DOT Vendor: C37140  Contract: 62410 

IL Project:      From Date: 11/30/2012
Route: FAP 307
Section: 130R-2 To Date: 12/31/2012
Project: NHF-0307/033/ State Job: C-91-101-02
Letting Date: 01/20/2012 Dist/Cnty: 01 - 043 (DUPAGE )
Airport: 130R-2 State Job: C-91-101-02
Scope: FAP-307, IL 64 FROM DUNHAM RD TO IL 59 WITHIN CITIES OF ST
CHARLES & WEST CHICAGO.

Payee:

MARTAM CONST INC & HERLIHY 1200 GASKET DR  ELGIN , IL  60120

 

 

 

 

Percent Completed:  51.77%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
39,568,013.38      1,275,793.23      65,098.00      40,778,708.61      21,112,406.67     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 21,112,406.67     
Total paid this estimate:   21,112,406.67     
     Previous payments to contractor: -19,405,778.32     
     Payment to contractor this estimate: 1,706,628.35     
 
          Voucher #   CC12518 Date: 01/10/2013 1 of 1 1,706,628.35     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  09 Total: 1,706,628.35     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X0301797  GATE REMOVAL   2.000  0.000  2.000  0.000  1.000  1.000  800.00  800.00 
X0322936  REMOV EX FLAR END SEC   116.000  0.000  116.000  40.000  42.000  2.000  100.00  200.00 
X0325225  BRICK PAVT REM & REPL   222.000  0.000  222.000  0.000  110.000  110.000  20.00  2,200.00 
X0327371  PLUG EXISTING PIPE   67.000  0.000  67.000  0.000  18.000  18.000  180.00  3,240.00 
X4022000  TEMP ACCESS- COM ENT   37.000  0.000  37.000  21.000  26.400  5.400  1,800.00  9,720.00 
X4024100  TEMP ACCESS WINTERIZE   5,769.000  0.000  5,769.000  0.000  1,341.000  1,341.000  0.10  134.10 
X6640308  CH LK GATES SPL   1.000  0.000  1.000  0.000  1.000  1.000  6,500.00  6,500.00 
X7010216  TRAF CONT & PROT SPL   1.000  0.000  1.000  0.450  0.500  0.050  710,000.00  35,500.00 
X7030025  WET REF TEM TP T3 L&S   2,031.000  -300.000  1,731.000  0.000  36.000  36.000  3.00  108.00 
X7030030  WET REF TEM TAPE T3 4   176,423.000  -70,000.000  106,423.000  206.000  6,281.000  6,075.000  0.65  3,948.75 
X7030055  WET REF TEM TPE T3 24   1,521.000  0.000  1,521.000  0.000  34.000  34.000  4.00  136.00 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.470  0.520  0.050  90,000.00  4,500.00 
Z0030355  IMP ATTN REL S U TL2   4.000  0.000  4.000  2.000  4.000  2.000  1,600.00  3,200.00 
Z0033028  MAINTAIN LIGHTING SYS   18.000  0.000  18.000  10.400  12.400  2.000  350.00  700.00 
Z0046304  P UNDR FOR STRUCT 4   299.000  0.000  299.000  0.000  178.000  178.000  23.36  4,158.08 
Z0062456  TEMP PAVEMENT   8,860.000  0.000  8,860.000  3,583.500  6,037.500  2,454.000  28.00  68,712.00 
Z0062458  TEMP PAVEMT VAR DEPTH   484.300  0.000  484.300  131.800  484.300  352.500  85.00  29,962.50 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
21001000  GEOTECH FAB F/GR STAB   200,260.000  0.000  200,260.000  81,616.050  137,415.050  55,799.000  0.80  44,639.20 
25100115  MULCH METHOD 2   28.500  0.000  28.500  6.440  22.140  15.700  900.00  14,130.00 
25100630  EROSION CONTR BLANKET   135,303.000  0.000  135,303.000  0.000  178.000  178.000  1.00  178.00 
28000250  TEMP EROS CONTR SEED   16,907.000  0.000  16,907.000  644.300  2,210.300  1,566.000  0.10  156.60 
28000305  TEMP DITCH CHECKS   790.000  0.000  790.000  755.000  129.000  -626.000  7.00  -4,382.00 
28000510  INLET FILTERS   249.000  0.000  249.000  10.000  13.000  3.000  25.00  75.00 
31101200  SUB GRAN MAT B 4   7,740.000  0.000  7,740.000  1,335.000  4,398.000  3,063.000  4.00  12,252.00 
31200502  STAB SUBBASE HMA 4.5   192,674.000  0.000  192,674.000  66,189.000  81,767.000  15,578.000  14.20  221,207.60 
35300500  PCC BSE CSE 10   5,397.000  0.000  5,397.000  0.000  2,534.000  2,534.000  36.00  91,224.00 
35501312  HMA BASE CSE 7   2,339.000  0.000  2,339.000  0.000  636.000  636.000  24.00  15,264.00 
40603080  HMA BC IL-19.0 N50   294.800  0.000  294.800  0.000  81.000  81.000  59.00  4,779.00 
42000501  PCC PVT 10 JOINTED   155,948.000  0.000  155,948.000  37,932.000  50,469.000  12,537.000  38.00  476,406.00 
42001420  BR APPR PVT CON (PCC)   2,159.000  0.000  2,159.000  400.000  800.000  400.000  45.00  18,000.00 
42300400  PCC DRIVEWAY PAVT 8   5,401.000  0.000  5,401.000  2,695.000  3,762.000  1,067.000  40.00  42,680.00 
44000100  PAVEMENT REM   114,360.000  0.000  114,360.000  27,775.000  27,836.000  61.000  5.00  305.00 
48101620  AGGREGATE SHLDS B 10   5,695.000  0.000  5,695.000  0.000  4,884.000  4,884.000  11.00  53,724.00 
48300500  PCC SHOULDERS 10   30,879.000  0.000  30,879.000  23,760.000  28,478.000  4,718.000  37.00  174,566.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
50105220  PIPE CULVERT REMOV   4,463.000  0.000  4,463.000  2,450.000  2,482.000  32.000  1.00  32.00 
50200100  STRUCTURE EXCAVATION   8,018.000  0.000  8,018.000  6,843.100  6,847.400  4.300  15.00  64.50 
50300225  CONC STRUCT   2,947.300  0.000  2,947.300  1,761.700  2,046.500  284.800  590.43  168,154.47 
50300255  CONC SUP-STR   1,575.500  0.000  1,575.500  716.000  756.000  40.000  695.58  27,823.20 
50300260  BR DECK GROOVING   3,710.000  0.000  3,710.000  0.000  2,286.000  2,286.000  5.55  12,687.30 
50800205  REINF BARS, EPOXY CTD   752,420.000  0.000  752,420.000  466,342.700  476,311.700  9,969.000  1.09  10,866.21 
50800515  BAR SPLICERS   2,676.000  0.000  2,676.000  2,562.000  2,557.000  -5.000  23.42  -117.10 
550A0420  STORM SEW CL A 2 27   1,644.000  0.000  1,644.000  8.000  28.000  20.000  52.00  1,040.00 
60108200  PIPE UNDERDRAIN 6 SP   2,626.000  0.000  2,626.000  125.000  409.000  284.000  10.00  2,840.00 
60237470  INLETS TA T24F&G   32.000  0.000  32.000  17.000  19.000  2.000  800.00  1,600.00 
60600605  CONC CURB TB   904.000  0.000  904.000  92.000  122.000  30.000  14.00  420.00 
60603800  COMB CC&G TB6.12   1,870.000  0.000  1,870.000  602.000  1,389.000  787.000  14.00  11,018.00 
60605000  COMB CC&G TB6.24   32,318.000  0.000  32,318.000  1,892.000  4,015.000  2,123.000  15.00  31,845.00 
63100167  TR BAR TRM T1 SPL TAN   2.000  0.000  2.000  0.000  2.000  2.000  2,845.00  5,690.00 
70103815  TR CONT SURVEILLANCE   300.000  0.000  300.000  98.400  118.400  20.000  1.00  20.00 
70106800  CHANGEABLE MESSAGE SN   40.000  0.000  40.000  7.400  11.400  4.000  900.00  3,600.00 
70300240  TEMP PVT MK LINE 6   9,520.000  0.000  9,520.000  5,409.000  3,728.000  -1,681.000  0.31  -521.11 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
70300280  TEMP PVT MK LINE 24   670.000  0.000  670.000  176.000  188.000  12.000  1.00  12.00 
70301000  WORK ZONE PAVT MK REM   67,304.000  0.000  67,304.000  1,893.000  4,135.000  2,242.000  0.01  22.42 
70400100  TEMP CONC BARRIER   4,000.000  0.000  4,000.000  3,976.000  4,000.000  24.000  16.00  384.00 
70400200  REL TEMP CONC BARRIER   4,000.000  0.000  4,000.000  0.000  3,976.000  3,976.000  6.00  23,856.00 
78300100  PAVT MARKING REMOVAL   18,550.000  0.000  18,550.000  17,626.200  18,550.000  923.800  0.05  46.19 
81028240  UNDRGRD C GALVS 4   3,002.000  0.000  3,002.000  1,676.000  1,716.000  40.000  38.00  1,520.00 
81304520  JUN BOX EM S 18X8X8   4.000  0.000  4.000  0.000  4.000  4.000  1,260.00  5,040.00 
83600200  LIGHT POLE FDN 24D   2,249.000  0.000  2,249.000  0.000  117.000  117.000  180.00  21,060.00 
88600700  PREFORM DETECT LOOP   6,226.000  0.000  6,226.000  753.100  1,126.100  373.000  18.50  6,900.50 
FRC01101  STORM SEWER MODIFICATI   0.000  10,000.000  10,000.000  4,097.310  10,000.000  5,902.690  1.00  5,902.69 
FRC01201  PAVEMENT PATCHING   0.000  20,000.000  20,000.000  18,474.870  20,000.000  1,525.130  1.00  1,525.13 
XXX19100  ACCELERATION/WINTER   0.000  30,000.000  30,000.000  0.000  24,373.120  24,373.120  1.00  24,373.12 
Total:   

$1,706,628.35

 