Invoice Archive
Contract Number
&
Estimate Numbers are listed below
Go to Current Estimate for this Contract Number
|
Contractor Invoice
Previous Report 09/15/2011
| DOT Vendor: |
C50910 |
|
Contract: |
46180 |
| IL Project: |
|
From Date: |
07/25/2011 |
| Route: |
VARIOUS |
|
|
|
| Section: |
D3 GRVD PVMT MRK RPR 12-07 |
To Date: |
09/15/2011 |
| Project: |
|
State Job: |
C-60-007-12 |
| Letting Date: |
06/17/2011 |
Dist/Cnty: |
03 - 000 (VARIOUS )
|
| Airport: |
D3 GRVD PVMT MRK RPR 12-07 |
State Job: |
C-60-007-12 |
| Scope: |
VARIOUS ROUTES.
|
|
|
|
Payee: |
ROADSAFE TRAFFIC SYSTEMS INC |
12225 DISK DR ROMEOVILLE , IL 60446
|
|
|
|
|
|
|
Contract Awarded
Amount |
Additions |
Deductions |
Total Adjusted
Contract Value |
Total Amount
Due to Date |
| 1,862,931.00 |
0.00 |
0.00 |
1,862,931.00 |
93,653.29 |
|
Total retainage incld this est held by IDOT:
|
|
|
0.00
|
| Total
due after retainage: |
|
|
93,653.29 |
| Total
paid this estimate: |
|
|
93,653.29 |
|
Previous payments to contractor: |
|
|
0.00 |
|
Payment to contractor this estimate: |
|
| 93,653.29 |
| |
|
Voucher # CC05409 | Date: 09/20/2011 |
|
1
of 1
|
93,653.29 |
|
---------------------------------------------------------------------------------------------------------------------------------------------- |
|
|
|
Pay Estimate Number: 01 |
Total: |
93,653.29 |
Report of Resident Engineer
Completed Work-In Place
For This Estimate Only
|
|
|
PAY ITEM |
QUANTITY |
PAYMENT |
|
Number |
Description |
Awarded |
Net of Adds/
Deducts |
Total Adjusted |
Completed Prior Est. |
Completed to Date |
This Estimate |
$ Unit Price |
$ This Estimate |
| X7800610 |
URETH PAVT MK LINE 4 |
615,000.000 |
0.000 |
615,000.000 |
0.000 |
244,656.000 |
244,656.000 |
0.34 |
83,183.04 |
| X7800630 |
URETH PAVT MK LINE 6 |
55,000.000 |
0.000 |
55,000.000 |
0.000 |
14,750.000 |
14,750.000 |
0.50 |
7,375.00 |
| X7800640 |
URETH PAVT MK LINE 8 |
25,000.000 |
0.000 |
25,000.000 |
0.000 |
4,127.000 |
4,127.000 |
0.75 |
3,095.25 |
|
Total: |
$93,653.29 |
|
|