DOT Vendor: C30690  Contract: 62420 

IL Project:      From Date: 07/31/2011
Route: FAP 365
Section: (58 & 59)WRS-3 To Date: 08/15/2011
Project: NHF-CMF-TE-0365/012/ State Job: C-91-127-02
Letting Date: 01/21/2011 Dist/Cnty: 01 - 043 (DUPAGE )
Airport: (58 & 59)WRS-3 State Job: C-91-127-02
Scope: FAP-365, CITY OF WARRENVILLE FROM W OF IL RT 59 (JOLIET RD)
TO EAST OF WINFIELD RD.

Payee:

K-FIVE CONSTRUCTION CORP 13769 MAIN ST  LEMONT , IL  60439

 

 

 

 

Percent Completed:  10.42%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
26,019,371.43      224,940.00      89,873.30      26,154,438.13      2,724,849.63     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 2,724,849.63     
Mobilzation Paid:225,000.00     
Total paid this estimate:   2,724,849.63     
     Previous payments to contractor: -1,865,602.39     
     Payment to contractor this estimate: 859,247.24     
 
          Voucher #   BC02144 Date: 08/18/2011 1 of 1 859,247.24     

----------------------------------------------------------------------------------------------------------------------------------------------     

Includes 15% mobilization Pay Estimate Number:  05 Total: 859,247.24     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X2070304  POROUS GRAN EMB SPEC   464.000  0.000  464.000  0.000  464.000  464.000  40.00  18,560.00 
X4021000  TEMP ACCESS- PRIV ENT   24.000  0.000  24.000  5.400  6.000  0.600  246.00  147.60 
X7010216  TRAF CONT & PROT SPL   1.000  0.000  1.000  0.340  0.370  0.030  359,250.00  10,777.50 
X7030025  WET REF TEM TP T3 L&S   1,920.000  0.000  1,920.000  582.400  703.470  121.070  3.05  369.26 
X7030030  WET REF TEM TAPE T3 4   92,650.000  0.000  92,650.000  15,531.800  21,873.200  6,341.400  0.91  5,770.67 
X7030040  WET REF TEM TAPE T3 6   4,473.000  0.000  4,473.000  2,398.400  2,668.000  269.600  1.75  471.80 
X7030055  WET REF TEM TPE T3 24   842.000  0.000  842.000  22.700  64.000  41.300  7.00  289.10 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.040  0.070  0.030  97,000.00  2,910.00 
Z0033028  MAINTAIN LIGHTING SYS   16.000  0.000  16.000  2.400  3.000  0.600  354.00  212.40 
20200100  EARTH EXCAVATION   82,252.000  0.000  82,252.000  250.900  28,833.900  28,583.000  9.60  274,396.80 
20201200  REM & DISP UNS MATL   80,656.000  0.000  80,656.000  0.000  14,915.200  14,915.200  8.90  132,745.28 
20800150  TRENCH BACKFILL   6,841.000  0.000  6,841.000  0.000  151.100  151.100  10.00  1,511.00 
28000250  TEMP EROS CONTR SEED   40,000.000  0.000  40,000.000  576.000  676.000  100.000  0.25  25.00 
28001000  AGGREGATE - EROS CONT   276.000  0.000  276.000  0.000  21.050  21.050  45.00  947.25 
40600200  BIT MATLS PR CT   234.000  0.000  234.000  0.000  0.400  0.400  1.00  0.40 
44000100  PAVEMENT REM   99,944.000  0.000  99,944.000  6,938.800  14,501.200  7,562.400  7.60  57,474.24 
44000200  DRIVE PAVEMENT REM   5,449.000  0.000  5,449.000  628.600  1,746.300  1,117.700  5.70  6,370.89 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
44000300  CURB REM   1,340.000  0.000  1,340.000  0.000  32.600  32.600  4.65  151.59 
44000500  COMB CURB GUTTER REM   15,346.000  0.000  15,346.000  3,908.700  4,982.900  1,074.200  4.70  5,048.74 
44000600  SIDEWALK REM   15,312.000  0.000  15,312.000  3,642.500  3,677.800  35.300  0.80  28.24 
44004250  PAVED SHLD REMOVAL   25,447.000  0.000  25,447.000  3,014.600  4,038.000  1,023.400  6.00  6,140.40 
50105220  PIPE CULVERT REMOV   603.000  0.000  603.000  0.000  67.000  67.000  13.00  871.00 
542A0259  P CUL CL A 1 54   83.000  0.000  83.000  0.000  37.000  37.000  101.00  3,737.00 
542A1069  P CUL CL A 2 24   428.000  0.000  428.000  0.000  85.000  85.000  41.00  3,485.00 
54213657  PRC FLAR END SEC 12   43.000  0.000  43.000  0.000  12.000  12.000  590.00  7,080.00 
54213669  PRC FLAR END SEC 24   9.000  0.000  9.000  0.000  2.000  2.000  930.00  1,860.00 
54213699  PRC FLAR END SEC 54   4.000  0.000  4.000  0.000  2.000  2.000  2,330.00  4,660.00 
54214749  PRCF END S EL EQRS 54   1.000  0.000  1.000  0.000  1.000  1.000  2,470.00  2,470.00 
54247200  GRATING-C FL END S 54   4.000  0.000  4.000  0.000  1.000  1.000  730.00  730.00 
550A0050  STORM SEW CL A 1 12   854.000  0.000  854.000  0.000  64.700  64.700  32.00  2,070.40 
550A0120  STORM SEW CL A 1 24   125.000  0.000  125.000  0.000  78.600  78.600  46.00  3,615.60 
550A0340  STORM SEW CL A 2 12   3,670.000  0.000  3,670.000  0.000  394.300  394.300  32.00  12,617.60 
550A4720  SS CL A 1 EQRS 54   601.000  0.000  601.000  0.000  224.000  224.000  126.00  28,224.00 
55100500  STORM SEWER REM 12   1,905.000  0.000  1,905.000  0.000  10.900  10.900  13.00  141.70 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
60200805  CB TA 4 DIA T8G   16.000  0.000  16.000  0.000  3.000  3.000  1,310.00  3,930.00 
60201110  CB TA 4 DIA T11V F&G   18.000  0.000  18.000  0.000  3.000  3.000  1,480.00  4,440.00 
60201340  CB TA 4 DIA T24F&G   90.000  0.000  90.000  0.000  11.000  11.000  1,400.00  15,400.00 
60221700  MAN TA 5 DIA T8G   1.000  0.000  1.000  0.000  1.000  1.000  1,840.00  1,840.00 
67100100  MOBILIZATION   1.000  0.000  1.000  0.750  0.900  0.150  1,500,000.00  225,000.00 
70106800  CHANGEABLE MESSAGE SN   12.000  0.000  12.000  6.000  9.000  3.000  500.00  1,500.00 
78100200  TEMP RAIS REF PVT MKR   860.000  0.000  860.000  0.000  71.000  71.000  6.00  426.00 
78300100  PAVT MARKING REMOVAL   3,000.000  0.000  3,000.000  942.200  1,888.000  945.800  1.25  1,182.25 
78300200  RAISED REF PVT MK REM   3,000.000  0.000  3,000.000  28.000  94.000  66.000  8.40  554.40 
84200804  REM POLE FDN   12.000  0.000  12.000  0.000  10.000  10.000  221.80  2,218.00 
85000200  MAIN EX TR SIG INSTAL   1.000  0.000  1.000  0.140  0.190  0.050  2,714.50  135.73 
89502300  REM ELCBL FR CON   20,500.000  0.000  20,500.000  0.000  5,614.000  5,614.000  0.40  2,245.60 
89502380  REMOV EX HANDHOLE   37.000  0.000  37.000  3.000  7.000  4.000  221.80  887.20 
89502385  REMOV EX CONC FDN   26.000  0.000  26.000  0.000  7.000  7.000  221.80  1,552.60 
X9100301  ENGR FIELD OFFICE TY A   0.000  30.000  30.000  2.500  3.000  0.500  4,050.00  2,025.00 
Total:   

$859,247.24

 