Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 11/29/2010
DOT Vendor: C53780  Contract: 63133 

IL Project:      From Date: 03/08/2010
Route: EAST AVE PINE AVE
Section: 06-00073-00-LS To Date: 11/29/2010
Project: TE-00D1/705/000 State Job: C-91-030-07
Letting Date: 01/15/2010 Dist/Cnty: 01 - 031 (COOK )
Airport: 06-00073-00-LS State Job: C-91-030-07
Scope: WATER TOWER CAMPUS INCLUDING EAST AVE FROM PINE AVE TO
FOREST AVE AND PINE AVE FROM EAST AVE TO LONGCOMMON RD

Payee:

SCHROEDER ASPHALT SERVICES INC P O BOX 831  HUNTLEY , IL  60142

 

 

 

 

Percent Completed:  64.77%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
346,724.55      0.00      0.00      346,724.55      224,585.25     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 224,585.25     
Mobilzation Paid:2,325.00     
Total paid this estimate:   224,585.25     
     Previous payments to contractor: -11,625.00     
     Payment to contractor this estimate: 212,960.25     
 
          Voucher #   CC13279 Date: 12/14/2010 1 of 1 212,960.25     

----------------------------------------------------------------------------------------------------------------------------------------------     

Includes 15% mobilization Pay Estimate Number:  01 Total: 212,960.25     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
K1003680  MULCH   345.000  0.000  345.000  0.000  208.000  208.000  8.10  1,684.80 
XX006561  PCC SDWLK 5 SP SWANEE   4,845.000  0.000  4,845.000  0.000  4,589.000  4,589.000  6.15  28,222.35 
XX007978  ARCHITECT LT SYSTEM   1.000  0.000  1.000  0.000  1.000  1.000  55,200.00  55,200.00 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.000  1.000  1.000  2,000.00  2,000.00 
Z0048665  RR PROT LIABILITY INS   1.000  0.000  1.000  0.000  1.000  1.000  5,400.00  5,400.00 
20201200  REM & DISP UNS MATL   522.000  0.000  522.000  0.000  276.000  276.000  36.00  9,936.00 
25200700  SODDING SPL   1,200.000  0.000  1,200.000  0.000  699.000  699.000  13.10  9,156.90 
40201000  AGGREGATE-TEMP ACCESS   100.000  0.000  100.000  0.000  91.740  91.740  20.00  1,834.80 
40600400  MIX CR JTS FLANGEWYS   4.000  0.000  4.000  0.000  4.000  4.000  385.00  1,540.00 
40600625  LEV BIND MM N50   105.000  0.000  105.000  0.000  72.000  72.000  110.00  7,920.00 
40603310  HMA SC "C" N50   350.000  0.000  350.000  0.000  200.000  200.000  89.00  17,800.00 
42400200  PC CONC SIDEWALK 5   1,612.000  0.000  1,612.000  0.000  1,612.000  1,612.000  4.55  7,334.60 
42400800  DETECTABLE WARNINGS   80.000  0.000  80.000  0.000  80.000  80.000  35.25  2,820.00 
44000100  PAVEMENT REM   292.000  0.000  292.000  0.000  292.000  292.000  14.00  4,088.00 
44000159  HMA SURF REM 2 1/2   2,263.000  0.000  2,263.000  0.000  2,263.000  2,263.000  5.25  11,880.75 
44000500  COMB CURB GUTTER REM   788.000  0.000  788.000  0.000  788.000  788.000  7.05  5,555.40 
44000600  SIDEWALK REM   3,921.000  0.000  3,921.000  0.000  3,916.000  3,916.000  1.60  6,265.60 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
44201741  CL D PATCH T2 8   24.000  0.000  24.000  0.000  24.000  24.000  100.00  2,400.00 
44201745  CL D PATCH T3 8   39.000  0.000  39.000  0.000  36.000  36.000  90.00  3,240.00 
60255500  MAN ADJUST   1.000  0.000  1.000  0.000  1.000  1.000  555.00  555.00 
60255800  MAN ADJ NEW T1F CL   8.000  0.000  8.000  0.000  7.000  7.000  850.00  5,950.00 
60258200  MAN RECON NEW T1F CL   1.000  0.000  1.000  0.000  1.000  1.000  1,360.00  1,360.00 
60603800  COMB CC&G TB6.12   555.000  0.000  555.000  0.000  555.000  555.000  19.00  10,545.00 
60608300  COMB CC&G TM2.12   30.000  0.000  30.000  0.000  30.000  30.000  19.00  570.00 
67100100  MOBILIZATION   1.000  0.000  1.000  0.750  0.900  0.150  15,500.00  2,325.00 
70102620  TR CONT & PROT 701501   1.000  0.000  1.000  0.000  0.900  0.900  4,500.00  4,050.00 
78000100  THPL PVT MK LTR & SYM   77.400  0.000  77.400  0.000  77.400  77.400  4.00  309.60 
78000200  THPL PVT MK LINE 4   978.000  0.000  978.000  0.000  978.000  978.000  1.25  1,222.50 
78000400  THPL PVT MK LINE 6   272.000  0.000  272.000  0.000  265.000  265.000  1.50  397.50 
78000500  THPL PVT MK LINE 8   155.000  0.000  155.000  0.000  135.000  135.000  1.75  236.25 
78000600  THPL PVT MK LINE 12   181.000  0.000  181.000  0.000  181.000  181.000  2.45  443.45 
78000650  THPL PVT MK LINE 24   35.000  0.000  35.000  0.000  35.000  35.000  6.05  211.75 
89502380  REMOV EX HANDHOLE   1.000  0.000  1.000  0.000  1.000  1.000  505.00  505.00 
Total:   

$212,960.25

 