 04/21/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 11/09/2012
DOT Vendor: C09740  Contract: 64C29 

IL Project:      From Date: 10/12/2012
Route: FAI 90
Section: (X2-1)R To Date: 11/09/2012
Project: NHI-0901/032/000 State Job: C-92-156-10
Letting Date: 01/20/2012 Dist/Cnty: 02 - 201 (WINNEBAGO )
Airport: (X2-1)R State Job: C-92-156-10
Scope: FAI-90, @ ROCKTON RD FROM WISCONSIN/ILLINOIS ST LN TO ROCK-
TON RD IN S. BELOIT.

Payee:

WILLIAM CHARLES CONSTRUCTION C PO BOX 2071  LOVES PARK , IL  61130

 

 

 

 

Percent Completed:  41.57%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
33,759,648.57      1,276,230.90      103,359.80      34,932,519.67      14,522,711.23     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 14,522,711.23     
Total paid this estimate:   14,522,711.23     
     Previous payments to contractor: -12,405,128.95     
     Payment to contractor this estimate: 2,117,582.28     
 
          Voucher #   BC03605 Date: 11/14/2012 1 of 1 2,117,582.28     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  10 Total: 2,117,582.28     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X4211080  WF BM TERM JT COM SPL   2.000  0.000  2.000  0.000  1.000  1.000  122,002.21  122,002.21 
X4401198  HMA SURF REM VAR DP   1,689.000  0.000  1,689.000  918.840  1,096.620  177.780  8.30  1,475.58 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.280  0.410  0.130  95,680.40  12,438.45 
Z0030330  IMP ATTN REL FRD TL3   7.000  0.000  7.000  0.000  1.000  1.000  2,500.05  2,500.05 
Z0030350  IMP ATTN REL NRD TL3   5.000  0.000  5.000  0.000  1.000  1.000  600.01  600.01 
Z0062456  TEMP PAVEMENT   73,090.000  -500.000  72,590.000  54,513.360  54,652.030  138.670  44.33  6,147.24 
20300100  CHANNEL EXCAVATION   2,252.000  0.000  2,252.000  563.000  1,126.000  563.000  18.38  10,347.94 
20800150  TRENCH BACKFILL   1,062.000  600.000  1,662.000  1,452.050  1,460.900  8.850  27.75  245.59 
28100105  STONE RIPRAP CL A3   40.000  0.000  40.000  0.000  23.330  23.330  37.05  864.38 
28100109  STONE RIPRAP CL A5   2,879.000  0.000  2,879.000  824.000  1,677.420  853.420  57.78  49,310.61 
31100910  SUB GRAN MAT A 12   175,958.000  1,500.000  177,458.000  60,222.300  82,227.850  22,005.550  9.00  198,049.95 
31200100  STAB SUBBASE 4   11,218.000  1,500.000  12,718.000  142.220  195.550  53.330  16.77  894.34 
31200500  STAB SUBBASE HMA 4   192,491.000  0.000  192,491.000  60,080.080  82,032.300  21,952.220  13.11  287,793.60 
40603345  HMA SC "D" N90   1,445.000  0.000  1,445.000  160.480  180.990  20.510  87.45  1,793.60 
42000416  PCC PVT 9 3/4 JOINTD   8,267.000  0.000  8,267.000  0.000  410.830  410.830  41.00  16,844.03 
42001420  BR APPR PVT CON (PCC)   3,065.000  0.000  3,065.000  0.000  832.440  832.440  65.00  54,108.60 
42100355  CONT R PCC PVT 12 3/4   117,258.000  200.000  117,458.000  37,541.870  43,777.430  6,235.560  37.00  230,715.72 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
42100615  PAVT REINFORCEMENT   117,258.000  200.000  117,458.000  37,541.870  43,777.430  6,235.560  22.00  137,182.32 
44004000  PAVED DITCH REMOVAL   225.000  0.000  225.000  0.000  188.000  188.000  11.03  2,073.64 
48300500  PCC SHOULDERS 10   1,422.000  700.000  2,122.000  0.000  53.330  53.330  34.00  1,813.22 
48300715  PCC SHOULDERS 12 3/4   60,889.000  0.000  60,889.000  2,353.780  21,349.890  18,996.110  35.00  664,863.85 
50200100  STRUCTURE EXCAVATION   360.000  0.000  360.000  0.000  163.030  163.030  35.00  5,706.05 
50300255  CONC SUP-STR   1,111.800  0.000  1,111.800  287.740  524.500  236.760  575.01  136,139.37 
50300260  BR DECK GROOVING   2,159.000  0.000  2,159.000  0.000  1,014.000  1,014.000  4.75  4,816.50 
50300300  PROTECTIVE COAT   2,446.000  0.000  2,446.000  0.000  1,157.000  1,157.000  1.00  1,157.00 
50800205  REINF BARS, EPOXY CTD   344,145.000  0.000  344,145.000  101,697.290  148,400.030  46,702.740  1.08  50,438.96 
50800515  BAR SPLICERS   282.000  0.000  282.000  0.000  132.000  132.000  24.00  3,168.00 
51500100  NAME PLATES   3.000  0.000  3.000  0.000  1.000  1.000  693.46  693.46 
54001001  BOX CUL END SEC C1   2.000  0.000  2.000  0.000  1.000  1.000  39,025.41  39,025.41 
54213663  PRC FLAR END SEC 18   32.000  0.000  32.000  28.000  32.000  4.000  598.95  2,395.80 
54214503  PRC FL END S EQ RS 18   8.000  0.000  8.000  4.000  6.000  2.000  618.95  1,237.90 
54215547  MET END SEC 12   2.000  0.000  2.000  0.000  1.000  1.000  221.65  221.65 
550A0120  STORM SEW CL A 1 24   265.000  0.000  265.000  265.000  264.500  -0.500  44.25  -22.12 
550A0680  STORM SEW CL A 3 18   100.000  0.000  100.000  94.000  100.000  6.000  87.40  524.40 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
550A4000  SS CL A 1 EQRS 18   792.000  0.000  792.000  624.600  660.600  36.000  54.89  1,976.04 
60270050  DR STR T4 W/2 T20F&G   47.000  0.000  47.000  46.000  47.000  1.000  3,723.40  3,723.40 
60900515  CONC THRUST BLOCKS   2.000  0.000  2.000  0.000  1.000  1.000  625.27  625.27 
61000225  TY F INLET BOX 610001   1.000  0.000  1.000  0.000  1.000  1.000  4,272.18  4,272.18 
67000400  ENGR FIELD OFFICE A   19.000  0.000  19.000  5.500  6.500  1.000  1,400.03  1,400.03 
70106800  CHANGEABLE MESSAGE SN   36.000  0.000  36.000  11.500  15.500  4.000  1,200.02  4,800.08 
70300220  TEMP PVT MK LINE 4   279,879.000  0.000  279,879.000  102,878.700  108,799.300  5,920.600  0.05  296.03 
70300250  TEMP PVT MK LINE 8   2,750.000  0.000  2,750.000  1,842.100  2,052.100  210.000  0.65  136.50 
70301000  WORK ZONE PAVT MK REM   87,918.000  0.000  87,918.000  6,131.700  6,173.200  41.500  0.12  4.98 
70400200  REL TEMP CONC BARRIER   101,841.000  0.000  101,841.000  1,295.000  2,156.000  861.000  1.50  1,291.50 
73400200  DRILL SHAFT CONC FDN   125.700  0.000  125.700  0.000  32.180  32.180  1,600.03  51,488.96 
Total:   

$2,117,582.28

 