Invoice Archive
Contract Number
&
Estimate Numbers are listed below
Go to Current Estimate for this Contract Number
|
Contractor Invoice
Previous Report 05/13/2011
| DOT Vendor: |
C35050 |
|
Contract: |
62253 |
| IL Project: |
|
From Date: |
02/09/2011 |
| Route: |
FAI 57 |
|
|
|
| Section: |
99(1&2)R-3&9-1HB-1-BR-2 |
To Date: |
05/13/2011 |
| Project: |
IM-057-7/276/335 |
State Job: |
C-91-283-01 |
| Letting Date: |
09/19/2008 |
Dist/Cnty: |
01 - 197 (WILL )
|
| Airport: |
99(1&2)R-3&9-1HB-1-BR-2 |
State Job: |
C-91-283-01 |
| Scope: |
FAI-57, MANHATTAN-MONROE RD & ENT/EXT RAMP TO I57.
|
|
|
|
Payee: |
LORIG CONSTRUCTION CO |
250 E TOUHY AVE DES PLAINES , IL 60018
|
|
|
|
|
|
|
| Percent Completed: 98.69% |
Contract Awarded
Amount |
Additions |
Deductions |
Total Adjusted
Contract Value |
Total Amount
Due to Date |
| 9,886,310.03 |
2,723,301.73 |
1,438,219.87 |
11,171,391.89 |
11,025,087.04 |
|
Total retainage incld this est held by IDOT:
|
|
|
0.00
|
| Total
due after retainage: |
|
|
11,025,087.04 |
| Total
paid this estimate: |
|
|
11,025,087.04 |
|
Previous payments to contractor: |
|
|
-10,799,661.81 |
|
Payment to contractor this estimate: |
|
| 225,425.23 |
| |
|
Voucher # CC23424 | Date: 05/17/2011 |
|
1
of 2
|
121,478.81 |
|
Voucher # CC23422 | Date: 05/17/2011 |
|
2
of 2
|
103,946.42 |
|
---------------------------------------------------------------------------------------------------------------------------------------------- |
|
|
|
Pay Estimate Number: 27 |
Total: |
225,425.23 |
Report of Resident Engineer
Completed Work-In Place
For This Estimate Only
|
|
|
PAY ITEM |
QUANTITY |
PAYMENT |
|
Number |
Description |
Awarded |
Net of Adds/
Deducts |
Total Adjusted |
Completed Prior Est. |
Completed to Date |
This Estimate |
$ Unit Price |
$ This Estimate |
| X0322034 |
STORM SEW WM REQ 15 |
56.000 |
44.300 |
100.300 |
41.000 |
100.300 |
59.300 |
75.00 |
4,447.50 |
| X0323574 |
MAINTAIN LIGHTING SYS |
14.000 |
9.520 |
23.520 |
22.420 |
23.520 |
1.100 |
1,100.00 |
1,210.00 |
| X0325047 |
EC C EPR RHW 3C#2#4G |
470.000 |
1.100 |
471.100 |
470.000 |
471.100 |
1.100 |
10.00 |
11.00 |
| X4067107 |
POL LB MM IL4.75 N50 |
435.000 |
-62.350 |
372.650 |
357.900 |
372.650 |
14.750 |
150.00 |
2,212.50 |
| X6700410 |
ENGR FLD OFF A SPL |
18.000 |
10.000 |
28.000 |
27.000 |
28.000 |
1.000 |
2,000.00 |
2,000.00 |
| X7330105 |
OSS WALKWAY TY A |
71.000 |
0.010 |
71.010 |
71.000 |
71.010 |
0.010 |
285.00 |
2.85 |
| 20700420 |
POROUS GRAN EMB SUBGR |
365.000 |
1,840.990 |
2,205.990 |
2,122.000 |
2,205.990 |
83.990 |
45.00 |
3,779.55 |
| 25000210 |
SEEDING CL 2A |
1.500 |
6.250 |
7.750 |
3.000 |
7.000 |
4.000 |
1,900.00 |
7,600.00 |
| 25000310 |
SEEDING CL 4 |
1.000 |
0.220 |
1.220 |
1.000 |
1.220 |
0.220 |
2,350.00 |
517.00 |
| 25000400 |
NITROGEN FERT NUTR |
342.000 |
655.500 |
997.500 |
642.000 |
997.500 |
355.500 |
2.00 |
711.00 |
| 25000500 |
PHOSPHORUS FERT NUTR |
342.000 |
655.500 |
997.500 |
642.000 |
997.500 |
355.500 |
2.00 |
711.00 |
| 25000600 |
POTASSIUM FERT NUTR |
342.000 |
655.500 |
997.500 |
642.000 |
997.500 |
355.500 |
2.00 |
711.00 |
| 25100630 |
EROSION CONTR BLANKET |
18,400.000 |
59,708.200 |
78,108.200 |
49,400.000 |
78,108.200 |
28,708.200 |
1.10 |
31,579.02 |
| 28100101 |
STONE RIPRAP CL A1 |
63.000 |
16.200 |
79.200 |
78.000 |
79.200 |
1.200 |
45.00 |
54.00 |
| 40600100 |
BIT MATLS PR CT |
1,080.000 |
0.000 |
1,080.000 |
0.000 |
2.100 |
2.100 |
0.01 |
0.02 |
| 40603595 |
P HMA SC "F" N90 |
354.000 |
268.570 |
622.570 |
529.000 |
622.570 |
93.570 |
150.00 |
14,035.50 |
| 40701936 |
HMA PAVT FD 12 3/4 |
6,587.000 |
546.540 |
7,133.540 |
7,070.000 |
7,133.540 |
63.540 |
60.00 |
3,812.40 |
continued
|
PAY ITEM |
QUANTITY |
PAYMENT |
|
Number |
Description |
Awarded |
Net of Adds/
Deducts |
Total Adjusted |
Completed Prior Est. |
Completed to Date |
This Estimate |
$ Unit Price |
$ This Estimate |
| 42100320 |
CONT REINF PCC PVT 11 |
1,401.000 |
2.500 |
1,403.500 |
1,401.000 |
1,403.500 |
2.500 |
58.78 |
146.95 |
| 42100920 |
PAVT REINFORCEMENT 11 |
1,401.000 |
2.500 |
1,403.500 |
1,401.000 |
1,403.500 |
2.500 |
38.00 |
95.00 |
| 42300400 |
PCC DRIVEWAY PAVT 8 |
95.000 |
35.420 |
130.420 |
95.000 |
130.420 |
35.420 |
50.00 |
1,771.00 |
| 44000100 |
PAVEMENT REM |
17,948.000 |
-2,215.570 |
15,732.430 |
15,396.890 |
15,732.430 |
335.540 |
8.50 |
2,852.09 |
| 48300600 |
PCC SHOULDERS 11 |
1,275.000 |
173.940 |
1,448.940 |
1,275.000 |
1,448.940 |
173.940 |
60.00 |
10,436.40 |
| 50800205 |
REINF BARS, EPOXY CTD |
170,340.000 |
3,489.340 |
173,829.340 |
170,409.340 |
173,829.340 |
3,420.000 |
1.45 |
4,959.00 |
| 550A0410 |
STORM SEW CL A 2 24 |
80.000 |
-72.000 |
8.000 |
0.000 |
8.000 |
8.000 |
56.00 |
448.00 |
| 55100900 |
STORM SEWER REM 18 |
470.000 |
51.230 |
521.230 |
470.000 |
521.230 |
51.230 |
20.00 |
1,024.60 |
| 55101800 |
STORM SEWER REM 42 |
15.000 |
0.200 |
15.200 |
15.000 |
15.200 |
0.200 |
32.00 |
6.40 |
| 60107600 |
PIPE UNDERDRAINS 4 |
3,064.000 |
187.500 |
3,251.500 |
3,064.000 |
3,251.500 |
187.500 |
20.00 |
3,750.00 |
| 60109580 |
P UNDR FOR STRUCT 4 |
292.000 |
28.760 |
320.760 |
292.000 |
320.760 |
28.760 |
15.00 |
431.40 |
| 60201330 |
CB TA 4 DIA T23F&G |
10.000 |
-4.000 |
6.000 |
5.000 |
6.000 |
1.000 |
1,700.00 |
1,700.00 |
| 60237470 |
INLETS TA T24F&G |
5.000 |
5.000 |
10.000 |
9.000 |
10.000 |
1.000 |
900.00 |
900.00 |
| 60500040 |
REMOV MANHOLES |
3.000 |
1.000 |
4.000 |
3.000 |
4.000 |
1.000 |
100.00 |
100.00 |
| 60605000 |
COMB CC&G TB6.24 |
1,827.000 |
929.700 |
2,756.700 |
2,222.000 |
2,756.700 |
534.700 |
22.00 |
11,763.40 |
| 60605900 |
COMB CC&G TB9.12 |
1,757.000 |
-43.900 |
1,713.100 |
1,086.000 |
1,713.100 |
627.100 |
21.00 |
13,169.10 |
| 60618320 |
CONC MEDIAN SURF 6 |
10,330.000 |
-8,499.900 |
1,830.100 |
1,459.000 |
1,830.100 |
371.100 |
5.00 |
1,855.50 |
continued
|
PAY ITEM |
QUANTITY |
PAYMENT |
|
Number |
Description |
Awarded |
Net of Adds/
Deducts |
Total Adjusted |
Completed Prior Est. |
Completed to Date |
This Estimate |
$ Unit Price |
$ This Estimate |
| 63000000 |
SPBGR TY A |
2,825.000 |
1,621.900 |
4,446.900 |
4,237.500 |
4,446.900 |
209.400 |
20.50 |
4,292.70 |
| 66900200 |
NON SPL WASTE DISPOSL |
300.000 |
1,441.400 |
1,741.400 |
1,470.000 |
1,741.400 |
271.400 |
80.00 |
21,712.00 |
| 72000100 |
SIGN PANEL T1 |
129.000 |
127.510 |
256.510 |
232.250 |
256.510 |
24.260 |
17.00 |
412.42 |
| 72000200 |
SIGN PANEL T2 |
30.000 |
52.000 |
82.000 |
69.000 |
82.000 |
13.000 |
21.00 |
273.00 |
| 78008210 |
POLYUREA PM T1 LN 4 |
5,829.000 |
22,652.500 |
28,481.500 |
25,329.000 |
28,481.500 |
3,152.500 |
0.65 |
2,049.13 |
| 78008250 |
POLYUREA PM T1 LN 12 |
454.000 |
461.500 |
915.500 |
654.000 |
915.500 |
261.500 |
4.00 |
1,046.00 |
| 78200410 |
GUARDRAIL MKR TYPE A |
39.000 |
42.000 |
81.000 |
61.000 |
81.000 |
20.000 |
8.00 |
160.00 |
| 78200500 |
BARRIER WALL MARKERS |
6.000 |
680.000 |
686.000 |
518.000 |
686.000 |
168.000 |
12.00 |
2,016.00 |
| 78201000 |
TERMINAL MARKER - DA |
7.000 |
6.000 |
13.000 |
12.000 |
13.000 |
1.000 |
38.00 |
38.00 |
| 81000600 |
CON T 2 GALVS |
2,829.000 |
324.500 |
3,153.500 |
2,829.000 |
3,153.500 |
324.500 |
13.00 |
4,218.50 |
| 81000800 |
CON T 3 GALVS |
56.000 |
47.900 |
103.900 |
56.000 |
103.900 |
47.900 |
25.00 |
1,197.50 |
| 81001000 |
CON T 4 GALVS |
66.000 |
565.500 |
631.500 |
341.000 |
631.500 |
290.500 |
34.00 |
9,877.00 |
| 81018700 |
CON P 3 GALVS |
1,133.000 |
97.400 |
1,230.400 |
1,133.000 |
1,230.400 |
97.400 |
25.00 |
2,435.00 |
| 81200230 |
CON EMB STR 2 PVC |
660.000 |
18.300 |
678.300 |
660.000 |
678.300 |
18.300 |
5.50 |
100.65 |
| 81304600 |
JUN BOX EM S 18X12X6 |
4.000 |
2.000 |
6.000 |
5.000 |
6.000 |
1.000 |
1,100.00 |
1,100.00 |
| 81800320 |
A CBL 3-1C4 MESS WIRE |
240.000 |
452.000 |
692.000 |
249.300 |
692.000 |
442.700 |
6.00 |
2,656.20 |
| 83057355 |
LT P WD 60 CL4 15MA |
4.000 |
1.000 |
5.000 |
4.000 |
5.000 |
1.000 |
1,100.00 |
1,100.00 |
continued
|
PAY ITEM |
QUANTITY |
PAYMENT |
|
Number |
Description |
Awarded |
Net of Adds/
Deducts |
Total Adjusted |
Completed Prior Est. |
Completed to Date |
This Estimate |
$ Unit Price |
$ This Estimate |
| 87301305 |
ELCBL C LEAD 14 1PR |
4,532.000 |
121.500 |
4,653.500 |
4,532.000 |
4,653.500 |
121.500 |
1.00 |
121.50 |
| FRC00100 |
ROADWAY PRESERVATION |
0.000 |
47,400.000 |
47,400.000 |
45,857.260 |
47,400.000 |
1,542.740 |
1.00 |
1,542.74 |
| FRC00701 |
ATTENUATOR BASES |
0.000 |
41,943.220 |
41,943.220 |
35,210.000 |
41,943.220 |
6,733.220 |
1.00 |
6,733.22 |
| FRC00800 |
LTG CONTR RADIO CONT D |
0.000 |
27,883.390 |
27,883.390 |
25,400.000 |
27,883.390 |
2,483.390 |
1.00 |
2,483.39 |
| FRC01801 |
REPLACE RUMBLE STRIPS |
0.000 |
8,940.000 |
8,940.000 |
1,741.200 |
3,503.640 |
1,762.440 |
1.00 |
1,762.44 |
| FRC02500 |
DRAINAGE/FIELD TILE |
0.000 |
2,860.980 |
2,860.980 |
2,345.000 |
2,860.980 |
515.980 |
1.00 |
515.98 |
| FRC03503 |
CONCRETE FDN GROUND MT |
0.000 |
18,249.060 |
18,249.060 |
6,050.000 |
18,249.060 |
12,199.060 |
1.00 |
12,199.06 |
| FRC04002 |
ABANDON EXIST CULVERT |
0.000 |
13,840.360 |
13,840.360 |
10,875.000 |
13,840.360 |
2,965.360 |
1.00 |
2,965.36 |
| FRC04200 |
REMOVE LIGHT POLE FDN |
0.000 |
4,040.630 |
4,040.630 |
3,620.000 |
4,040.630 |
420.630 |
1.00 |
420.63 |
| FRC04300 |
STRM SEWER PIPE STA 14 |
0.000 |
4,774.500 |
4,774.500 |
4,700.000 |
4,774.500 |
74.500 |
1.00 |
74.50 |
| FRC04500 |
SLOTTED DRAIN CONN@45+ |
0.000 |
2,173.180 |
2,173.180 |
1,980.000 |
2,173.180 |
193.180 |
1.00 |
193.18 |
| FRC04502 |
PIPE RUN 4 & SS STR 4B |
0.000 |
4,648.140 |
4,648.140 |
3,080.000 |
4,648.140 |
1,568.140 |
1.00 |
1,568.14 |
| FRC04703 |
5' CB TY1-FCL |
0.000 |
11,873.030 |
11,873.030 |
10,000.000 |
11,873.030 |
1,873.030 |
1.00 |
1,873.03 |
| FRC04704 |
BRICK & MORTAR @ STRUC |
0.000 |
3,918.180 |
3,918.180 |
2,500.000 |
3,918.180 |
1,418.180 |
1.00 |
1,418.18 |
| FRC05000 |
UNDERDRAIN INSTALL IN |
0.000 |
4,559.080 |
4,559.080 |
4,400.000 |
4,559.080 |
159.080 |
1.00 |
159.08 |
| FRC05400 |
EXPLORATORY EXC FOR UT |
0.000 |
3,066.800 |
3,066.800 |
1,750.000 |
3,066.800 |
1,316.800 |
1.00 |
1,316.80 |
| FRC08200 |
REMV CONC FDNS/POSTS I |
0.000 |
12,200.000 |
12,200.000 |
7,610.530 |
7,742.600 |
132.070 |
1.00 |
132.07 |
continued
|
PAY ITEM |
QUANTITY |
PAYMENT |
|
Number |
Description |
Awarded |
Net of Adds/
Deducts |
Total Adjusted |
Completed Prior Est. |
Completed to Date |
This Estimate |
$ Unit Price |
$ This Estimate |
| FRC08300 |
MAINT OF PERM TRAF SIG |
0.000 |
9,900.000 |
9,900.000 |
0.000 |
903.950 |
903.950 |
1.00 |
903.95 |
| XXX03200 |
ANTISTRIP ADDITIVE |
0.000 |
7,413.000 |
7,413.000 |
1,858.300 |
7,413.000 |
5,554.700 |
1.00 |
5,554.70 |
|
Total: |
$225,425.23 |
|
|