Contractor Invoice

Previous Report 05/11/2012
DOT Vendor: C53780  Contract: 63133 

IL Project:      From Date: 11/04/2011
Route: EAST AVE PINE AVE
Section: 06-00073-00-LS To Date: 05/11/2012
Project: TE-00D1/705/000 State Job: C-91-030-07
Letting Date: 01/15/2010 Dist/Cnty: 01 - 031 (COOK )
Airport: 06-00073-00-LS State Job: C-91-030-07
Scope: WATER TOWER CAMPUS INCLUDING EAST AVE FROM PINE AVE TO
FOREST AVE AND PINE AVE FROM EAST AVE TO LONGCOMMON RD

Payee:

SCHROEDER ASPHALT SERVICES INC P O BOX 831  HUNTLEY , IL  60142

 

 

 

 

Percent Completed:  97.37%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
346,724.55      31,294.87      76,250.60      301,768.82      295,370.82     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 295,370.82     
Mobilzation Paid:1,550.00     
Total paid this estimate:   295,370.82     
     Previous payments to contractor: -283,426.72     
     Payment to contractor this estimate: 11,944.10     
 
          Voucher #   CC22892 Date: 05/25/2012 1 of 1 11,944.10     

----------------------------------------------------------------------------------------------------------------------------------------------     

Includes final mobilization Pay Estimate Number:  05 Total: 11,944.10     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
K1003680  MULCH   345.000  227.000  572.000  345.000  572.000  227.000  8.10  1,838.70 
XX006561  PCC SDWLK 5 SP SWANEE   4,845.000  263.000  5,108.000  4,845.000  5,108.000  263.000  6.15  1,617.45 
42400200  PC CONC SIDEWALK 5   1,612.000  257.000  1,869.000  1,612.000  1,869.000  257.000  4.55  1,169.35 
42400800  DETECTABLE WARNINGS   80.000  8.000  88.000  80.000  88.000  8.000  35.25  282.00 
44000100  PAVEMENT REM   292.000  37.000  329.000  292.000  329.000  37.000  14.00  518.00 
44000159  HMA SURF REM 2 1/2   2,263.000  124.000  2,387.000  2,263.000  2,387.000  124.000  5.25  651.00 
44000500  COMB CURB GUTTER REM   788.000  59.000  847.000  788.000  847.000  59.000  7.05  415.95 
44000600  SIDEWALK REM   3,921.000  324.000  4,245.000  3,921.000  4,245.000  324.000  1.60  518.40 
60255500  MAN ADJUST   1.000  1.000  2.000  1.000  2.000  1.000  555.00  555.00 
60603800  COMB CC&G TB6.12   555.000  23.000  578.000  555.000  578.000  23.000  19.00  437.00 
67100100  MOBILIZATION   1.000  0.000  1.000  0.900  1.000  0.100  15,500.00  1,550.00 
78000200  THPL PVT MK LINE 4   978.000  3.000  981.000  978.000  981.000  3.000  1.25  3.75 
XXX17100  LIQUIDATED DAMAGES   0.000  1.500  1.500  0.000  1.500  1.500  -875.00  -1,312.50 
X9100100  TOPSOIL F&P 24   0.000  185.000  185.000  0.000  185.000  185.000  20.00  3,700.00 
Total:   

$11,944.10

 