State of Illinois Department of Transportation

Contract Search

 05/22/2013 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 11/27/2012
DOT Vendor: C19500  Contract: 60T64 

IL Project:      From Date: 09/13/2012
Route: VARIOUS
Section: 2012-018 RS To Date: 11/27/2012
Project: State Job: C-91-402-12
Letting Date: 06/15/2012 Dist/Cnty: 01 - 031 (COOK )
Airport: 2012-018 RS State Job: C-91-402-12
Scope: VARIOUS ROUTES.

Payee:

GALLAGHER ASPHALT CORPORATION 18100 S INDIANA AVENUE  THORNTON , IL  60476

 

 

 

 

Percent Completed:  93.37%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
1,068,777.00      0.00      0.00      1,068,777.00      997,871.55     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 997,871.55     
Mobilzation Paid:6,353.19     
Total paid this estimate:   997,871.55     
     Previous payments to contractor: -636,963.40     
     Payment to contractor this estimate: 360,908.15     
 
          Voucher #   CC10085 Date: 11/28/2012 1 of 1 360,908.15     

----------------------------------------------------------------------------------------------------------------------------------------------     

Includes final mobilization Pay Estimate Number:  02 Total: 360,908.15     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
40600200  BIT MATLS PR CT   15.000  0.000  15.000  0.000  9.160  9.160  0.01  0.09 
40603340  HMA SC "D" N70   3,960.000  0.000  3,960.000  2,589.620  3,960.000  1,370.380  152.50  208,982.95 
44000157  HMA SURF REM 2   35,344.000  0.000  35,344.000  23,012.790  35,344.000  12,331.210  7.95  98,033.12 
67100100  MOBILIZATION   1.000  0.000  1.000  0.900  1.000  0.100  63,531.86  6,353.19 
70300100  SHORT TERM PAVT MKING   4,069.000  0.000  4,069.000  688.000  1,766.000  1,078.000  1.25  1,347.50 
70301000  WORK ZONE PAVT MK REM   1,711.000  0.000  1,711.000  0.000  624.940  624.940  0.01  6.25 
78000100  THPL PVT MK LTR & SYM   550.000  0.000  550.000  0.000  186.000  186.000  3.75  697.50 
78000200  THPL PVT MK LINE 4   43,447.000  0.000  43,447.000  0.000  28,345.000  28,345.000  0.85  24,093.25 
78000400  THPL PVT MK LINE 6   1,310.000  0.000  1,310.000  0.000  1,310.000  1,310.000  1.50  1,965.00 
78000500  THPL PVT MK LINE 8   250.000  0.000  250.000  0.000  117.000  117.000  2.00  234.00 
78000600  THPL PVT MK LINE 12   250.000  0.000  250.000  0.000  201.000  201.000  2.40  482.40 
78000650  THPL PVT MK LINE 24   532.000  0.000  532.000  0.000  207.000  207.000  3.50  724.50 
78100100  RAISED REFL PAVT MKR   790.000  0.000  790.000  0.000  329.000  329.000  23.00  7,567.00 
78300200  RAISED REF PVT MK REM   790.000  0.000  790.000  110.000  269.000  159.000  9.60  1,526.40 
88600600  DET LOOP REPL   1,700.000  0.000  1,700.000  0.000  593.000  593.000  15.00  8,895.00 
Total:   

$360,908.15

 