State of Illinois Department of Transportation

Contract Search

 04/23/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below


Archive    60W25 / 08


Archive    60W25 / 07
Archive    60W25 / 06
Archive    60W25 / 05
Archive    60W25 / 04
Archive    60W25 / 03
Archive    60W25 / 02
Archive    60W25 / 01
Archive    60W25 / 00

Contractor Invoice

Current Report 04/08/2014
DOT Vendor: C46570  Contract: 60W25 

IL Project:      From Date: 03/21/2014
Route: FAI 90/94 (I-90/94)
Section: 2013-007R To Date: 04/08/2014
Project: NHPP-000S/941/ State Job: C-91-227-13
Letting Date: 08/02/2013 Dist/Cnty: 01 - 031 (COOK )
Airport: 2013-007R State Job: C-91-227-13
Scope: FAI-90/94, CITY OF CHICAGO, CIRCLE INTERCHNG: I-290 @ MORGAN
ST CROSSOVER BRIDGE.

Payee:

FH PASCHEN/SN NIELSEN LLC 5515 N EAST RIVER ROAD  CHICAGO , IL  60656

 

 

 

 

Percent Completed:  62.53%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
18,459,602.10      2,787,141.97      2,781,663.24      18,465,080.83      11,619,421.35     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 11,619,421.35     
Total paid this estimate:   11,619,421.35     
     Previous payments to contractor: -9,805,273.03     
     Payment to contractor this estimate: 1,814,148.32     
 
          Voucher #   CC17461 Date: 04/11/2014 1 of 1 1,814,148.32     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  09 Total: 1,814,148.32     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X0322400  PILE EXTRACTION   27.000  2.000  29.000  10.000  15.000  5.000  2,000.00  10,000.00 
X0324571  MAINT ST LTG SYS CHGO   1.000  0.000  1.000  0.746  0.799  0.053  12,336.06  653.81 
X0327357  CONSTRN VBRN MONITRNG   1.000  0.000  1.000  0.746  0.789  0.043  75,000.00  3,225.00 
X0327616  MAINT ITS DURG CONSTR   6.000  0.000  6.000  5.630  6.000  0.370  14,600.00  5,402.00 
X5017307  PROTECTIVE SHIELD SPL   270.000  0.000  270.000  0.000  83.000  83.000  135.00  11,205.00 
X6700410  ENGR FLD OFF A SPL   12.000  0.000  12.000  5.500  6.000  0.500  3,500.00  1,750.00 
X7010216  TRAF CONT & PROT SPL   1.000  0.000  1.000  0.748  0.779  0.031  375,000.00  11,625.00 
X7011015  TR C-PROT EXPRESSWAYS   1.000  0.000  1.000  0.748  0.779  0.031  150,000.00  4,650.00 
X7013820  TR CONT SURVEIL EXPWY   50.000  104.000  154.000  50.000  108.710  58.710  250.00  14,677.50 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.590  0.900  0.310  250,000.00  77,500.00 
Z0022800  FENCE REMOVAL   282.000  0.000  282.000  69.300  120.400  51.100  6.00  306.60 
Z0033028  MAINTAIN LIGHTING SYS   6.000  0.000  6.000  5.900  6.000  0.100  1,328.63  132.86 
28000510  INLET FILTERS   78.000  0.000  78.000  36.000  37.000  1.000  125.00  125.00 
50200100  STRUCTURE EXCAVATION   148.000  0.000  148.000  0.000  9.050  9.050  250.00  2,262.50 
50300225  CONC STRUCT   1,034.100  15.400  1,049.500  177.370  530.880  353.510  650.00  229,781.50 
50300285  FORM LINER TEX SURF   1,732.000  0.000  1,732.000  0.000  827.570  827.570  25.00  20,689.25 
50500405  F & E STRUCT STEEL   42,810.000  0.000  42,810.000  15,198.000  15,558.000  360.000  3.05  1,098.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
50800105  REINFORCEMENT BARS   398,156.000  -305,326.000  92,830.000  24,393.750  47,170.470  22,776.720  0.93  21,182.35 
50800205  REINF BARS, EPOXY CTD   401,200.000  -36,920.000  364,280.000  17,457.070  76,135.770  58,678.700  0.91  53,397.62 
50800515  BAR SPLICERS   1,031.000  -760.000  271.000  26.000  98.000  72.000  19.98  1,438.56 
51602000  PERMANENT CASING   1,274.000  0.000  1,274.000  304.830  617.290  312.460  250.00  78,115.00 
51603000  DRILLED SHAFT IN SOIL   1,729.000  -1,274.000  455.000  108.560  219.840  111.280  1,600.00  178,048.00 
51604000  DRILLED SHAFT IN ROCK   42.000  -28.000  14.000  3.150  6.310  3.160  6,500.00  20,540.00 
70103815  TR CONT SURVEILLANCE   50.000  110.000  160.000  50.000  107.080  57.080  250.00  14,270.00 
70400100  TEMP CONC BARRIER   1,325.000  0.000  1,325.000  973.200  998.500  25.300  40.00  1,012.00 
70400200  REL TEMP CONC BARRIER   1,725.000  0.000  1,725.000  1,031.200  1,695.400  664.200  20.00  13,284.00 
85000200  MAIN EX TR SIG INSTAL   1.000  0.000  1.000  0.616  0.659  0.043  435.41  18.73 
MATALL00  MATERIAL ALLOWANCE   0.000  0.000  0.000  0.000  0.000  0.000  0.00  -19,777.50 
XXX25000  VALUE ENG INCENTIVE   0.000  522,813.540  522,813.540  261,406.770  522,813.540  261,406.770  1.00  261,406.77 
X9100800  MICROPILE SPECIAL   0.000  72.000  72.000  35.000  72.000  37.000  20,955.91  775,368.67 
X9100801  MICROPILE PRF LOAD TES   0.000  4.000  4.000  0.000  2.000  2.000  10,380.05  20,760.10 
Total:   

$1,814,148.32

 