Previous Report 11/16/2010
DOT Vendor: C13130  Contract: 60363 

IL Project:      From Date: 10/19/2010
Route: FAI 55
Section: (26,26HB-1&114)R-2 To Date: 11/16/2010
Project: IM-055-6/232/255 State Job: C-91-263-97
Letting Date: 08/01/2008 Dist/Cnty: 01 - 197 (WILL )
Airport: (26,26HB-1&114)R-2 State Job: C-91-263-97
Scope: FAI-55, IL 59, ON SEIL RD, AND ON EAST FRONTAGE RD. IN
SHOREWOOD & JOLIET.

Payee:

D CONST & TJ LAMBRECHT CONST 1488 S BROADWAY  COAL CITY , IL  60416

 

 

 

 

Percent Completed:  88.45%
Contract Awarded
Amount
Additions Deductions Total Adjusted
Contract Value
Total Amount
Due to Date
25,978,708.15      2,212,008.51      1,732,394.67      26,458,321.99      23,401,671.58     
Total retainage incld this est held by IDOT:   0.00      
Total due after retainage: 23,401,671.58     
Total paid this estimate:   23,401,671.58     
     Previous payments to contractor: -22,548,990.36     
     Payment to contractor this estimate: 852,681.22     
 
          Voucher #   CC11514 Date: 11/18/2010 1 of 1 852,681.22     

----------------------------------------------------------------------------------------------------------------------------------------------     

Pay Estimate Number:  31 Total: 852,681.22     

 

 

 

 


 

 

 

Report of Resident Engineer
Completed Work-In Place
For This Estimate Only

 

PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X0326017  CONC MEDIAN SURF 5 SP   13,720.000  0.000  13,720.000  3,655.700  13,620.000  9,964.300  14.00  139,500.20 
X4021000  TEMP ACCESS- PRIV ENT   26.000  -2.000  24.000  11.000  20.000  9.000  2,200.00  19,800.00 
X4022000  TEMP ACCESS- COM ENT   13.000  0.000  13.000  6.600  13.000  6.400  2,100.00  13,440.00 
X4023000  TEMP ACCESS- ROAD   12.000  0.000  12.000  6.600  10.000  3.400  2,550.00  8,670.00 
X8420140  REM EX LU & LUM SALV   12.000  1.000  13.000  9.000  12.000  3.000  322.39  967.17 
Z0076600  TRAINEES   5,000.000  0.000  5,000.000  3,662.500  3,941.000  278.500  0.80  222.80 
20200100  EARTH EXCAVATION   43,279.000  -3,449.000  39,830.000  19,667.700  22,271.700  2,604.000  10.00  26,040.00 
21101815  COMPOST F & P 4   130,419.000  0.000  130,419.000  82,915.200  98,720.800  15,805.600  2.85  45,045.96 
25000210  SEEDING CL 2A   18.100  0.000  18.100  6.540  18.100  11.560  1,700.00  19,652.00 
25000350  SEEDING CL 7   18.200  5.900  24.100  20.200  24.067  3.867  825.00  3,190.28 
25000400  NITROGEN FERT NUTR   1,777.000  0.000  1,777.000  547.800  1,777.000  1,229.200  2.85  3,503.22 
25000500  PHOSPHORUS FERT NUTR   1,777.000  0.000  1,777.000  547.800  1,777.000  1,229.200  2.85  3,503.22 
25000600  POTASSIUM FERT NUTR   1,777.000  0.000  1,777.000  547.800  1,777.000  1,229.200  2.85  3,503.22 
25100115  MULCH METHOD 2   1.900  32.980  34.880  30.500  34.840  4.340  3,000.00  13,020.00 
25100630  EROSION CONTR BLANKET   188,378.000  -14,000.000  174,378.000  84,164.900  158,703.000  74,538.100  0.85  63,357.38 
28000200  EARTH EXC - EROS CONT   60.000  111.700  171.700  138.100  171.700  33.600  50.00  1,680.00 
28000300  TEMP DITCH CHECKS   64.000  61.000  125.000  94.000  118.000  24.000  105.00  2,520.00 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
28100107  STONE RIPRAP CL A4   210.000  131.000  341.000  310.900  318.500  7.600  60.00  456.00 
40701996  HMA PAVT FD 15 3/4   5,846.000  0.000  5,846.000  4,116.000  5,846.000  1,730.000  66.25  114,612.50 
42400200  PC CONC SIDEWALK 5   30,534.000  193.000  30,727.000  27,861.400  29,626.100  1,764.700  5.00  8,823.50 
42400800  DETECTABLE WARNINGS   238.000  0.000  238.000  18.000  138.000  120.000  25.00  3,000.00 
44000100  PAVEMENT REM   49,358.000  -2,104.000  47,254.000  35,119.000  44,673.300  9,554.300  9.00  85,988.70 
44004250  PAVED SHLD REMOVAL   12,059.000  -1,373.000  10,686.000  6,932.400  10,686.000  3,753.600  6.00  22,521.60 
48101600  AGGREGATE SHLDS B 8   4,020.000  -537.000  3,483.000  1,829.500  2,564.500  735.000  10.30  7,570.50 
48203029  HMA SHOULDERS 8   9,150.000  -2,049.000  7,101.000  5,122.000  6,347.500  1,225.500  32.20  39,461.10 
550A0050  STORM SEW CL A 1 12   939.000  0.000  939.000  815.000  917.000  102.000  35.00  3,570.00 
550A0070  STORM SEW CL A 1 15   271.000  0.000  271.000  228.600  267.600  39.000  35.00  1,365.00 
60201340  CB TA 4 DIA T24F&G   78.000  0.000  78.000  77.000  78.000  1.000  1,700.00  1,700.00 
60218400  MAN TA 4 DIA T1F CL   5.000  0.000  5.000  4.000  5.000  1.000  1,600.00  1,600.00 
60240328  INLETS TB T24F&G   39.000  1.000  40.000  38.000  40.000  2.000  1,150.00  2,300.00 
63100167  TR BAR TRM T1 SPL TAN   8.000  1.000  9.000  6.000  9.000  3.000  3,245.00  9,735.00 
70102550  TR CONT-PROT TEMP DET   2.000  0.000  2.000  0.000  2.000  2.000  11,330.00  22,660.00 
70300220  TEMP PVT MK LINE 4   6,155.000  16,278.900  22,433.900  21,723.600  22,433.900  710.300  0.20  142.06 
78000100  THPL PVT MK LTR & SYM   291.000  0.000  291.000  0.000  249.600  249.600  3.91  975.94 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
78000200  THPL PVT MK LINE 4   47,727.000  -16,600.000  31,127.000  0.000  17,942.500  17,942.500  0.75  13,456.88 
78000400  THPL PVT MK LINE 6   872.000  0.000  872.000  0.000  317.400  317.400  1.12  355.49 
78000500  THPL PVT MK LINE 8   4,595.000  856.000  5,451.000  0.000  5,451.000  5,451.000  1.56  8,503.56 
78000600  THPL PVT MK LINE 12   1,141.000  0.000  1,141.000  0.000  787.100  787.100  2.26  1,778.85 
78000650  THPL PVT MK LINE 24   182.000  0.000  182.000  0.000  120.400  120.400  4.02  484.01 
78003120  PREF PL PM TB LINE 5   8,227.000  -3,007.000  5,220.000  0.000  5,220.000  5,220.000  6.71  35,026.20 
78008200  POLYUREA PM T1 LTR-SY   619.000  -83.000  536.000  0.000  536.000  536.000  5.78  3,098.08 
78008210  POLYUREA PM T1 LN 4   26,587.000  11,429.000  38,016.000  3,948.700  32,335.300  28,386.600  0.87  24,696.34 
78008230  POLYUREA PM T1 LN 6   1,508.000  362.000  1,870.000  0.000  1,870.000  1,870.000  1.30  2,431.00 
78008250  POLYUREA PM T1 LN 12   282.000  165.000  447.000  0.000  297.800  297.800  2.62  780.24 
78008270  POLYUREA PM T1 LN 24   199.000  72.000  271.000  0.000  271.000  271.000  5.78  1,566.38 
78100100  RAISED REFL PAVT MKR   612.000  11.000  623.000  0.000  598.000  598.000  29.15  17,431.70 
78100105  RAISED REF PVT MKR BR   23.000  0.000  23.000  0.000  23.000  23.000  115.50  2,656.50 
78201000  TERMINAL MARKER - DA   10.000  1.000  11.000  9.000  10.000  1.000  60.50  60.50 
78300100  PAVT MARKING REMOVAL   34,548.000  0.000  34,548.000  17,608.100  23,491.000  5,882.900  0.98  5,765.24 
81000600  CON T 2 GALVS   615.000  4,850.000  5,465.000  1,564.200  4,269.500  2,705.300  12.58  34,032.67 
X9103802  CON AT ST 2 GALVS   0.000  235.000  235.000  0.000  235.000  235.000  22.05  5,181.75 

 

 

continued
PAY ITEM QUANTITY PAYMENT
Number Description Awarded Net of Adds/
Deducts
Total Adjusted Completed Prior Est. Completed to Date This Estimate $ Unit Price $ This Estimate
X9104501  HMA SHLD SC MATL ADJ   0.000  14,796.000  14,796.000  4,674.600  9,788.500  5,113.900  0.25  1,278.48 
Total:   

$852,681.22

 

IDOT Privacy Statement | Illinois Privacy Information | Kids Privacy | Web Accessibility  | FOIA