000  350.01  3,850.11 
73000100  WOOD SIN SUPPORT   548.000  0.000  548.000  0.000  86.000  86.000  24.00  2,064.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
73400200  DRILL SHAFT CONC FDN   125.700  0.000  125.700  32.180  64.100  31.920  1,600.03  51,072.96 
78201000  TERMINAL MARKER - DA   7.000  0.000  7.000  0.000  2.000  2.000  30.00  60.00 
FRC00801  PILE SPLICE   0.000  7,425.770  7,425.770  0.000  2,574.230  2,574.230  1.00  2,574.23 
X9200201  LEV BINDER (HM) N70   0.000  20.000  20.000  5.130  8.970  3.840  171.00  656.64 
X9200202  CLASS D PATCH TY 2 13"   0.000  294.150  294.150  120.000  294.150  174.150  243.00  42,318.45 
X9200205  NIGHTTIME LANE CLOSURE   0.000  4.000  4.000  2.000  4.000  2.000  1,500.00  3,000.00 
X9200601  TEMP PVT (SPL)   0.000  1,360.350  1,360.350  1,000.000  1,360.350  360.350  23.62  8,511.47 
X9200701  QUARTERLY REPORTING   0.000  8.000  8.000  1.000  2.000  1.000  350.00  350.00 
X9201002  IMP ATTEN NRD NAR TL3R   0.000  4.000  4.000  1.000  2.000  1.000  900.00  900.00 
X9201103  EXPANSION JOINT 3"   0.000  100.000  100.000  0.000  45.000  45.000  78.75  3,543.75 
Total:   

$300,919.89

 