Previous Report 07/18/2012
DOT Vendor: C46570  Contract: 64815 

IL Project:      From Date: 06/13/2012
Route: FAI 280
Section: 81-1(B-1,HB,HB-1,HB-2,VB,VB1)R To Date: 07/18/2012
Project: NHI-ARRA-2806/050/003 State Job: C-92-159-10
Letting Date: 01/21/2011 Dist/Cnty: 02 - 161 (ROCK ISLAND)
Airport: 81-1(B-1,HB,HB-1,HB-2,VB,VB1)R State Job: C-92-159-10
Scope: FAI-280, MISSISSIPPI RIVER TO AIRPORT RD.

Payee:

FH PASCHEN SN NIELSEN & ASSOC 5515 N EAST RIVER ROAD  CHICAGO , IL  60656

 

 

 

 

Percent Completed:  64.93%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
22,406,848.23      782,582.93      692,841.21      22,496,589.95      15,330,406.52     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 15,330,406.52     
Total paid this estimate:   15,330,406.52     
     Previous payments to contractor: -14,064,753.22     
     Payment to contractor this estimate: 1,265,653.30     
 
          Voucher #   CC00745 Date: 07/20/2012 1 of 2 11,134.93     
          Voucher #   CC00723 Date: 07/20/2012 2 of 2 1,254,518.37     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  19 Total: 1,265,653.30     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X2070304  POROUS GRAN EMB SPEC   2,291.000  0.000  2,291.000  779.730  1,237.950  458.220  41.84  19,171.93 
X5051401  F&E STRUCT STL BR N1   1.000  0.000  1.000  0.500  1.000  0.500  200,000.00  100,000.00 
X5051405  F&E STRUCT STL BR N5   1.000  0.000  1.000  0.500  1.000  0.500  675,000.00  337,500.00 
Z0012754  STR REP CON DP = < 5   157.000  0.000  157.000  110.730  157.000  46.270  100.00  4,627.00 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.550  0.750  0.200  250,000.00  50,000.00 
Z0030350  IMP ATTN REL NRD TL3   13.000  0.000  13.000  9.000  12.000  3.000  960.00  2,880.00 
Z0046304  P UNDR FOR STRUCT 4   1,998.000  0.000  1,998.000  823.040  1,109.540  286.500  25.00  7,162.50 
Z0065704  BIT CT AG SLOPEWALL 6   5,208.000  0.000  5,208.000  0.000  1,411.300  1,411.300  30.00  42,339.00 
28000400  PERIMETER EROS BAR   7,650.000  0.000  7,650.000  4,695.600  4,816.600  121.000  2.25  272.25 
28100707  STONE DUMP RIP CL A4   42.000  0.000  42.000  38.300  42.000  3.700  59.10  218.67 
42001430  BR APPR PVT CON (FLX)   820.000  0.000  820.000  571.730  820.000  248.270  100.00  24,827.00 
44000500  COMB CURB GUTTER REM   196.000  0.000  196.000  0.000  195.500  195.500  8.21  1,605.06 
44000600  SIDEWALK REM   1,082.000  0.000  1,082.000  0.000  747.100  747.100  1.60  1,195.36 
44004250  PAVED SHLD REMOVAL   12,267.000  0.000  12,267.000  6,829.870  6,933.080  103.210  4.28  441.74 
48203023  HMA SHOULDERS 6 1/2   6,257.000  0.000  6,257.000  2,250.000  2,472.580  222.580  31.00  6,899.98 
50200100  STRUCTURE EXCAVATION   4,015.000  0.000  4,015.000  2,306.500  3,265.500  959.000  29.45  28,242.55 
50300225  CONC STRUCT   1,963.200  0.000  1,963.200  1,389.600  1,490.400  100.800  810.00  81,648.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
50300255  CONC SUP-STR   5,734.800  0.000  5,734.800  2,350.800  3,268.800  918.000  595.00  546,210.00 
50300260  BR DECK GROOVING   14,671.000  0.000  14,671.000  5,571.420  7,449.720  1,878.300  3.95  7,419.28 
50300300  PROTECTIVE COAT   18,287.000  0.000  18,287.000  7,032.120  9,022.000  1,989.880  4.00  7,959.52 
50500505  STUD SHEAR CONNECTORS   57,603.000  0.000  57,603.000  29,591.000  50,144.000  20,553.000  2.25  46,244.25 
50800205  REINF BARS, EPOXY CTD   1,524,940.000  15,210.000  1,540,150.000  812,432.120  1,041,259.520  228,827.400  0.91  208,232.93 
50800515  BAR SPLICERS   5,072.000  0.000  5,072.000  549.500  810.500  261.000  22.84  5,961.24 
51100100  SLOPE WALL 4   4,092.000  0.000  4,092.000  709.600  1,171.100  461.500  71.72  33,098.78 
52100010  ELAST BEARING ASSY T1   40.000  0.000  40.000  38.000  40.000  2.000  600.00  1,200.00 
52100020  ELAST BEARING ASSY T2   6.000  0.000  6.000  5.000  6.000  1.000  600.00  600.00 
52100520  ANCHOR BOLTS 1   232.000  0.000  232.000  148.000  180.000  32.000  22.00  704.00 
52100530  ANCHOR BOLTS 1 1/4   72.000  0.000  72.000  60.000  72.000  12.000  36.00  432.00 
59100100  GEOCOMPOSITE WALL DR   1,176.000  0.000  1,176.000  444.810  645.230  200.420  18.37  3,681.71 
63000001  SPBGR TY A 6FT POSTS   15,262.500  0.000  15,262.500  6,925.600  7,450.600  525.000  16.50  8,662.50 
63100045  TRAF BAR TERM T2   5.000  0.000  5.000  2.000  4.000  2.000  700.00  1,400.00 
63100070  TRAF BAR TERM T5   12.000  0.000  12.000  5.000  7.000  2.000  625.00  1,250.00 
63100085  TRAF BAR TERM T6   24.000  0.000  24.000  10.000  12.000  2.000  2,400.00  4,800.00 
63100167  TR BAR TRM T1 SPL TAN   5.000  0.000  5.000  2.000  4.000  2.000  2,200.00  4,400.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
63200310  GUARDRAIL REMOV   13,061.000  0.000  13,061.000  12,901.550  13,061.000  159.450  3.00  478.35 
67000400  ENGR FIELD OFFICE A   18.000  0.000  18.000  14.330  15.330  1.000  2,500.00  2,500.00 
70100410  TRAF CONT-PROT 701416   2.000  0.000  2.000  1.480  1.610  0.130  68,485.00  8,903.05 
70100420  TRAF CONT-PROT 701411   14.000  0.000  14.000  3.270  4.150  0.880  1,200.00  1,056.00 
70100805  TRAF CONT-PROT 701402   1.000  0.000  1.000  0.540  0.630  0.090  76,792.00  6,911.28 
70100820  TRAF CONT-PROT 701451   1.000  0.000  1.000  0.510  0.640  0.130  2,000.00  260.00 
70102635  TR CONT & PROT 701701   1.000  0.000  1.000  0.510  0.640  0.130  500.00  65.00 
70301000  WORK ZONE PAVT MK REM   97,158.000  0.000  97,158.000  19,367.100  22,571.900  3,204.800  0.90  2,884.32 
78200410  GUARDRAIL MKR TYPE A   335.000  0.000  335.000  141.000  155.000  14.000  7.00  98.00 
78201000  TERMINAL MARKER - DA   27.000  0.000  27.000  17.000  19.000  2.000  40.00  80.00 
78300100  PAVT MARKING REMOVAL   14,530.000  0.000  14,530.000  4,956.080  5,896.740  940.660  1.50  1,410.99 
MATALL00  MATERIAL ALLOWANCE   0.000  0.000  0.000  0.000  0.000  0.000  0.00  -352,193.00 
X9200901  HMA SC "C" N70   0.000  2,799.000  2,799.000  1,354.200  1,378.840  24.640  77.60  1,912.06 
Total:   

$1,265,653.30

 