DOT Vendor: C30690  Contract: 62420 

IL Project:      From Date: 06/30/2011
Route: FAP 365
Section: (58 & 59)WRS-3 To Date: 07/22/2011
Project: NHF-CMF-TE-0365/012/ State Job: C-91-127-02
Letting Date: 01/21/2011 Dist/Cnty: 01 - 043 (DUPAGE )
Airport: (58 & 59)WRS-3 State Job: C-91-127-02
Scope: FAP-365, CITY OF WARRENVILLE FROM W OF IL RT 59 (JOLIET RD)
TO EAST OF WINFIELD RD.

Payee:

K-FIVE CONSTRUCTION CORP 13769 MAIN ST  LEMONT , IL  60439

 

 

 

 

Percent Completed:  6.5%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
26,019,371.43      224,940.00      89,873.30      26,154,438.13      1,699,419.72     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 1,699,419.72     
Total paid this estimate:   1,699,419.72     
     Previous payments to contractor: -1,452,269.26     
     Payment to contractor this estimate: 247,150.46     
 
          Voucher #   BC01273 Date: 08/02/2011 1 of 1 247,150.46     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  03 Total: 247,150.46     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X4021000  TEMP ACCESS- PRIV ENT   24.000  0.000  24.000  0.000  3.000  3.000  246.00  738.00 
X4022000  TEMP ACCESS- COM ENT   17.000  0.000  17.000  0.000  1.200  1.200  714.00  856.80 
X7010216  TRAF CONT & PROT SPL   1.000  0.000  1.000  0.250  0.340  0.090  359,250.00  32,332.50 
X7030025  WET REF TEM TP T3 L&S   1,920.000  0.000  1,920.000  436.800  582.400  145.600  3.05  444.08 
X7030030  WET REF TEM TAPE T3 4   92,650.000  0.000  92,650.000  6,590.659  15,530.859  8,940.200  0.91  8,135.58 
X7030040  WET REF TEM TAPE T3 6   4,473.000  0.000  4,473.000  1,563.000  2,398.400  835.400  1.75  1,461.95 
X7030055  WET REF TEM TPE T3 24   842.000  0.000  842.000  0.000  22.700  22.700  7.00  158.90 
Z0013797  STAB CONSTR ENTRANCE   200.000  0.000  200.000  0.000  200.000  200.000  20.00  4,000.00 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.000  0.040  0.040  97,000.00  3,880.00 
Z0033028  MAINTAIN LIGHTING SYS   16.000  0.000  16.000  0.000  2.400  2.400  354.00  849.60 
Z0062456  TEMP PAVEMENT   3,797.000  0.000  3,797.000  3,149.600  3,168.500  18.900  37.50  708.75 
Z0064800  SELECTIVE CLEARING   38.000  130.000  168.000  38.000  168.000  130.000  175.00  22,750.00 
Z0073510  TEMP TR SIGNAL TIMING   3.000  0.000  3.000  0.000  1.500  1.500  1,050.00  1,575.00 
20100110  TREE REMOV 6-15   1,404.000  3,250.000  4,654.000  1,404.000  4,654.000  3,250.000  9.00  29,250.00 
20100210  TREE REMOV OVER 15   859.000  450.000  1,309.000  859.000  1,309.000  450.000  10.00  4,500.00 
20200100  EARTH EXCAVATION   82,252.000  0.000  82,252.000  0.000  250.900  250.900  9.60  2,408.64 
25100115  MULCH METHOD 2   36.000  0.000  36.000  0.000  3.600  3.600  200.00  720.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
28000250  TEMP EROS CONTR SEED   40,000.000  0.000  40,000.000  0.000  480.000  480.000  0.25  120.00 
44000100  PAVEMENT REM   99,944.000  0.000  99,944.000  0.000  1,364.900  1,364.900  7.60  10,373.24 
44000200  DRIVE PAVEMENT REM   5,449.000  0.000  5,449.000  19.000  289.500  270.500  5.70  1,541.85 
44000500  COMB CURB GUTTER REM   15,346.000  0.000  15,346.000  3,032.100  3,291.200  259.100  4.70  1,217.77 
44004250  PAVED SHLD REMOVAL   25,447.000  0.000  25,447.000  0.000  287.900  287.900  6.00  1,727.40 
83057355  LT P WD 60 CL4 15MA   16.000  0.000  16.000  0.000  12.000  12.000  843.30  10,119.60 
83057356  LT P WD 60 CL4 2-15MA   3.000  0.000  3.000  0.000  3.000  3.000  954.20  2,862.60 
85000200  MAIN EX TR SIG INSTAL   1.000  0.000  1.000  0.000  0.140  0.140  2,714.50  380.03 
89000100  TEMP TR SIG INSTALL   3.000  0.000  3.000  0.000  1.800  1.800  38,424.40  69,163.92 
89502375  REMOV EX TS EQUIP   3.000  0.000  3.000  0.000  2.100  2.100  11,468.50  24,083.85 
89502380  REMOV EX HANDHOLE   37.000  0.000  37.000  0.000  3.000  3.000  221.80  665.40 
X9100301  ENGR FIELD OFFICE TY A   0.000  30.000  30.000  0.000  2.500  2.500  4,050.00  10,125.00 
Total:   

$247,150.46

 