Contract Search

 04/21/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 08/08/2013
DOT Vendor: C48130  Contract: 60H45 

IL Project:      From Date: 07/12/2013
Route: FAP 345
Section: 8R-R To Date: 08/08/2013
Project: NHF-0345/056/ State Job: C-91-632-09
Letting Date: 04/27/2012 Dist/Cnty: 01 - 089 (KANE )
Airport: 8R-R State Job: C-91-632-09
Scope: FAP-345, US20/MCLEAN BLVD INTERCHANGE; MCLEAN BLVD FROM
FLEETWOOD DR TO LILLIAN ST IN ELGIN.

Payee:

PLOTE CONSTRUCTION INC 1100 BRANDT DRIVE  HOFFMAN ESTATES , IL  60192

 

 

 

 

Percent Completed:  14.07%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
34,731,343.80      303,726.20      6,000.00      35,029,070.00      7,819,027.47     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 7,819,027.47     
Total paid this estimate:   7,819,027.47     
     Previous payments to contractor: -6,790,394.16     
     Payment to contractor this estimate: 1,028,633.31     
 
          Voucher #   CC02336 Date: 08/12/2013 1 of 1 1,028,633.31     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  09 Total: 1,028,633.31     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X0322118  REM CON FLAR END SEC   23.000  0.000  23.000  5.000  8.000  3.000  100.00  300.00 
X4402800  ISLAND PAVEMENT REM   149.000  0.000  149.000  0.000  70.500  70.500  9.00  634.50 
X6700410  ENGR FLD OFF A SPL   24.000  0.000  24.000  2.500  3.500  1.000  3,500.00  3,500.00 
X7010216  TRAF CONT & PROT SPL   1.000  0.000  1.000  0.530  0.560  0.030  332,000.00  9,960.00 
X7030025  WET REF TEM TP T3 L&S   1,602.000  0.000  1,602.000  72.800  145.600  72.800  3.75  273.00 
X7030030  WET REF TEM TAPE T3 4   226,349.000  0.000  226,349.000  47,200.000  48,694.200  1,494.200  1.03  1,539.03 
X7030055  WET REF TEM TPE T3 24   602.000  0.000  602.000  89.000  149.200  60.200  6.50  391.30 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.440  0.480  0.040  97,500.00  3,900.00 
Z0042002  POROUS GRAN EMB SUBGR   3,578.000  0.000  3,578.000  748.500  819.500  71.000  18.00  1,278.00 
Z0062456  TEMP PAVEMENT   36,436.000  0.000  36,436.000  2,536.100  3,732.000  1,195.900  37.00  44,248.30 
20200100  EARTH EXCAVATION   149,753.000  0.000  149,753.000  21,581.200  26,251.200  4,670.000  15.60  72,852.00 
20201200  REM & DISP UNS MATL   29,933.000  0.000  29,933.000  16,662.700  16,733.700  71.000  11.00  781.00 
20800150  TRENCH BACKFILL   7,726.000  0.000  7,726.000  1,158.100  2,509.400  1,351.300  15.00  20,269.50 
21001000  GEOTECH FAB F/GR STAB   105,569.000  0.000  105,569.000  6,231.200  12,361.200  6,130.000  1.25  7,662.50 
30300112  AGG SUBGRADE IMPR 12   139,968.000  0.000  139,968.000  6,231.200  12,361.200  6,130.000  7.90  48,427.00 
42000501  PCC PVT 10 JOINTED   50,903.000  0.000  50,903.000  0.000  1,298.900  1,298.900  41.00  53,254.90 
44000100  PAVEMENT REM   140,195.000  0.000  140,195.000  15,385.600  19,837.300  4,451.700  5.00  22,258.50 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
44000500  COMB CURB GUTTER REM   10,970.000  0.000  10,970.000  217.700  1,084.900  867.200  3.50  3,035.20 
44000600  SIDEWALK REM   19,312.000  0.000  19,312.000  1,062.400  1,382.000  319.600  1.00  319.60 
44003100  MEDIAN REMOVAL   122.000  0.000  122.000  0.000  122.000  122.000  5.50  671.00 
44004250  PAVED SHLD REMOVAL   15,701.000  0.000  15,701.000  7,895.000  8,766.300  871.300  4.50  3,920.85 
48300500  PCC SHOULDERS 10   10,470.000  0.000  10,470.000  0.000  677.000  677.000  33.00  22,341.00 
50200100  STRUCTURE EXCAVATION   1,258.000  0.000  1,258.000  278.000  394.200  116.200  25.00  2,905.00 
51201800  FUR STL PILE HP14X73   6,290.000  2,448.000  8,738.000  264.000  5,515.000  5,251.000  88.00  462,088.00 
51202305  DRIVING PILES   6,290.000  2,448.000  8,738.000  0.000  615.000  615.000  0.01  6.15 
54213663  PRC FLAR END SEC 18   4.000  0.000  4.000  1.000  2.000  1.000  525.00  525.00 
54213669  PRC FLAR END SEC 24   15.000  0.000  15.000  0.000  2.000  2.000  600.00  1,200.00 
550A0340  STORM SEW CL A 2 12   7,782.000  0.000  7,782.000  432.100  924.500  492.400  53.00  26,097.20 
550A0360  STORM SEW CL A 2 15   486.000  0.000  486.000  0.000  486.000  486.000  57.00  27,702.00 
550A0380  STORM SEW CL A 2 18   2,831.000  0.000  2,831.000  516.400  1,094.700  578.300  59.00  34,119.70 
550A0410  STORM SEW CL A 2 24   1,539.000  0.000  1,539.000  65.100  143.200  78.100  67.00  5,232.70 
550A0430  STORM SEW CL A 2 30   315.000  0.000  315.000  0.000  43.000  43.000  77.00  3,311.00 
550A0640  STORM SEW CL A 3 12   2,094.000  0.000  2,094.000  555.000  775.500  220.500  57.00  12,568.50 
55101200  STORM SEWER REM 24   848.000  0.000  848.000  49.000  101.000  52.000  8.00  416.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
55200600  STORM SEWERS JKD 18   106.000  0.000  106.000  0.000  70.500  70.500  100.00  7,050.00 
60200805  CB TA 4 DIA T8G   26.000  0.000  26.000  6.000  11.000  5.000  1,700.00  8,500.00 
60201340  CB TA 4 DIA T24F&G   119.000  0.000  119.000  3.000  5.000  2.000  1,800.00  3,600.00 
60204505  CB TA 5 DIA T8G   9.000  0.000  9.000  0.000  1.000  1.000  2,500.00  2,500.00 
60218400  MAN TA 4 DIA T1F CL   33.000  0.000  33.000  4.000  10.000  6.000  1,600.00  9,600.00 
60221100  MAN TA 5 DIA T1F CL   31.000  0.000  31.000  2.000  4.000  2.000  2,000.00  4,000.00 
60240328  INLETS TB T24F&G   32.000  0.000  32.000  3.000  14.000  11.000  1,500.00  16,500.00 
66900200  NON SPL WASTE DISPOSL   906.000  0.000  906.000  282.600  437.500  154.900  59.20  9,170.08 
70103815  TR CONT SURVEILLANCE   538.000  0.000  538.000  38.500  59.900  21.400  1.00  21.40 
70106800  CHANGEABLE MESSAGE SN   40.000  0.000  40.000  2.540  2.700  0.160  800.00  128.00 
73600200  REMOV OH SIN STR-CANT   2.000  0.000  2.000  0.000  1.000  1.000  3,000.00  3,000.00 
73700300  REM CONC FDN-OVHD   2.000  0.000  2.000  0.000  1.000  1.000  1,500.00  1,500.00 
78300100  PAVT MARKING REMOVAL   39,339.000  0.000  39,339.000  11,037.600  11,201.900  164.300  0.95  156.09 
78300200  RAISED REF PVT MK REM   845.000  0.000  845.000  196.000  214.000  18.000  9.00  162.00 
FRC00900  ADDITIONAL TRAFFIC CON   0.000  5,000.000  5,000.000  431.770  1,762.850  1,331.080  1.00  1,331.08 
FRC01000  RE-ALIGN TEMP CONCRETE   0.000  3,000.000  3,000.000  0.000  2,768.990  2,768.990  1.00  2,768.99 
FRC01100  UNKNOWN OBSTRUCTION   0.000  5,000.000  5,000.000  0.000  981.890  981.890  1.00  981.89 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
FRC01300  DEBRIS CLEAN UP   0.000  4,780.910  4,780.910  0.000  4,780.910  4,780.910  1.00  4,780.91 
FRC01400  ASPHALT WEDGE REMOVAL   0.000  554.440  554.440  0.000  554.440  554.440  1.00  554.44 
MATALL00  MATERIAL ALLOWANCE   0.000  0.000  0.000  0.000  0.000  0.000  0.00  54,340.00 
Total:   

$1,028,633.31

 