CONSTRUCTION UPDATE REPORT

North Cook

Effective: 05/16/13 3:22 PM

LOCATION AND DESCRIPTION MUNICIPALITY
START DATE
EST. STOP DATE
COST (millions)
COMMENTS
25th Avenue

Resurfacing parkway restoration, and pedestrian buttons.
Franklin Park
May 2013
6/2013
$0.27
IMPACT ON TRAVEL: 63719 Project consists of sidewalk removal and replacement for ADA compliance, earth excavation, removal and disposal of unsuitable material, curb and gutter removal and replacement, solar powered flashing signage with pedestrian push buttons, pedestrian push buttons with posts, wireless communication devices, parkway restoration and all other incidental items to complete the work on 25th Avenue from Chestnut Avenue to north of King Street in the Village of Franklin Park.
Devon Avenue over I-94 (Eden's Expressway)

Sidewalk and bridge work
Lincolnwood
6/2012
5/2013
$0.565
IMPACT ON TRAVEL: 60P85 Sidewalk replacement and structural repair of concrete on the structure carrying Devon Ave. Over I-94 (Eden's Expressway) in Lincolnwood, Jefferson Twp., Cook County.
Division Street

Landscape medians with irrigation system and curb and sidewalk.
Melrose Park
7/2012
6/2013
$1.121
IMPACT ON TRAVEL: 63654 Project consists of the installation of landscaped medians with irrigation systems and planting and obelisks, installation of decorative overhead LED strand lights, installation of trees, removal and replacement of existing sidewalk, curb and gutters, driveway aprons, grass parkways and all other incidental items to complete the work on FAU Route 1026 (Division Street) from 25th Avenue to 9th Avenue in the Village of Melrose Park.
East Oakton Street

Sidewalk, street lights, landscaping
Skokie
5/2013
9/2013
$1.451
IMPACT ON TRAVEL: 63737 This project consists of removal of the existing sidewalk, the construction of decorative brick paver sidewalk, PCC sidewalk, decorative street lights, curb and gutter repair and landscaping, on East Oakton Street from Skokie Blvd (US 41) to Lowell Avenue in Skokie.
Franklin Avenue

Resurfacing, drainage, and curb and gutter.
Franklin Park
4/2013
8/2013
$1.843
IMPACT ON TRAVEL: 63811 Project consists of HMA surface removal, PCC surface removal, pavement patching, resurfacing with HMA and stone-matrix asphalt surface and binder courses, detector loop replacement, guardrail removal and replacement, concrete curb and gutter removal and replacement; drainage structure adjustments, placement of thermoplastic pavement markings and all other incidental items to complete the work on Franklin Avenue from approximately 1,500 feet east of County Line Road to Williams Drive in the Village of Franklin Park.
Golf Road

Reconstruction improvements
Rolling Meadows
5/2013
11/2013
$5.318
IMPACT ON TRAVEL: 83735 Improvements consist of reconstructing Golf Road from the I-90 viaduct to 800’ west of Algonquin Road and reconstructing New Wilke from south of Golf Road to 500' north of Golf Road, located in the City of Rolling Meadows.
Hassell Road

Roadway reconstruction, traffic signals, drainage, and landscaping.
Hoffman Estates
5/2013
5/2014
$4.586
IMPACT ON TRAVEL: 63770 This project consists of roadway reconstruction, culvert and storm sewer replacement, traffic signal modification, drainage improvements and landscaping located on Hassell Road from Barrington Road to Fairway Court in the Village of Hoffman Estates.
I-190

Resurfacing
Rosemont, Chicago
5/2013
7/2013
$4.943
IMPACT ON TRAVEL: 60T33 2.05 miles of resurfacing on I-190 from O'Hare Airport to I-90 in Rosemont and Chicago.
OTHER COMMENTS: Work is being done at nite time.
I-290 and IL 53 Ext

Bridge repairs
Palatine, Elk Grove Township, Itasca
4/2013
7/2013
$0.55
IMPACT ON TRAVEL: 60T70 Substructure repairs at various locations on I-290 and Il 53 ext. in Palatine, Elk Grove Township and Itasca in Cook and DuPage Counties.
OTHER COMMENTS: Also in DuPage
I-290/IL 53

Sign replacement safety project
Schaumburg,Rolling Meadows, Palatine, Arlington Heights
6/2012
6/2013
$1.385
IMPACT ON TRAVEL: 60P24 Sign replacement safety project along I-290/IL 53 from Thorndale Ave. to US 12 in Schaumburg, Rolling Meadows, Palatine and Arlington Heights.
I-90 at I-294

Replacement of an existing storm water pump station.
Rosemont
2/2011
3/2013
$10.354
IMPACT ON TRAVEL: 62392 Removal and replacement of an existing storm water pump station draining I-90 at I-294 in Rosemont
IL 21

Traffic signal modernizatrion at 8 intersections.
Chicago, Niles, Morton Grove
10/2012
6/2013
$1.995
IMPACT ON TRAVEL: 60R44 Traffic signal modernization along IL 21 at 8 intersections including new mast arms, controllers, LED signal heads and pavement markings.
OTHER COMMENTS: Also in Niles and Morton Grove.
IL 21

Streetscape, landscaping, and traffic signals
Niles
5/2012
6/2013
$1.954
IMPACT ON TRAVEL: 63622 Project consists of streetscape, landscaping, traffic signal modifications, lighting improvements and all other incidental items to complete the work on IL 21 between Birchwood Avenue and Monroe Street in the Village of Niles.
IL 58 (Golf Rd.)

Traffic signal modernization
Niles
10/2012
6/2013
$533
IMPACT ON TRAVEL: 60R51 Safety project consisting of traffic signal modernization on IL 58 (Golf Rd.) and other work, located at intersections with Dee Rd. and Western Ave. in Niles
IL 58 at Shales Parkway/Countryfield Lane

Intersection improvement
Elgin
5/2013
8/2013
$0.517
IMPACT ON TRAVEL: 60L43 Intersection improvement on IL 58 at Shales Parkway/Countryfield Lane in Elgin.
IL 59

Roadway lighting and landscaping
Bartlett
11/2011
5/2013
$0.498
IMPACT ON TRAVEL: 63512 This project consists of 5,092 feet of construction of roadway lighting and landscaping, from the intersection of IL Route 59 to West Bartlett Road and the intersection of West Bartlett Road and Western Avenue in Bartlett.
IL 59 @ Shoe Factory Road

Resurfacing, roadway lighting, and staorm sewers.
Hoffman Estates
8/2012
6/2013
$0.933
IMPACT ON TRAVEL: 63711 Project consists of PCC pavement and patching, storm sewer, traffic signal modification, roadway lighting and all other incidental items to complete the work at the intersection of IL 59 and Shoe Factory Road in the Village of Hoffman Estates.
IL 62 (Algonquin Road)

Construction of additional lanes, and retaining walls.
South Barrington
4/2012
4/2013
$7.661
IMPACT ON TRAVEL: 60I35 Construction of additional lanes, retaining walls, pavement reconstruction and vertical realignment on IL Route 62 (Algonquin Road) from Eastings Way to Penny Road in South Barrington.
IL 68

Sidewalk, driveway paveing, and landscaping.
Buffalo Grove
5/2013
9/2013
$0.662
IMPACT ON TRAVEL: 63614 Project consists of sidewalk construction, driveway pavement removal and replacement, landscaping and all other incidental items to complete the work on FAP Route 343 (IL 68) from Ridge Road to Huntington Lane in the Village of Buffalo Grove.
Intersection of US 41 and Old Orchard Road.

Resurfacing, storm sewer and roadway lighting, landscaping
Skokie
5/2012
5/2013
$6.302
IMPACT ON TRAVEL: 63566 Project consists of the reconstruction and resurfacing, storm sewer and drainage adjustments and installation, water main, roadway lighting, traffic signal installation and landscaping at the intersection of U.S. Route 41 and Old Orchard Road in Skokie.
Kensington Road

Reconstruction Reconstruction
Mount Prospect
4/2013
11/2013
$3.332
IMPACT ON TRAVEL: 63746 Project consists of the reconstruciton of Kensington Road from Forest Avenue to IL 83 in the Village of Mount Prospect.
Lake Street over Addison Creek

Box culvert, roadway reconstruction
Stone Park, Melrose Park
6/2011
6/2013
$3.114
IMPACT ON TRAVEL: 60H44 Replacement of a triple box culvert, roadway reconstruction, striping and other work for the structure carrying Lake Street over Addison Creek in Stone Park and Melrose Park.
Longmeadow Lane

Bridge replacement, and sewer
Hanover Park, Schaumburg Township
5/2013
9/2013
$0.567
IMPACT ON TRAVEL: 63754 Project consists of the removal and replacement of the existing bridge with a double barrel cast-in place culvert, embankment, sanitary sewer, HMA pavement, curb and gutter, sidewalk and all other incidental items to complete the work on Longmeadow Lane at the West Branch of the DuPage River (project starts 1/4 mile south of IL 19 and terminates 240’ north) in the Village of Hanover Park and Schaumburg Township.
McDonald Creek Path

Construction of new path
Arlington Heights
5/2012
6/2013
$0.263
IMPACT ON TRAVEL: 63624 Project consists of the removal and replacement of HMA path, removal and replacement of curb and gutter, retaining wall and all other incidental items to complete the work on McDonald Creek path from Hintz Road to Windsor Road in Arlington Heights.
Meacham Road

Roadway lighting
Elk Grove Village
5/2012
5/2013
$1.218
IMPACT ON TRAVEL: 63530 Project consists of installing a roadway lighting system including light poles with luminaires, metal foundations, unit duct, galvanized steel conduit, lighting controllers, landscape restoration and all other incidental items to complete the work on Meacham Road from north of Nerge Rd. to Texas Street and on Rohlwing Road from Elgin-O'Hare Expressway to Helen Lane in Elk Grove Village.
On the North side of Davis Street

Fence, landscaping and sidewalk construction
Arlington Heights
5/2012
5/2013
$0.41
IMPACT ON TRAVEL: 63615 This project consists of sidewalk construction, fence removal and replacement and landscaping on the north side of Davis Street between Pine Avenue to Bristol Lane in the Village of Arlington Heights
Palatine Road

Widening to add center median-left turn lanes and traffic signals
Hoffman Estates
5/2013
10/2013
$2.132
IMPACT ON TRAVEL: 63749 This project consists of roadway widening to add a center median, two-way left turn lane, HMA overlay and new traffic control signal with pedestrian crossing located on Palatine Road from Huntington Boulevard to Haman Road in the Village of Hoffman Estates.
Schaumburg Road

Resurfacing, sewers, lighting and traffic signals.
Schaumburg
5/2013
77/2013
$6.583
IMPACT ON TRAVEL: 63629 Project consists of pavement removal, earth excavation, curb and gutter removal and replacement, storm sewer, HMA binder and surface courses, street lighting, traffic signals, pavement marking and all other incidental items to complete the work on FAU Route 1322 (Schaumburg Road) at Barrington Road in the Village of Schaumburg.
Schoenbeck Road

Parkway restoratoin and drainage improvements
Prospect Heights
5/2013
7/2013
$0.33
IMPACT ON TRAVEL: 63731 This project consists of new sidewalk installation including drainage improvements and parkway restoration located on Schoenbeck Road from Marion Street to Palatine Road in the City of Prospect Heights.
Touhy Avenue

Bridge reconstruction
Lincolnwood and Skokie
9/2012
7/2013
$0.663
IMPACT ON TRAVEL: 60P72 Bridge deck overlay and bridge joint repair on the structure carrying Touhy Ave. over I-94 in Lincolnwood and Skokie.
US 12/45 (Mannheim Rd.) at Balmoral Ave.

Bridge work
Rosemont, Schiller Park
5/2013
9/2013
$0.609
IMPACT ON TRAVEL: 60V68 Project: Beam and bearing fabrication for the proposed reconstruction of the structures carrying US12/45 (Mannheim Rd.) at Balmoral Avenue Flyunder Ramp) from IL 19 to I-190 in Rosemont and Schiller Park.
US 12/45 (Mannheim Road)

Roadway reconstruction, lighting, and Traffic signals.
Rosemont, Des Plaines
5/2013
8/2014
$21.497
IMPACT ON TRAVEL: 60P35 1.46 miles of roadway reconstruction and widening on US 12/45 (Mannheim Rd.) from IL 72 to IL-190 lighting, traffic signal modernization, drainage and other work in Rosemont and Des Plaines.
US 12/45 (Mannheim Road)

Roadway reconstruction and widening
Rosemont, Schiller Park
5/2013
8/2013
$37.495
IMPACT ON TRAVEL: 60G37 1.65 miles of roadway reconstruction and widening of US 12/45 (Mannheim Rd.) from IL 19 to I-190, construction of Balmoral Underpass, retaining walls, lighting, traffic signal modernization, and other work in Rosemont and Schiller Park.
US 12/45 @ intersection with Perry Street

Roadway widening, resurfacing, traffic signals, landscaping.
Des Plaines
4/2012
3/2013
$1.027
IMPACT ON TRAVEL: 63616 Project consists of roadway widening, resurfacing, traffic signal installation, roadway lighting, landscaping and all other incidental items to complete the work on FAP Route 330 (U.S. Routes 12/45) at the intersection with Perry Street in Des Plaines.
US 14

Traffic signals modifications, resurfacing and widening.
Arlington Heights
4/2013
12/2013
$3.543
IMPACT ON TRAVEL: 63514 Project consists of widening and resurfacing on US 14 from Arthur Avenue to Waterman Avenue with Grade Crossing improvements at the Union Pacific Railroad, traffic signal modifications at US 14 and Arthur Avenue and resurfacing of Arthur Avenue and Davis Street, located in the Village of Arlington Heights.
US 20

Bridge painting
Elgin
4/2013
9/2013
$0.287
IMPACT ON TRAVEL: 60V88 Bridge painting at various locations on US 20 in Elgin.
OTHER COMMENTS: Also in Kane
US 20 (Lake St.)

Drainage corrections
Bloomingdale
5/2013
6/2013
$0.49
IMPACT ON TRAVEL: 60P88 Drainage corrections to US 20 (Lake St.) located east of Roselle Rd/Bloomingdale Rd. in Bloomingdale.
US 45/IL 21 (Milwaukee Ave.)

Drainage repairs
Wheelling
5/2013
7/2013
$0.39
IMPACT ON TRAVEL: 60T36 Drainage repairs to US 45/IL 21 (Millwaukee Avae.) located north of IL 68 (Dundee Rd.) in Wheeling.
Various

Landscape restoration and storm sewers
Northfield
5/2013
7/2013
$0.131
IMPACT ON TRAVEL: 63729 Project consists of excavation and sidewalk installation, storm sewer removal and replacement, curb and gutter removal and replacement, box culvert extension, temporary erosion control measures, landscape restoration and all other incidental items to complete the work at various locations throughout the Village of Northfield.
Various

Traffic signal modernization
Mt. Prospect
3/2013
8/2013
$0.755
IMPACT ON TRAVEL: 60T82 Traffic signal modernization, timing/progression and sidewalk installation at various locations in Mt. Prospect.
Various

Traffic signal modernization and sidewalk installation
Skokie
10/2012
7/2013
$1.411
IMPACT ON TRAVEL: 60R47 Traffic signal modernization and sidewalk installation at various locations in Skokie.
Various

Scour countermeasures
Northern Cook County
7/2012
4/2013
$0.683
IMPACT ON TRAVEL: 60R54 Scour countermeasures for bridges at various locations in Northern Cook County
Various locations

Relocation of existing signs and new signs.
Lincolnwood
6/2012
5/2013
$0.18
IMPACT ON TRAVEL: 63685 Project consists of two traffic calming bump outs, various new signs and the relocation of existing signs, removal and replacement markings and all other incidental items to complete the work at various locations in the Village of Lincolnwood.
Various locations

Cleaning and painting bridges.
Cook County
4/2013
9/2013
$0.616
IMPACT ON TRAVEL: 60V86 Cleaning and painting of existing steel bridges at various locations in Cook County.
Various routes

Bridge painting
Morton Grove, Libertyville, Northfield, Prospect Heights
4/2012
4/2013
$478
IMPACT ON TRAVEL: 60P58 Bridge painting of various structures on various routes in Morton Grove, Libertyville, Northfield and Prospect Heights.
OTHER COMMENTS: Also in Lake County
Viaducts crossings at Ridgland Ave./Marion St and South Boulevard and North Boulevard

Architectural enhancements and streetscape and lighting improvements.
Oak Park
5/2013
11/2013
$1.248
IMPACT ON TRAVEL: 63722 Project consists of rchitectural enhancements, streetscape and lighting improvements which includes decorative ornamental metal panels and sign panels, replacement of brick pavers with PCC sidewalk, bike rack replacement, decorative lighting posts and fixtures and all other incidental items to complete the work on FAU Route 2783 at the viaducts crossings at Ridgeland Avenue and Marion Street between South Boulevard and North Boulevard in the Village of Oak Park.
Walnut Lane

Storm sewers, curb and gugger, pcc parking lane and lighting.
Schuamburg
4/2013
11/2013
$2.517
IMPACT ON TRAVEL: 63738 Work consists of pavement removal, earth excavation, construction of storm sewers, watermain, sanitary sewer force main, full-depth HMA pavement combination curb and gutter, PCC parking lane, sidewalks, street lighting improvements and landscaping on Walnut Lane, project limits are from Bode Road to Golf Road (IL 58) located in the Village of Schaumburg.
Waukegan Road and Chestnut Avenue

Roadway widening, lighting, and resurfacing at intersection
Glenview
5/2013
6/2014
$2.954
IMPACT ON TRAVEL: 63756 Project consists of roadway widening and resurfacing, curb and gutter, sidewalks, storm sewer, water main, intersection signalization, street lighting, and parkway restoration, located at the intersection of IL Route 43 (Waukegan Road) and Chestnut Avenue in the Village of Glenview.
West Lake Avenue

sidewalk, parkway restoration
Glenview
4/2013
12/2013
$0.932
IMPACT ON TRAVEL: 63612 Project consists of sidewalk, curb and gutter, driveways, storm sewer, adjustment of drainage structures, parkway restoration and all other incidental items to complete the work on West Lake Avenue from Pfingsten Road to approximately 60’ east of Pickwick Lane in the Village of Glenview
Willow Road

Guardrail, traffic signals, retaining wall
Glenview
8/2012
5/2013
$0.126
IMPACT ON TRAVEL: 63606 Project consists of sidewalk, guardrail, modular block retaining wall, traffic signal modification, landscaping restoration and all other incidental items to complete the work on the north side of FAP Rte. 305 (Willow Road) at I-294 in the Village of Glenview.
Willow Road

Roadway reconstruction, adding lanes, bridge, lighting and drainage.
Northfield, Northbrook, Glenview, Winnetka
4/2013
10/2014
$27.234
IMPACT ON TRAVEL: 60T35 1.80 miles of roadway reconstruction, adding lanes, drainage work, bridge replacement, lighting, traffic signal modernization, and other work on Willow Rd. from IL 43 (Waukegan Road) to I-94 in Northfield, Northbrook, Glenview, and Winnetka.
Willow Road

Scour countermeasures for Willow Road over Des Plaines River.
Northfield Township
5/2013
6/2013
$0.346
IMPACT ON TRAVEL: 60V73 Scour countermeasures for the structures carrying Willow Road over the Des Plaines River in Unincorporated Northfield Township.
Willow Road

Two new box culverts.
Northbrook
5/2013
9/2013
$0.963
IMPACT ON TRAVEL: 60W04 Removal and replacement of two box culverts on Willow Road located east of Shermer Road in Northbrook.
Wolf Road over Palatine Road

Bridge replacement
Prospect Heights, Wheeling
4/2012
5/2013
$1.267
IMPACT ON TRAVEL: 60M52 Superstructure replacement, bridge beam replacement and new deck for the structure carrying Wolf Road over Palatine Road (SN 016-0680) in Prospect Heights and Wheeling.