State of Illinois Department of Transportation

Contract Search

 07/29/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below


Archive    60H45 / 19


Archive    60H45 / 18
Archive    60H45 / 17
Archive    60H45 / 16
Archive    60H45 / 15
Archive    60H45 / 14
Archive    60H45 / 13
Archive    60H45 / 12
Archive    60H45 / 11
Archive    60H45 / 10
Archive    60H45 / 09
Archive    60H45 / 08
Archive    60H45 / 07
Archive    60H45 / 06
Archive    60H45 / 05
Archive    60H45 / 04
Archive    60H45 / 03
Archive    60H45 / 02
Archive    60H45 / 01
Archive    60H45 / 00

Contractor Invoice

Current Report 07/25/2014
DOT Vendor: C48130  Contract: 60H45 

IL Project:      From Date: 07/10/2014
Route: FAP 345
Section: 8R-R To Date: 07/25/2014
Project: NHF-0345/056/ State Job: C-91-632-09
Letting Date: 04/27/2012 Dist/Cnty: 01 - 089 (KANE )
Airport: 8R-R State Job: C-91-632-09
Scope: FAP-345, US20/MCLEAN BLVD INTERCHANGE; MCLEAN BLVD FROM
FLEETWOOD DR TO LILLIAN ST IN ELGIN.

Payee:

PLOTE CONSTRUCTION INC 1100 BRANDT DRIVE  HOFFMAN ESTATES , IL  60192

 

 

 

 

Percent Completed:  43.83%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
34,731,343.80      1,472,626.57      29,600.00      36,174,370.37      17,043,937.06     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 17,043,937.06     
Total paid this estimate:   17,043,937.06     
     Previous payments to contractor: -16,797,582.75     
     Payment to contractor this estimate: 246,354.31     
 
          Voucher #   CC01345 Date: 07/28/2014 1 of 1 246,354.31     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  20 Total: 246,354.31     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X7010216  TRAF CONT & PROT SPL   1.000  0.000  1.000  0.850  0.860  0.010  332,000.00  3,320.00 
Z0007605  BLDG REMOV NO 5   1.000  0.000  1.000  0.900  1.000  0.100  12,800.00  1,280.00 
Z0007606  BLDG REMOV NO 6   1.000  0.000  1.000  0.900  1.000  0.100  4,650.00  465.00 
Z0013798  CONSTRUCTION LAYOUT   1.000  0.000  1.000  0.920  0.940  0.020  97,500.00  1,950.00 
Z0030250  IMP ATTN TEMP NRD TL3   6.000  0.000  6.000  0.000  2.000  2.000  3,500.00  7,000.00 
Z0062456  TEMP PAVEMENT   36,436.000  0.000  36,436.000  20,343.800  22,311.400  1,967.600  37.00  72,801.20 
20200100  EARTH EXCAVATION   149,753.000  0.000  149,753.000  42,022.200  43,993.000  1,970.800  15.60  30,744.48 
20800150  TRENCH BACKFILL   7,726.000  0.000  7,726.000  4,551.000  4,577.600  26.600  15.00  399.00 
25100630  EROSION CONTR BLANKET   177,386.000  0.000  177,386.000  15,863.200  15,600.000  -263.200  0.79  -207.93 
28000250  TEMP EROS CONTR SEED   2,010.000  0.000  2,010.000  1,757.900  1,997.900  240.000  5.75  1,380.00 
28000400  PERIMETER EROS BAR   22,032.000  0.000  22,032.000  7,654.500  7,600.000  -54.500  1.75  -95.38 
28000510  INLET FILTERS   238.000  0.000  238.000  32.000  39.000  7.000  135.00  945.00 
42100315  CONT R PCC PVT 10 3/4   40,206.000  0.000  40,206.000  22,408.200  22,449.400  41.200  36.00  1,483.20 
44000100  PAVEMENT REM   140,195.000  0.000  140,195.000  26,971.800  27,171.300  199.500  5.00  997.50 
44000500  COMB CURB GUTTER REM   10,970.000  0.000  10,970.000  4,975.100  5,111.100  136.000  3.50  476.00 
44000600  SIDEWALK REM   19,312.000  0.000  19,312.000  9,606.200  10,150.200  544.000  1.00  544.00 
48101498  AGGREGATE SHLDS B 4   7,443.000  0.000  7,443.000  0.000  2,230.300  2,230.300  6.25  13,939.38 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
48101620  AGGREGATE SHLDS B 10   1,838.000  0.000  1,838.000  0.000  484.900  484.900  17.00  8,243.30 
48300515  PCC SHOULDERS 10 3/4   29,711.000  0.000  29,711.000  8,362.800  8,525.000  162.200  38.00  6,163.60 
550A0050  STORM SEW CL A 1 12   874.000  0.000  874.000  132.600  208.100  75.500  53.00  4,001.50 
550A0340  STORM SEW CL A 2 12   7,782.000  0.000  7,782.000  2,044.500  2,040.200  -4.300  53.00  -227.90 
550A0410  STORM SEW CL A 2 24   1,539.000  0.000  1,539.000  435.700  519.900  84.200  67.00  5,641.40 
550A0640  STORM SEW CL A 3 12   2,094.000  0.000  2,094.000  1,278.500  1,523.500  245.000  57.00  13,965.00 
550B0050  STORM SEW CL B 1 12   932.000  0.000  932.000  504.700  580.800  76.100  52.00  3,957.20 
56400400  FIRE HYDNTS RELOCATED   3.000  0.000  3.000  2.000  3.000  1.000  4,082.10  4,082.10 
60100060  CONC HDWL FOR P DRAIN   27.000  0.000  27.000  0.000  10.000  10.000  351.08  3,510.80 
60200805  CB TA 4 DIA T8G   26.000  0.000  26.000  15.000  16.000  1.000  1,700.00  1,700.00 
60201340  CB TA 4 DIA T24F&G   119.000  0.000  119.000  13.000  14.000  1.000  1,800.00  1,800.00 
60240328  INLETS TB T24F&G   32.000  0.000  32.000  21.000  23.000  2.000  1,500.00  3,000.00 
70301000  WORK ZONE PAVT MK REM   146,640.000  0.000  146,640.000  1,067.400  5,570.000  4,502.600  0.39  1,756.01 
70400100  TEMP CONC BARRIER   18,889.000  0.000  18,889.000  12,982.000  15,620.000  2,638.000  7.00  18,466.00 
70400200  REL TEMP CONC BARRIER   40,459.000  0.000  40,459.000  3,715.000  8,222.000  4,507.000  3.50  15,774.50 
78300100  PAVT MARKING REMOVAL   39,339.000  0.000  39,339.000  11,993.600  12,535.100  541.500  0.95  514.43 
81603081  UD 3#2#4GXLPUSE 1.5 P   18,491.000  0.000  18,491.000  5,211.600  5,685.900  474.300  13.28  6,298.70 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
83600200  LIGHT POLE FDN 24D   830.000  0.000  830.000  237.500  294.500  57.000  180.46  10,286.22 
Total:   

$246,354.31

 