State of Illinois Department of Transportation

Contract Search

 07/22/2014 

Invoice Archive
Contract Number
&
Estimate Numbers are listed below



Go to Current Estimate for this Contract Number

Contractor Invoice

Previous Report 09/19/2013
DOT Vendor: C21960  Contract: 60477 

IL Project:      From Date: 09/04/2013
Route: FAP 870 (IL 53)
Section: 532B To Date: 09/19/2013
Project: F-0870/012/ State Job: C-91-397-97
Letting Date: 06/17/2011 Dist/Cnty: 01 - 043 (DUPAGE )
Airport: 532B State Job: C-91-397-97
Scope: FAP-870, IL 53 FROM ARMY TRAIL RD TO ELGIN O'HARE EXPWY IN
VILLAGES OF ITASCA AND ADDISON.

Payee:

GRECO CONT INC & PIR TANO 2100 S MOUNT PROSPECT RD  DES PLAINES , IL  60018

 

 

 

 

Percent Completed:  63.74%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
45,475,053.19      5,020,001.10      7,767,333.13      42,727,721.16      28,056,382.41     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 28,056,382.41     
Total paid this estimate:   28,056,382.41     
     Previous payments to contractor: -27,106,389.79     
     Payment to contractor this estimate: 949,992.62     
 
          Voucher #   BC01095 Date: 09/23/2013 1 of 1 949,992.62     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  37 Total: 949,992.62     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X0301423  NOISE AB WALL GRD MT   28,453.000  82.000  28,535.000  26,575.260  26,832.260  257.000  29.91  7,686.87 
X6061930  CONC MED TSB6.18 MOD   11,642.000  0.000  11,642.000  0.000  11,246.200  11,246.200  9.96  112,012.15 
X7030030  WET REF TEM TAPE T3 4   448,624.000  -28,540.000  420,084.000  109,068.700  110,436.700  1,368.000  1.00  1,368.00 
X7030040  WET REF TEM TAPE T3 6   65,013.000  -857.000  64,156.000  7,971.500  8,445.500  474.000  1.80  853.20 
Z0001050  AGG SUBGRADE 12   246,425.000  -13,904.000  232,521.000  160,866.300  165,767.900  4,901.600  7.00  34,311.20 
Z0030850  TEMP INFO SIGNING   3,132.000  1,496.200  4,628.200  3,316.700  3,329.200  12.500  13.50  168.75 
Z0042002  POROUS GRAN EMB SUBGR   14,177.000  0.000  14,177.000  8,311.110  8,791.810  480.700  23.35  11,224.34 
Z0056608  STORM SEW WM REQ 12   5,981.000  -3,323.000  2,658.000  1,088.600  1,096.200  7.600  39.00  296.40 
20201200  REM & DISP UNS MATL   52,540.000  0.000  52,540.000  31,055.290  31,523.590  468.300  10.25  4,800.08 
20800150  TRENCH BACKFILL   28,384.000  169.390  28,553.390  17,843.490  18,296.590  453.100  36.00  16,311.60 
21001000  GEOTECH FAB F/GR STAB   3,161.000  73,278.000  76,439.000  65,200.850  69,309.050  4,108.200  0.91  3,738.47 
31200502  STAB SUBBASE HMA 4.5   207,432.000  0.000  207,432.000  140,208.900  150,115.800  9,906.900  14.75  146,126.77 
42000506  PCC PVT 10 1/4 JOINTD   191,097.000  -1,167.000  189,930.000  124,210.700  130,803.100  6,592.400  36.80  242,600.32 
42300400  PCC DRIVEWAY PAVT 8   1,919.000  2,205.700  4,124.700  1,739.810  1,801.610  61.800  44.94  2,777.29 
44000100  PAVEMENT REM   162,984.000  58,690.280  221,674.280  146,687.330  166,570.630  19,883.300  6.37  126,656.62 
44000200  DRIVE PAVEMENT REM   17,541.000  0.000  17,541.000  15,032.800  15,060.200  27.400  5.97  163.57 
50105220  PIPE CULVERT REMOV   257.000  0.000  257.000  241.000  257.000  16.000  24.00  384.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
54213660  PRC FLAR END SEC 15   27.000  -4.000  23.000  20.000  22.000  2.000  473.97  947.94 
550A0050  STORM SEW CL A 1 12   4,193.000  -213.000  3,980.000  3,214.300  3,374.800  160.500  34.00  5,457.00 
550A0070  STORM SEW CL A 1 15   1,609.000  -239.000  1,370.000  1,235.900  1,295.900  60.000  30.00  1,800.00 
550A0090  STORM SEW CL A 1 18   376.000  0.000  376.000  120.000  376.000  256.000  35.00  8,960.00 
550A0340  STORM SEW CL A 2 12   6,023.000  -1,219.000  4,804.000  4,227.450  4,393.150  165.700  34.00  5,633.80 
550A0360  STORM SEW CL A 2 15   2,930.000  -304.000  2,626.000  2,003.200  2,217.600  214.400  32.00  6,860.80 
55100500  STORM SEWER REM 12   9,055.000  208.000  9,263.000  3,839.100  4,508.900  669.800  10.00  6,698.00 
60201330  CB TA 4 DIA T23F&G   44.000  0.000  44.000  30.700  31.300  0.600  1,900.87  1,140.52 
60201340  CB TA 4 DIA T24F&G   255.000  -24.000  231.000  177.300  188.700  11.400  1,911.87  21,795.32 
60204505  CB TA 5 DIA T8G   9.000  1.000  10.000  6.300  7.200  0.900  2,496.83  2,247.15 
60207605  CB TC T8G   16.000  10.000  26.000  23.400  24.300  0.900  826.94  744.24 
60208240  CB TC T24F&G   4.000  7.000  11.000  10.900  11.000  0.100  952.94  95.29 
60218400  MAN TA 4 DIA T1F CL   49.000  5.000  54.000  43.500  48.900  5.400  1,948.87  10,523.89 
60221100  MAN TA 5 DIA T1F CL   72.000  3.000  75.000  60.100  60.400  0.300  2,676.82  803.05 
60223800  MAN TA 6 DIA T1F CL   18.000  1.000  19.000  15.500  16.400  0.900  4,212.72  3,791.45 
60237470  INLETS TA T24F&G   1.000  5.000  6.000  1.800  2.000  0.200  778.95  155.79 
60260050  SAN MAN RECONST   8.000  0.000  8.000  5.900  6.900  1.000  1,547.90  1,547.90 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
60500040  REMOV MANHOLES   108.000  2.000  110.000  59.000  65.000  6.000  151.99  911.94 
60500060  REMOV INLETS   102.000  0.000  102.000  56.000  58.000  2.000  62.00  124.00 
60600605  CONC CURB TB   1,685.000  0.000  1,685.000  462.000  525.600  63.600  17.50  1,113.00 
60603800  COMB CC&G TB6.12   324.000  1,105.800  1,429.800  858.600  890.500  31.900  14.90  475.31 
60604400  COMB CC&G TB6.18   11,252.500  -660.000  10,592.500  1,476.500  3,201.500  1,725.000  16.30  28,117.50 
60605000  COMB CC&G TB6.24   52,105.500  -1,563.000  50,542.500  32,138.850  36,339.950  4,201.100  15.40  64,696.94 
60608600  COMB CC&G TM6.06   106.000  0.000  106.000  0.000  64.500  64.500  14.50  935.25 
60610400  COMB CC&G TM6.24   246.000  0.000  246.000  0.000  193.000  193.000  16.90  3,261.70 
66900200  NON SPL WASTE DISPOSL   7,468.000  0.000  7,468.000  5,591.660  5,860.860  269.200  62.00  16,690.40 
70106800  CHANGEABLE MESSAGE SN   68.000  0.000  68.000  25.803  29.473  3.670  749.95  2,752.32 
81000600  CON T 2 GALVS   22,161.000  3,812.000  25,973.000  10,523.000  11,071.000  548.000  7.25  3,973.00 
81000700  CON T 2 1/2 GALVS   561.000  -30.000  531.000  39.000  87.000  48.000  12.00  576.00 
81000800  CON T 3 GALVS   982.000  2,242.000  3,224.000  2,395.600  2,482.600  87.000  14.00  1,218.00 
81001000  CON T 4 GALVS   851.000  4,763.000  5,614.000  2,729.400  3,097.900  368.500  18.00  6,633.00 
81400100  HANDHOLE   92.000  1.000  93.000  32.000  37.000  5.000  899.94  4,499.70 
81400200  HD HANDHOLE   31.000  3.000  34.000  10.000  11.000  1.000  1,199.92  1,199.92 
81400300  DBL HANDHOLE   29.000  -3.000  26.000  5.000  8.000  3.000  1,899.87  5,699.61 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
81900200  TR & BKFIL F ELECT WK   39,735.000  9,877.000  49,612.000  12,793.700  13,590.700  797.000  2.00  1,594.00 
83600200  LIGHT POLE FDN 24D   930.000  11.000  941.000  290.000  350.000  60.000  124.99  7,499.40 
87800100  CONC FDN TY A   176.000  -12.000  164.000  27.000  43.000  16.000  124.99  1,999.84 
87800150  CONC FDN TY C   56.000  -8.000  48.000  12.000  20.000  8.000  294.98  2,359.84 
87800415  CONC FDN TY E 36D   468.000  -28.000  440.000  126.000  139.000  13.000  169.99  2,209.87 
88600700  PREFORM DETECT LOOP   12,355.000  -322.000  12,033.000  8,594.500  9,301.500  707.000  19.00  13,433.00 
FRC00800  MAIN LIGHT SYSTEMS   0.000  108,000.000  108,000.000  40,433.510  41,334.630  901.120  1.00  901.12 
FRC05600  TEMP POLE SUPPORT SPL   0.000  27,884.100  27,884.100  16,331.580  17,365.320  1,033.740  1.00  1,033.74 
FRC12100  EXT MAINT OF EXIST TRA   0.000  31,500.000  31,500.000  5,133.780  5,330.780  197.000  1.00  197.00 
MATALL00  MATERIAL ALLOWANCE   0.000  0.000  0.000  0.000  0.000  0.000  0.00  -22,838.55 
X9102900  SS WMR CP 361 JT 12"   0.000  3,372.000  3,372.000  3,178.000  3,251.000  73.000  37.00  2,701.00 
X9102905  XX WMR CP 361 JT 36"   0.000  276.000  276.000  168.000  207.000  39.000  137.00  5,343.00 
Total:   

$949,992.62

 