Illinois Department of Transportation, Ann L. Schneider, Secretary
Loading
Patrick J. Quinn, Governor
Traveling PublicMapsProjectsRoad ClosuresNewsDoing BusinessLetting & BiddingCareers@IDOTGeneral Info





State of Illinois Department of Transportation

Contract Search

 04/15/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 03/31/2013
DOT Vendor: C37140  Contract: 62410 

IL Project:      From Date: 03/15/2013
Route: FAP 307
Section: 130R-2 To Date: 03/31/2013
Project: NHF-0307/033/ State Job: C-91-101-02
Letting Date: 01/20/2012 Dist/Cnty: 01 - 043 (DUPAGE )
Airport: 130R-2 State Job: C-91-101-02
Scope: FAP-307, IL 64 FROM DUNHAM RD TO IL 59 WITHIN CITIES OF ST
CHARLES & WEST CHICAGO.

Payee:

MARTAM CONST INC & HERLIHY 1200 GASKET DR  ELGIN , IL  60120

 

 

 

 

Percent Completed:  58.11%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
39,568,013.38      1,959,851.92      228,600.50      41,299,264.80      23,997,466.25     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 23,997,466.25     
Total paid this estimate:   23,997,466.25     
     Previous payments to contractor: -23,740,671.26     
     Payment to contractor this estimate: 256,794.99     
 
          Voucher #   CC17558 Date: 04/08/2013 1 of 1 256,794.99     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  13 Total: 256,794.99     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X7010216  TRAF CONT & PROT SPL   1.000  0.000  1.000  0.620  0.660  0.040  710,000.00  28,400.00 
X8250505  LIGHT CONTROLLER SPL   3.000  0.000  3.000  0.000  0.100  0.100  11,300.00  1,130.00 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.670  0.730  0.060  90,000.00  5,400.00 
Z0033028  MAINTAIN LIGHTING SYS   18.000  0.000  18.000  18.000  10.000  -8.000  350.00  -2,800.00 
25100630  EROSION CONTR BLANKET   135,303.000  0.000  135,303.000  178.000  350.000  172.000  1.00  172.00 
28000305  TEMP DITCH CHECKS   790.000  0.000  790.000  129.000  671.000  542.000  7.00  3,794.00 
28000500  INLET & PIPE PROTECT   170.000  0.000  170.000  102.000  170.000  68.000  15.00  1,020.00 
28000510  INLET FILTERS   249.000  0.000  249.000  20.000  32.000  12.000  25.00  300.00 
35300500  PCC BSE CSE 10   5,397.000  0.000  5,397.000  3,643.000  3,578.000  -65.000  36.00  -2,340.00 
35400500  PCC BASE CSE W 10   169.000  0.000  169.000  0.000  65.000  65.000  65.00  4,225.00 
50200100  STRUCTURE EXCAVATION   8,018.000  0.000  8,018.000  7,436.400  7,512.400  76.000  15.00  1,140.00 
50300225  CONC STRUCT   2,947.300  0.000  2,947.300  2,333.400  2,454.400  121.000  590.43  71,442.03 
50800205  REINF BARS, EPOXY CTD   752,420.000  0.000  752,420.000  524,138.700  571,032.700  46,894.000  1.09  51,114.46 
51201800  FUR STL PILE HP14X73   16,932.000  0.000  16,932.000  10,945.000  11,985.000  1,040.000  50.00  52,000.00 
51202305  DRIVING PILES   16,932.000  0.000  16,932.000  8,346.000  9,236.000  890.000  1.00  890.00 
51204650  PILE SHOES   328.000  0.000  328.000  268.000  300.000  32.000  80.00  2,560.00 
70103815  TR CONT SURVEILLANCE   300.000  0.000  300.000  183.400  204.400  21.000  1.00  21.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
70106800  CHANGEABLE MESSAGE SN   40.000  0.000  40.000  19.400  22.400  3.000  900.00  2,700.00 
70300220  TEMP PVT MK LINE 4   6,890.000  70,000.000  76,890.000  76,890.000  63,036.000  -13,854.000  0.30  -4,156.20 
70301000  WORK ZONE PAVT MK REM   67,304.000  0.000  67,304.000  4,135.000  4,685.000  550.000  0.01  5.50 
81603090  UD 3#4#6GXLPUSE 1 1/4   40,214.000  0.000  40,214.000  9,422.000  10,903.000  1,481.000  8.25  12,218.25 
X9101901  TEMP EPOXY L&S   0.000  1,150.000  1,150.000  0.000  123.100  123.100  3.00  369.30 
X9101902  TEMP EPOXY, 4"   0.000  74,000.000  74,000.000  0.000  27,257.000  27,257.000  0.65  17,717.05 
X9101903  TEMP EPOXY, 6"   0.000  1,800.000  1,800.000  0.000  542.000  542.000  1.30  704.60 
X9101905  TEMP EPOXY, 24"   0.000  1,000.000  1,000.000  0.000  117.000  117.000  4.00  468.00 
X9102101  PAVMT SEPARATION JNT   0.000  310.000  310.000  144.000  310.000  166.000  50.00  8,300.00 
Total:   

$256,794.99

 

IDOT Privacy Statement | Illinois Privacy Information | Kids Privacy | Web Accessibility  | FOIA