DOT Vendor: C13130  Contract: 60363 

IL Project:      From Date: 10/26/2009
Route: FAI 55
Section: (26,26HB-1&114)R-2 To Date: 11/09/2009
Project: IM-055-6/232/255 State Job: C-91-263-97
Letting Date: 08/01/2008 Dist/Cnty: 01 - 197 (WILL )
Airport: (26,26HB-1&114)R-2 State Job: C-91-263-97
Scope: FAI-55, IL 59, ON SEIL RD, AND ON EAST FRONTAGE RD. IN
SHOREWOOD & JOLIET.

Payee:

D CONST & TJ LAMBRECHT CONST 1488 S BROADWAY  COAL CITY , IL  60416

 

 

 

 

Percent Completed:  44.64%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
25,978,708.15      879,115.76      924,301.19      25,933,522.72      12,251,390.25     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 12,251,390.25     
Total paid this estimate:   12,251,390.25     
     Previous payments to contractor: -11,752,576.93     
     Payment to contractor this estimate: 498,813.32     
 
          Voucher #   CC10518 Date: 11/12/2009 1 of 1 498,813.32     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  14 Total: 498,813.32     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X0323574  MAINTAIN LIGHTING SYS   35.000  0.000  35.000  6.800  7.800  1.000  1,122.70  1,122.70 
X4021000  TEMP ACCESS- PRIV ENT   26.000  -2.000  24.000  7.800  11.000  3.200  2,200.00  7,040.00 
X4022000  TEMP ACCESS- COM ENT   13.000  0.000  13.000  4.200  6.600  2.400  2,100.00  5,040.00 
X4023000  TEMP ACCESS- ROAD   12.000  0.000  12.000  1.800  6.600  4.800  2,550.00  12,240.00 
X6700410  ENGR FLD OFF A SPL   34.000  0.000  34.000  10.500  11.500  1.000  3,000.00  3,000.00 
X6700600  ENGR FIELD LAB SPL   24.000  0.000  24.000  10.500  11.500  1.000  2,200.00  2,200.00 
X7011015  TR C-PROT EXPRESSWAYS   1.000  0.000  1.000  0.300  0.400  0.100  200,000.00  20,000.00 
Z0001050  AGG SUBGRADE 12   86,009.000  -1,000.000  85,009.000  30,231.000  48,654.100  18,423.100  14.40  265,292.64 
Z0018700  DRAINAGE STR REMOVED   32.000  2.000  34.000  14.000  15.000  1.000  200.00  200.00 
Z0076600  TRAINEES   5,000.000  0.000  5,000.000  1,389.000  2,067.500  678.500  0.80  542.80 
20200100  EARTH EXCAVATION   43,279.000  -2,344.000  40,935.000  14,276.700  16,412.700  2,136.000  10.00  21,360.00 
20201200  REM & DISP UNS MATL   52,983.000  -2,891.000  50,092.000  14,748.000  14,895.600  147.600  11.70  1,726.92 
20400800  FURNISHED EXCAV   270,081.000  -5,246.000  264,835.000  235,864.000  237,544.000  1,680.000  15.77  26,493.60 
20700420  POROUS GRAN EMB SUBGR   10,734.000  6,860.000  17,594.000  17,573.800  17,594.000  20.200  30.25  611.05 
20800150  TRENCH BACKFILL   5,687.000  590.000  6,277.000  3,570.200  3,585.800  15.600  30.00  468.00 
21101505  TOPSOIL EXC & PLAC   13,753.000  519.000  14,272.000  6,552.800  7,854.800  1,302.000  12.48  16,248.96 
25000350  SEEDING CL 7   18.200  0.000  18.200  7.500  8.700  1.200  825.00  990.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
25100115  MULCH METHOD 2   1.900  20.000  21.900  19.950  20.980  1.030  3,000.00  3,090.00 
25100630  EROSION CONTR BLANKET   188,378.000  -14,000.000  174,378.000  21,127.200  26,882.300  5,755.100  0.85  4,891.84 
28000300  TEMP DITCH CHECKS   64.000  0.000  64.000  53.000  64.000  11.000  105.00  1,155.00 
44000157  HMA SURF REM 2   666.000  0.000  666.000  0.000  609.800  609.800  3.50  2,134.30 
44000200  DRIVE PAVEMENT REM   6,313.000  0.000  6,313.000  3,013.400  3,804.300  790.900  3.23  2,554.61 
44004250  PAVED SHLD REMOVAL   12,059.000  0.000  12,059.000  6,379.100  6,803.300  424.200  6.00  2,545.20 
50105220  PIPE CULVERT REMOV   3,090.000  0.000  3,090.000  977.400  1,059.900  82.500  15.00  1,237.50 
50300225  CONC STRUCT   563.400  -0.600  562.800  395.530  446.140  50.610  850.00  43,018.50 
50800105  REINFORCEMENT BARS   57,500.000  180.000  57,680.000  53,778.000  54,269.000  491.000  1.60  785.60 
50800205  REINF BARS, EPOXY CTD   118,750.000  -880.000  117,870.000  27,938.600  35,063.600  7,125.000  1.60  11,400.00 
542A1057  P CUL CL A 2 12   260.000  0.000  260.000  0.000  80.000  80.000  35.00  2,800.00 
542A1060  P CUL CL A 2 15   60.000  0.000  60.000  0.000  40.000  40.000  38.00  1,520.00 
54213660  PRC FLAR END SEC 15   11.000  0.000  11.000  3.000  5.000  2.000  420.00  840.00 
550A0340  STORM SEW CL A 2 12   3,257.000  0.000  3,257.000  1,145.100  1,150.300  5.200  35.00  182.00 
550A0360  STORM SEW CL A 2 15   1,729.000  -63.000  1,666.000  694.300  723.500  29.200  35.00  1,022.00 
55100500  STORM SEWER REM 12   257.000  0.000  257.000  2.000  18.000  16.000  12.00  192.00 
60107600  PIPE UNDERDRAINS 4   2,099.000  0.000  2,099.000  759.200  844.100  84.900  12.00  1,018.80 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
60107700  PIPE UNDERDRAINS 6   7,892.000  0.000  7,892.000  1,570.000  2,033.200  463.200  14.00  6,484.80 
60108200  PIPE UNDERDRAIN 6 SP   387.000  0.000  387.000  0.000  34.000  34.000  22.00  748.00 
60201340  CB TA 4 DIA T24F&G   78.000  0.000  78.000  38.000  40.000  2.000  1,700.00  3,400.00 
70101800  TRAF CONT & PROT SPL   1.000  0.000  1.000  0.400  0.490  0.090  200,000.00  18,000.00 
70106800  CHANGEABLE MESSAGE SN   48.000  0.000  48.000  9.300  10.300  1.000  1,240.00  1,240.00 
X9101801  DRILL & GROUT TIE BARS   0.000  80.000  80.000  14.000  17.000  3.000  27.50  82.50 
X9101901  STR REP CON DP OVER 5   0.000  60.000  60.000  36.400  60.000  23.600  165.00  3,894.00 
Total:   

$498,813.32

 