State of Illinois Department of Transportation

Contract Search

 07/21/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 08/19/2013
DOT Vendor: C30690  Contract: 62419 

IL Project:      From Date: 08/02/2013
Route: FAP 365
Section: (57&58)WRS-2 To Date: 08/19/2013
Project: State Job: C-91-126-02
Letting Date: 01/21/2011 Dist/Cnty: 01 - 043 (DUPAGE )
Airport: (57&58)WRS-2 State Job: C-91-126-02
Scope: FAP-365, IL RT 56 IN CITY OF WHEATON FROM E OF WINFIELD RD
TO NAPERVILLE RD.

Payee:

K-FIVE CONSTRUCTION CORP 13769 MAIN ST  LEMONT , IL  60439

 

 

 

 

Percent Completed:  91.57%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
26,538,284.84      10,264,138.05      7,038,791.14      29,763,631.75      27,253,876.27     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 27,253,876.27     
Mobilzation Paid:150,000.00     
Total paid this estimate:   27,253,876.27     
     Previous payments to contractor: -26,582,016.67     
     Payment to contractor this estimate: 671,859.60     
 
          Voucher #   BC00657 Date: 08/21/2013 1 of 1 671,859.60     

----------------------------------------------------------------------------------------------------------------------------------------------     

Includes final mobilization Pay Estimate Number:  40 Total: 671,859.60     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X0325509  TEMP PAVEMT VAR DEPTH   2,430.000  851.000  3,281.000  2,909.000  3,281.000  372.000  46.00  17,112.00 
X4021000  TEMP ACCESS- PRIV ENT   5.000  0.000  5.000  3.000  5.000  2.000  311.00  622.00 
X4022000  TEMP ACCESS- COM ENT   15.000  0.000  15.000  12.000  15.000  3.000  630.00  1,890.00 
X4023000  TEMP ACCESS- ROAD   11.000  0.000  11.000  6.000  11.000  5.000  1,258.00  6,290.00 
X4401198  HMA SURF REM VAR DP   1,442.000  1,240.000  2,682.000  1,442.000  2,682.000  1,240.000  4.30  5,332.00 
X5610712  WATER MAIN REMOV 12   6,900.000  0.000  6,900.000  0.000  245.000  245.000  15.00  3,675.00 
X5610716  WATER MAIN REMOV 16   480.000  0.000  480.000  0.000  369.000  369.000  15.00  5,535.00 
X7810300  REC REF PVT MARKER   179.000  0.000  179.000  0.000  179.000  179.000  40.00  7,160.00 
X8730027  ELCBL C GROUND 6 1C   3,763.000  0.000  3,763.000  3,571.400  3,662.100  90.700  1.20  108.84 
Z0073002  TEMP SOIL RETEN SYSTM   1,281.000  0.000  1,281.000  916.700  1,281.000  364.300  26.60  9,690.38 
20201200  REM & DISP UNS MATL   70,551.000  -46,173.200  24,377.800  24,922.400  24,377.800  -544.600  8.75  -4,765.25 
21001000  GEOTECH FAB F/GR STAB   34,511.000  25,481.000  59,992.000  58,596.000  59,992.000  1,396.000  1.55  2,163.80 
21101625  TOPSOIL F & P 6   77,982.000  -13,982.000  64,000.000  0.000  31,544.000  31,544.000  1.75  55,202.00 
21101630  TOPSOIL F & P 8   45,153.000  -41,553.000  3,600.000  0.000  1,833.200  1,833.200  2.00  3,666.40 
25000600  POTASSIUM FERT NUTR   1,438.000  0.000  1,438.000  445.500  592.200  146.700  1.25  183.37 
40600200  BIT MATLS PR CT   129.000  0.000  129.000  103.840  112.670  8.830  547.00  4,830.01 
40600982  HMA SURF REM BUTT JT   476.000  53.330  529.330  476.000  529.330  53.330  14.05  749.29 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
40603080  HMA BC IL-19.0 N50   421.000  36.300  457.300  393.780  457.300  63.520  101.00  6,415.52 
40603153  P HMA SC SMA N80   15,211.000  61.000  15,272.000  14,990.700  15,272.000  281.300  95.00  26,723.50 
40603310  HMA SC "C" N50   302.000  -15.850  286.150  74.000  286.150  212.150  125.00  26,518.75 
40603595  P HMA SC "F" N90   178.000  144.850  322.850  178.000  322.850  144.850  98.00  14,195.30 
44000100  PAVEMENT REM   110,655.000  1,457.800  112,112.800  99,289.800  99,830.000  540.200  7.45  4,024.49 
48203029  HMA SHOULDERS 8   1,697.000  141.200  1,838.200  1,129.200  1,322.400  193.200  23.05  4,453.26 
48203053  HMA SHOULDERS 14   30,658.000  0.000  30,658.000  25,835.100  29,606.050  3,770.950  47.00  177,234.65 
50100100  REM EXIST STRUCT   1.000  0.000  1.000  0.000  1.000  1.000  17,500.00  17,500.00 
55100500  STORM SEWER REM 12   1,682.000  0.000  1,682.000  997.100  500.100  -497.000  6.00  -2,982.00 
55100700  STORM SEWER REM 15   600.000  0.000  600.000  466.000  97.000  -369.000  6.00  -2,214.00 
60602500  CONC GUTTER TA   1,420.000  -1,420.000  0.000  1,420.000  0.000  -1,420.000  16.00  -22,720.00 
60603800  COMB CC&G TB6.12   27,887.000  3,290.900  31,177.900  28,107.000  30,458.700  2,351.700  12.00  28,220.40 
60604400  COMB CC&G TB6.18   1,549.000  405.200  1,954.200  1,663.200  1,208.000  -455.200  19.80  -9,012.96 
60605000  COMB CC&G TB6.24   5,016.000  353.000  5,369.000  5,016.000  5,369.000  353.000  24.30  8,577.90 
60608300  COMB CC&G TM2.12   2,039.000  -596.000  1,443.000  2,039.000  1,443.000  -596.000  12.00  -7,152.00 
60619600  CONC MED TSB6.12   22,713.000  1,019.380  23,732.380  22,713.000  23,109.300  396.300  7.90  3,130.77 
60624600  CORRUGATED MED   200.000  128.700  328.700  218.300  328.700  110.400  10.00  1,104.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
67100100  MOBILIZATION   1.000  0.000  1.000  0.900  1.000  0.100  1,500,000.00  150,000.00 
72400310  REMOV SIGN PANEL T1   639.000  0.000  639.000  213.000  639.000  426.000  10.00  4,260.00 
72400320  REMOV SIGN PANEL T2   92.000  0.000  92.000  20.000  92.000  72.000  10.00  720.00 
73700100  REM GR MT SIN SUPPORT   166.000  0.000  166.000  52.000  166.000  114.000  25.00  2,850.00 
78000100  THPL PVT MK LTR & SYM   4,406.000  37.000  4,443.000  2,826.900  4,220.500  1,393.600  3.50  4,877.60 
78000200  THPL PVT MK LINE 4   54,921.000  0.000  54,921.000  13,056.000  54,921.000  41,865.000  0.60  25,119.00 
78000400  THPL PVT MK LINE 6   26,707.000  185.000  26,892.000  17,398.000  24,719.000  7,321.000  0.75  5,490.75 
78000600  THPL PVT MK LINE 12   5,659.000  0.000  5,659.000  2,623.900  5,659.000  3,035.100  1.75  5,311.42 
78000650  THPL PVT MK LINE 24   1,428.000  0.000  1,428.000  829.500  1,393.000  563.500  3.75  2,113.12 
78100100  RAISED REFL PAVT MKR   943.000  0.000  943.000  0.000  943.000  943.000  23.00  21,689.00 
78300100  PAVT MARKING REMOVAL   10,000.000  34,333.400  44,333.400  10,498.300  10,577.400  79.100  1.25  98.87 
85700205  FAC T4 CAB SPL   5.000  -1.000  4.000  3.000  4.000  1.000  19,008.00  19,008.00 
86400100  TRANSCEIVER - FIB OPT   5.000  0.000  5.000  3.000  4.000  1.000  3,475.00  3,475.00 
88030050  SH LED 1F 3S BM   2.000  0.000  2.000  1.000  2.000  1.000  842.00  842.00 
88500100  INDUCTIVE LOOP DETECT   61.000  0.000  61.000  50.000  61.000  11.000  187.00  2,057.00 
FRC04101  PAVT MRK REM WTR BLAST   0.000  19,200.000  19,200.000  17,324.380  18,480.920  1,156.540  1.00  1,156.54 
XXX19101  ACCELERATION   0.000  19,500.000  19,500.000  0.000  10,513.360  10,513.360  1.00  10,513.36 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X9100604  TOPSOIL EX & PL, 24"   0.000  19,054.970  19,054.970  17,852.700  19,054.970  1,202.270  15.65  18,815.52 
Total:   

$671,859.60

 