 07/21/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 11/30/2012
DOT Vendor: C37020  Contract: 62195 

IL Project:      From Date: 10/31/2012
Route: FAP 307
Section: 129-R-2 To Date: 11/30/2012
Project: NHF-CMF-0307/035/ State Job: C-91-184-01
Letting Date: 01/20/2012 Dist/Cnty: 01 - 089 (KANE )
Airport: 129-R-2 State Job: C-91-184-01
Scope: FAP-307, IL RT 64 FROM 7TH AVE TO DUNHAM RD WITHIN CITY OF
ST. CHARLES.

Payee:

MARTAM CONSTRUCTION INC 1200 GASKET DRIVE  ELGIN , IL  60120

 

 

 

 

Percent Completed:  42.18%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
9,617,630.44      492,506.38      470,430.90      9,639,705.92      4,065,957.07     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 4,065,957.07     
Total paid this estimate:   4,065,957.07     
     Previous payments to contractor: -3,738,700.25     
     Payment to contractor this estimate: 327,256.82     
 
          Voucher #   CC10850 Date: 12/10/2012 1 of 1 327,256.82     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  07 Total: 327,256.82     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X0327004  TEMP WP 60 CL 4   2.000  0.000  2.000  0.000  2.000  2.000  981.00  1,962.00 
X4024100  TEMP ACCESS WINTERIZE   500.000  0.000  500.000  0.000  500.000  500.000  23.50  11,750.00 
X6026622  VV REMOVED   11.000  0.000  11.000  3.000  5.000  2.000  400.00  800.00 
X6060052  COMB CC&G TB6.24 SPL   5,280.000  0.000  5,280.000  146.000  1,792.000  1,646.000  35.00  57,610.00 
X7010216  TRAF CONT & PROT SPL   1.000  0.000  1.000  0.430  0.480  0.050  348,000.00  17,400.00 
X8250505  LIGHT CONTROLLER SPL   2.000  0.000  2.000  0.000  1.500  1.500  8,081.00  12,121.50 
Z0001050  AGG SUBGRADE 12   29,000.000  0.000  29,000.000  9,550.000  9,861.000  311.000  9.00  2,799.00 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.460  0.520  0.060  30,000.00  1,800.00 
Z0033028  MAINTAIN LIGHTING SYS   18.000  0.000  18.000  6.500  7.500  1.000  1,100.00  1,100.00 
Z0062456  TEMP PAVEMENT   899.000  0.000  899.000  562.000  829.000  267.000  36.00  9,612.00 
20200100  EARTH EXCAVATION   11,008.000  0.000  11,008.000  4,147.000  4,292.000  145.000  0.10  14.50 
20201200  REM & DISP UNS MATL   6,234.000  0.000  6,234.000  1,395.600  1,404.600  9.000  14.00  126.00 
21101615  TOPSOIL F & P 4   12,986.000  0.000  12,986.000  0.000  1,722.800  1,722.800  2.60  4,479.28 
25000400  NITROGEN FERT NUTR   161.000  0.000  161.000  0.000  20.000  20.000  2.00  40.00 
25000600  POTASSIUM FERT NUTR   161.000  0.000  161.000  0.000  20.000  20.000  2.00  40.00 
25100105  MULCH METHOD 1   4.000  0.000  4.000  0.000  1.300  1.300  1,300.00  1,690.00 
28000250  TEMP EROS CONTR SEED   200.000  0.000  200.000  0.000  26.000  26.000  5.00  130.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
28000400  PERIMETER EROS BAR   3,260.000  0.000  3,260.000  1,882.000  2,742.000  860.000  3.00  2,580.00 
35501308  HMA BASE CSE 6   133.000  0.000  133.000  0.000  40.000  40.000  36.00  1,440.00 
35501316  HMA BASE CSE 8   1,760.000  0.000  1,760.000  0.000  269.000  269.000  37.00  9,953.00 
40603335  HMA SC "D" N50   213.000  0.000  213.000  0.000  61.900  61.900  105.00  6,499.50 
40800050  INCIDENTAL HMA SURF   50.000  0.000  50.000  0.000  16.300  16.300  200.00  3,260.00 
42300400  PCC DRIVEWAY PAVT 8   3,713.000  0.000  3,713.000  300.000  1,068.000  768.000  39.00  29,952.00 
42400200  PC CONC SIDEWALK 5   50,201.000  0.000  50,201.000  4,396.000  7,562.000  3,166.000  3.50  11,081.00 
42400800  DETECTABLE WARNINGS   400.000  0.000  400.000  74.000  104.000  30.000  16.00  480.00 
44000100  PAVEMENT REM   13,424.000  0.000  13,424.000  6,223.000  6,553.000  330.000  9.00  2,970.00 
44000200  DRIVE PAVEMENT REM   6,076.000  0.000  6,076.000  1,415.000  1,499.000  84.000  8.00  672.00 
44000500  COMB CURB GUTTER REM   12,975.000  0.000  12,975.000  4,489.000  4,517.000  28.000  4.00  112.00 
44200162  PAVT PATCH T4 13   97.000  0.000  97.000  58.000  80.000  22.000  100.00  2,200.00 
44201353  CL C PATCH T2 10   500.000  0.000  500.000  0.000  21.000  21.000  30.00  630.00 
44201359  CL C PATCH T4 10   1,000.000  0.000  1,000.000  128.000  206.000  78.000  30.00  2,340.00 
44201794  CL D PATCH T3 12   400.000  0.000  400.000  71.000  139.000  68.000  82.00  5,576.00 
44201796  CL D PATCH T4 12   600.000  0.000  600.000  0.000  187.000  187.000  82.00  15,334.00 
50800105  REINFORCEMENT BARS   3,230.000  0.000  3,230.000  0.000  1,590.000  1,590.000  1.00  1,590.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
50800205  REINF BARS, EPOXY CTD   20,140.000  0.000  20,140.000  0.000  1,341.000  1,341.000  1.50  2,011.50 
550A0430  STORM SEW CL A 2 30   733.000  0.000  733.000  80.000  72.000  -8.000  68.00  -544.00 
56100800  WATER MAIN 10   1,695.000  0.000  1,695.000  1,578.000  1,579.000  1.000  75.00  75.00 
56400500  FIRE HYDNTS TO BE REM   8.000  0.000  8.000  7.000  8.000  1.000  600.00  600.00 
60107600  PIPE UNDERDRAINS 4   1,200.000  0.000  1,200.000  0.000  492.000  492.000  14.00  6,888.00 
60600605  CONC CURB TB   995.000  0.000  995.000  133.000  383.000  250.000  15.00  3,750.00 
60603800  COMB CC&G TB6.12   2,852.000  0.000  2,852.000  1,104.000  1,419.000  315.000  15.00  4,725.00 
60605000  COMB CC&G TB6.24   9,050.000  0.000  9,050.000  2,755.000  3,608.000  853.000  16.00  13,648.00 
66900450  SPL WASTE PLNS/REPORT   1.000  0.000  1.000  0.000  0.330  0.330  15,000.00  4,950.00 
70103815  TR CONT SURVEILLANCE   300.000  0.000  300.000  116.600  132.600  16.000  1.00  16.00 
70301000  WORK ZONE PAVT MK REM   61,100.000  0.000  61,100.000  145.000  1,199.000  1,054.000  0.01  10.54 
81028200  UNDRGRD C GALVS 2   8,212.000  0.000  8,212.000  2,571.000  3,051.000  480.000  15.00  7,200.00 
81028220  UNDRGRD C GALVS 3   4,213.000  0.000  4,213.000  2,950.000  3,040.000  90.000  26.00  2,340.00 
81028240  UNDRGRD C GALVS 4   1,096.000  0.000  1,096.000  100.000  604.000  504.000  33.00  16,632.00 
81028250  UNDRGRD C GALVS 5   170.000  0.000  170.000  105.000  170.000  65.000  43.00  2,795.00 
81028370  UNDRGRD C PVC 3   515.000  0.000  515.000  315.000  515.000  200.000  7.70  1,540.00 
81603110  UD 4#4#6GXLPUSE 1 1/2   15,300.000  0.000  15,300.000  0.000  3,154.000  3,154.000  9.00  28,386.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
83600200  LIGHT POLE FDN 24D   567.000  0.000  567.000  44.000  137.000  93.000  130.00  12,090.00 
Total:   

$327,256.82

 

IDOT Privacy Statement | Illinois Privacy Information | Kids Privacy | Web Accessibility  | FOIA