State of Illinois Department of Transportation

Contract Search

 04/17/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 06/30/2011
DOT Vendor: C12970  Contract: 63398 

IL Project:      From Date: 06/04/2011
Route: FAP 336
Section: 05-00308-00-WR To Date: 06/30/2011
Project: HPP-TCSP-RSCMF--0336/031/00 State Job: C-91-191-05
Letting Date: 11/05/2010 Dist/Cnty: 01 - 111 (MCHENRY )
Airport: 05-00308-00-WR State Job: C-91-191-05
Scope: ACKMAN ROAD TO ILLINOIS ROUTE 31

Payee:

CURRAN CONTRACTING/PLOTE CONST 286 MEMORIAL COURT  CRYSTAL LAKE , IL  60014

 

 

 

 

Percent Completed:  16.5%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
26,610,956.43      227,505.48      130,378.50      26,708,083.41      4,405,970.18     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 4,405,970.18     
Total paid this estimate:   4,405,970.18     
     Previous payments to contractor: -3,532,279.98     
     Payment to contractor this estimate: 873,690.20     
 
          Voucher #   CC00596 Date: 07/28/2011 3 of 3 604,178.34     
          Voucher #   CC00543 Date: 07/28/2011 2 of 3 47,078.20     
          Voucher #   CC00542 Date: 07/28/2011 1 of 3 222,433.66     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  05 Total: 873,690.20     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
XX005723  VIDEO DET SY COMP INT   5.000  0.000  5.000  0.000  4.500  4.500  24,584.30  110,629.35 
XX008434  MANHOLE SPL TYPE 2   3.000  2.000  5.000  1.000  2.000  1.000  6,675.00  6,675.00 
X0322936  REMOV EX FLAR END SEC   81.000  0.000  81.000  4.000  5.000  1.000  64.95  64.95 
X2070304  POROUS GRAN EMB SPEC   60.000  0.000  60.000  0.000  52.850  52.850  38.00  2,008.30 
Z0001050  AGG SUBGRADE 12   195,078.000  0.000  195,078.000  0.000  1,150.000  1,150.000  8.30  9,545.00 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.200  0.250  0.050  84,900.00  4,245.00 
Z0030850  TEMP INFO SIGNING   1,260.000  0.000  1,260.000  59.900  223.650  163.750  14.00  2,292.50 
Z0042002  POROUS GRAN EMB SUBGR   3,778.000  0.000  3,778.000  1,060.110  1,634.510  574.400  26.00  14,934.40 
Z0062456  TEMP PAVEMENT   40,821.000  0.000  40,821.000  9,133.870  10,944.570  1,810.700  26.00  47,078.20 
20200100  EARTH EXCAVATION   128,625.000  0.000  128,625.000  13,251.550  27,455.950  14,204.400  11.25  159,799.50 
20201200  REM & DISP UNS MATL   46,260.000  0.000  46,260.000  36,062.510  37,525.810  1,463.300  15.30  22,388.49 
20800150  TRENCH BACKFILL   5,127.000  0.000  5,127.000  1,768.600  2,173.350  404.750  18.75  7,589.06 
25100635  HD EROS CONTR BLANKET   462,099.000  0.000  462,099.000  12,633.210  15,444.510  2,811.300  0.55  1,546.21 
28000250  TEMP EROS CONTR SEED   124,118.000  0.000  124,118.000  749.300  807.400  58.100  0.01  0.58 
28000400  PERIMETER EROS BAR   55,473.000  0.000  55,473.000  43,814.450  43,837.950  23.500  1.50  35.25 
28000500  INLET & PIPE PROTECT   69.000  0.000  69.000  29.000  32.000  3.000  100.00  300.00 
28000510  INLET FILTERS   321.000  0.000  321.000  5.000  6.000  1.000  135.00  135.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
44000100  PAVEMENT REM   152,389.000  0.000  152,389.000  0.000  6,247.410  6,247.410  5.05  31,549.42 
44000165  HMA SURF REM 4   23,397.000  0.000  23,397.000  0.000  297.170  297.170  2.50  742.93 
44000200  DRIVE PAVEMENT REM   2,897.000  0.000  2,897.000  399.500  1,081.630  682.130  2.75  1,875.85 
44000500  COMB CURB GUTTER REM   6,309.000  0.000  6,309.000  3,553.150  5,667.150  2,114.000  5.25  11,098.50 
44004250  PAVED SHLD REMOVAL   13,132.000  0.000  13,132.000  4,087.770  5,369.210  1,281.440  4.50  5,766.48 
50800105  REINFORCEMENT BARS   16,400.000  0.000  16,400.000  0.000  16,224.000  16,224.000  1.30  21,091.20 
54002020  EXPAN BOLTS 3/4   33.000  0.000  33.000  0.000  33.000  33.000  16.00  528.00 
54003000  CONC BOX CUL   106.000  0.000  106.000  0.000  105.720  105.720  915.00  96,733.80 
54213669  PRC FLAR END SEC 24   13.000  0.000  13.000  0.000  1.000  1.000  535.00  535.00 
550A0050  STORM SEW CL A 1 12   2,164.000  0.000  2,164.000  14.200  384.900  370.700  29.50  10,935.65 
550A0090  STORM SEW CL A 1 18   690.000  0.000  690.000  0.000  195.500  195.500  29.25  5,718.38 
550A0120  STORM SEW CL A 1 24   1,328.000  -44.000  1,284.000  0.000  415.000  415.000  38.50  15,977.50 
550A0340  STORM SEW CL A 2 12   6,859.000  -121.000  6,738.000  177.100  545.900  368.800  29.50  10,879.60 
550A0380  STORM SEW CL A 2 18   2,286.000  145.000  2,431.000  0.000  50.600  50.600  29.25  1,480.05 
550A0410  STORM SEW CL A 2 24   2,822.000  -204.000  2,618.000  131.400  487.300  355.900  38.00  13,524.20 
550A0430  STORM SEW CL A 2 30   985.000  416.000  1,401.000  0.000  395.300  395.300  48.50  19,172.05 
550A0450  STORM SEW CL A 2 36   1,306.000  -370.000  936.000  168.000  625.700  457.700  60.00  27,462.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
550A0470  STORM SEW CL A 2 42   1,141.000  20.000  1,161.000  0.000  320.000  320.000  65.00  20,800.00 
550A0490  STORM SEW CL A 2 54   774.000  0.000  774.000  735.800  759.800  24.000  100.00  2,400.00 
550A0500  STORM SEW CL A 2 60   3,116.000  0.000  3,116.000  3,000.000  3,088.000  88.000  112.00  9,856.00 
55101200  STORM SEWER REM 24   3,890.000  0.000  3,890.000  112.000  120.000  8.000  14.00  112.00 
56400400  FIRE HYDNTS RELOCATED   7.000  0.000  7.000  4.000  5.000  1.000  1,450.00  1,450.00 
60200805  CB TA 4 DIA T8G   19.000  -9.000  10.000  0.000  1.000  1.000  1,350.00  1,350.00 
60201340  CB TA 4 DIA T24F&G   169.000  -17.000  152.000  25.000  33.000  8.000  1,465.00  11,720.00 
60204505  CB TA 5 DIA T8G   8.000  10.000  18.000  3.000  5.000  2.000  1,950.00  3,900.00 
60205040  CB TA 5 DIA T24F&G   9.000  15.000  24.000  6.000  9.000  3.000  2,075.00  6,225.00 
60208240  CB TC T24F&G   82.000  2.000  84.000  1.000  2.000  1.000  935.00  935.00 
60218400  MAN TA 4 DIA T1F CL   41.000  -8.000  33.000  0.000  1.000  1.000  1,425.00  1,425.00 
60221100  MAN TA 5 DIA T1F CL   26.000  11.000  37.000  2.000  15.000  13.000  2,055.00  26,715.00 
60224446  MAN TA 7 DIA T1F CL   33.000  2.000  35.000  25.000  27.000  2.000  4,730.00  9,460.00 
63200310  GUARDRAIL REMOV   2,848.000  0.000  2,848.000  1,355.000  2,525.000  1,170.000  3.42  4,001.40 
67000400  ENGR FIELD OFFICE A   27.000  0.000  27.000  3.990  4.860  0.870  1,600.00  1,392.00 
70101800  TRAF CONT & PROT SPL   1.000  0.000  1.000  0.100  0.175  0.075  919,100.00  68,932.50 
70106800  CHANGEABLE MESSAGE SN   378.000  0.000  378.000  10.920  16.140  5.220  50.00  261.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
78000100  THPL PVT MK LTR & SYM   3,859.000  0.000  3,859.000  0.000  249.600  249.600  3.50  873.60 
78000400  THPL PVT MK LINE 6   15,905.000  0.000  15,905.000  0.000  69.000  69.000  1.09  75.21 
78000650  THPL PVT MK LINE 24   1,421.000  0.000  1,421.000  0.000  233.800  233.800  3.55  829.99 
78300100  PAVT MARKING REMOVAL   66,618.000  0.000  66,618.000  0.000  7,147.570  7,147.570  2.55  18,226.30 
89502380  REMOV EX HANDHOLE   69.000  0.000  69.000  2.000  53.000  51.000  191.80  9,781.80 
89502385  REMOV EX CONC FDN   59.000  0.000  59.000  0.000  45.000  45.000  191.80  8,631.00 
Total:   

$873,690.20

 