Previous Report 12/17/2013
DOT Vendor: C15600  Contract: 62537 

IL Project:      From Date: 12/03/2013
Route: FAP 336
Section: 112R-N To Date: 12/17/2013
Project: NHF-0336/051/ State Job: C-91-351-02
Letting Date: 04/27/2012 Dist/Cnty: 01 - 111 (MCHENRY )
Airport: 112R-N State Job: C-91-351-02
Scope: FAP-336, IL RT 31 @ IL RT 176 & @ TERRA COTTA AVE WITHIN
CITY OF CRYSTAL LAKE, NUNDA TOWNSHIP..

Payee:

R W DUNTEMAN COMPANY P O BOX 1129  ADDISON , IL  60101

 

 

 

 

Percent Completed:  42.43%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
10,189,282.86      217,817.18      0.00      10,407,100.04      4,509,627.21     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 4,509,627.21     
Total paid this estimate:   4,509,627.21     
     Previous payments to contractor: -4,279,056.10     
     Payment to contractor this estimate: 230,571.11     
 
          Voucher #   CC11054 Date: 12/19/2013 1 of 1 230,571.11     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  22 Total: 230,571.11     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X5630710  CONN TO EX W MAIN 10   2.000  1.000  3.000  2.000  3.000  1.000  1,500.00  1,500.00 
X7010216  TRAF CONT & PROT SPL   1.000  0.000  1.000  0.610  0.670  0.060  45,000.00  2,700.00 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.600  0.660  0.060  40,995.00  2,459.70 
Z0062456  TEMP PAVEMENT   10,614.000  0.000  10,614.000  8,274.040  8,940.450  666.410  38.76  25,830.05 
21001000  GEOTECH FAB F/GR STAB   53,454.000  0.000  53,454.000  11,393.600  0.000  -11,393.600  1.41  -16,064.98 
21101615  TOPSOIL F & P 4   42,015.000  0.000  42,015.000  0.000  6,503.340  6,503.340  1.00  6,503.34 
21101815  COMPOST F & P 4   4,102.000  0.000  4,102.000  0.000  4,102.000  4,102.000  3.60  14,767.20 
25000210  SEEDING CL 2A   4.050  0.000  4.050  0.000  0.290  0.290  1,200.00  348.00 
25000312  SEEDING CL 4A   0.850  0.000  0.850  0.000  0.850  0.850  1,250.00  1,062.50 
25000400  NITROGEN FERT NUTR   668.000  0.000  668.000  0.000  38.000  38.000  1.50  57.00 
25000500  PHOSPHORUS FERT NUTR   668.000  0.000  668.000  0.000  38.000  38.000  1.50  57.00 
25000600  POTASSIUM FERT NUTR   668.000  0.000  668.000  0.000  38.000  38.000  1.50  57.00 
25100630  EROSION CONTR BLANKET   23,719.000  0.000  23,719.000  0.000  8,182.750  8,182.750  0.90  7,364.48 
28000305  TEMP DITCH CHECKS   305.000  0.000  305.000  0.000  84.000  84.000  10.00  840.00 
28000500  INLET & PIPE PROTECT   39.000  0.000  39.000  0.000  14.000  14.000  150.00  2,100.00 
30300112  AGG SUBGRADE IMPR 12   60,765.000  0.000  60,765.000  22,768.110  23,603.470  835.360  9.76  8,153.12 
35600714  HMA BC WID 9 1/2   2,353.000  0.000  2,353.000  778.130  1,244.130  466.000  35.55  16,566.30 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
40603240  P HMA BC IL19.0 N90   1,135.000  0.000  1,135.000  100.980  475.720  374.740  98.48  36,904.40 
42000416  PCC PVT 9 3/4 JOINTD   47,437.000  0.000  47,437.000  15,950.650  16,639.930  689.280  47.06  32,437.52 
42300400  PCC DRIVEWAY PAVT 8   514.000  0.000  514.000  0.000  142.400  142.400  47.00  6,692.80 
48203029  HMA SHOULDERS 8   2,902.000  0.000  2,902.000  0.000  1,156.600  1,156.600  28.53  32,997.80 
550A0340  STORM SEW CL A 2 12   3,434.000  0.000  3,434.000  1,709.600  1,830.900  121.300  42.00  5,094.60 
550A0380  STORM SEW CL A 2 18   808.000  0.000  808.000  736.000  808.000  72.000  50.00  3,600.00 
550A0410  STORM SEW CL A 2 24   702.000  0.000  702.000  600.000  702.000  102.000  56.00  5,712.00 
56105100  WATER VALVES 10   1.000  1.000  2.000  1.000  2.000  1.000  2,800.00  2,800.00 
60201340  CB TA 4 DIA T24F&G   65.000  0.000  65.000  46.000  47.000  1.000  2,300.00  2,300.00 
60207605  CB TC T8G   5.000  0.000  5.000  3.000  4.000  1.000  1,200.00  1,200.00 
60237470  INLETS TA T24F&G   2.000  0.000  2.000  1.000  2.000  1.000  1,100.00  1,100.00 
60248900  VV TA 5 DIA T1F CL   3.000  1.000  4.000  2.000  4.000  2.000  2,800.00  5,600.00 
60603800  COMB CC&G TB6.12   6,029.000  0.000  6,029.000  571.800  1,203.800  632.000  14.50  9,164.00 
60605000  COMB CC&G TB6.24   11,174.000  0.000  11,174.000  2,966.300  3,475.900  509.600  16.00  8,153.60 
67000400  ENGR FIELD OFFICE A   18.000  0.000  18.000  15.000  16.000  1.000  2,513.68  2,513.68 
Total:   

$230,571.11

 