DOT Vendor: C15520  Contract: 63422 

IL Project:      From Date: 04/20/2011
Route: FAU 3602
Section: 08-F3000-07-BT To Date: 08/17/2011
Project: TE-00D1/822/000 State Job: C-91-484-10
Letting Date: 03/11/2011 Dist/Cnty: 01 - 097 (LAKE )
Airport: 08-F3000-07-BT State Job: C-91-484-10
Scope: 1.2 MILES NORTH OF ILLINOIS ROUTE 176

Payee:

DUNNET BAY CONSTRUCTION CO 115 N BRANDON DR  GLENDALE HEIGHTS , IL  60139

 

 

 

 

Percent Completed:  17.02%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
1,752,211.92      0.00      0.00      1,752,211.92      298,181.52     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 298,181.52     
Mobilzation Paid:12,675.00     
Total paid this estimate:   298,181.52     
     Previous payments to contractor: -63,375.00     
     Payment to contractor this estimate: 234,806.52     
 
          Voucher #   CC02988 Date: 08/19/2011 1 of 1 234,806.52     

----------------------------------------------------------------------------------------------------------------------------------------------     

Includes 15% mobilization Pay Estimate Number:  01 Total: 234,806.52     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X2010350  TREE REMOV ACRES SPL   1.100  0.000  1.100  0.000  1.100  1.100  6,000.00  6,600.00 
X6700405  ENGR FLD OFF A MOD   7.000  0.000  7.000  0.000  2.480  2.480  2,100.00  5,208.00 
X7010216  TRAF CONT & PROT SPL   1.000  0.000  1.000  0.000  0.300  0.300  3,500.00  1,050.00 
Z0013797  STAB CONSTR ENTRANCE   334.000  0.000  334.000  0.000  166.700  166.700  25.00  4,167.50 
Z0022800  FENCE REMOVAL   1,092.000  0.000  1,092.000  0.000  1,092.000  1,092.000  3.55  3,876.60 
Z0030240  IMP ATTN TEMP NRD TL2   2.000  0.000  2.000  0.000  2.000  2.000  4,800.00  9,600.00 
Z0030850  TEMP INFO SIGNING   77.000  0.000  77.000  0.000  51.400  51.400  15.00  771.00 
Z0062456  TEMP PAVEMENT   2,346.000  0.000  2,346.000  0.000  2,346.000  2,346.000  30.85  72,374.10 
Z0073002  TEMP SOIL RETEN SYSTM   2,207.000  0.000  2,207.000  0.000  1,657.710  1,657.710  0.10  165.77 
20101300  TREE PRUN 1-10   15.000  0.000  15.000  0.000  8.000  8.000  60.00  480.00 
20101350  TREE PRUN OVER 10   15.000  0.000  15.000  0.000  4.000  4.000  125.00  500.00 
20200100  EARTH EXCAVATION   32,743.000  0.000  32,743.000  0.000  18,290.000  18,290.000  4.23  77,366.70 
28000400  PERIMETER EROS BAR   3,704.000  0.000  3,704.000  0.000  3,500.000  3,500.000  2.50  8,750.00 
44000100  PAVEMENT REM   503.000  0.000  503.000  0.000  438.700  438.700  5.00  2,193.50 
48101200  AGGREGATE SHLDS B   523.000  0.000  523.000  0.000  133.530  133.530  36.40  4,860.49 
50200100  STRUCTURE EXCAVATION   4,536.000  0.000  4,536.000  0.000  1,864.780  1,864.780  3.55  6,619.97 
5421D015  P CUL CL D 1 15 TEMP   210.000  0.000  210.000  0.000  210.000  210.000  27.25  5,722.50 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
54213870  STEEL END SEC 15   4.000  0.000  4.000  0.000  3.000  3.000  170.50  511.50 
54244405  FL INLT BX MED 542546   5.000  0.000  5.000  0.000  1.000  1.000  2,407.50  2,407.50 
67100100  MOBILIZATION   1.000  0.000  1.000  0.750  0.900  0.150  84,500.00  12,675.00 
70106800  CHANGEABLE MESSAGE SN   6.000  0.000  6.000  0.000  1.740  1.740  1,000.00  1,740.00 
70300220  TEMP PVT MK LINE 4   2,194.000  0.000  2,194.000  0.000  1,850.000  1,850.000  0.18  333.00 
70300230  TEMP PVT MK LINE 5   2,377.000  0.000  2,377.000  0.000  2,084.000  2,084.000  0.20  416.80 
70300520  PAVT MARK TAPE T3 4   5,404.000  0.000  5,404.000  0.000  1,904.000  1,904.000  0.85  1,618.40 
70300530  PAVT MARK TAPE T3 5   5,221.000  0.000  5,221.000  0.000  1,649.000  1,649.000  1.00  1,649.00 
70400100  TEMP CONC BARRIER   165.000  0.000  165.000  0.000  165.000  165.000  17.00  2,805.00 
78300100  PAVT MARKING REMOVAL   2,726.000  0.000  2,726.000  0.000  362.300  362.300  0.95  344.19 
Total:   

$234,806.52

 